EBK OPERATIONS MANAGEMENT
11th Edition
ISBN: 8220103630726
Author: RENDER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 13, Problem 13DQ
Question:
13. What are major limitations of using the transportation method for aggregate planning?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question
Canning Transport is to move goods from three factories (origins) to three distribution centers
(destinations). Information about the move is given below. Solve the problem using the
transportation simplex method and compute the total shipping cost.
Supply
200
Origin
A
B
100
150
Destination
Demand
X
50
Y
125
125
Shipping costs
Destination
Origin
X
Y
A
3
2
в
9
10
5
4
(Source B cannot ship to destination Z)
Question 40
Philips manufacturers multicookers in Woodlands, Pasir Ris, and Toa Payoh. Multicookers must then be transported to
meet demand in Novena, Orchard, and Bukit Timah. The table below shows the transportation costs per unit, supply,
and demand information.
Source \ Destination
Novena
Orchard
Bukit Timah
SUPPLY
Woodlands
$10
$20
$30
1000
Pasir Ris
$15
$25
$20
1500
Toa Payoh
$20
$20
$10
2000
DEMAND
1000
1800
1200
How many units should be shipped from Pasir Ris to Novena in order to minimize transportation costs?
O 500
O 1,500
O 800
O 1,200
O 1,000
Question 3 (Module 2):
In the past, Arup Mukherjee's tire dealership in Sudbury sold an average of 1,000
radials each year. In the past two years, 200 and 250, respectively, were sold in fall,
350 and 300 in winter, 150 and 165 in spring, and 300 and 285 in summer. With a
major expansion planned, Mukherjee projects sales next year to increase to 1,200
radials. What will be the demand during each season?
Chapter 13 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 20PCh. 13 - Prob. 21PCh. 13 - Prob. 22PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1VCCh. 13 - Prob. 2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question 3 List any five (5) costs prevalent in aggregate planning in the motor car industry.arrow_forwardQuestion 3. There are a number of key risks that the logistics function may face. Explain five typical immediate responses that can be used to deal with these risks.arrow_forwardQuestion 39 Philips manufacturers multicookers in Woodlands, Pasir Ris, and Toa Payoh. Multicookers must then be transported to meet demand in Novena, Orchard, and Bukit Timah. The table below shows the transportation costs per unit, supply, and demand information. Source \ Destination Novena Orchard Bukit Timah SUPPLY Woodlands $10 $20 $30 1000 Pasir Ris $15 $25 $20 1500 Toa Payoh $20 $20 $10 2000 DEMAND 1000 1800 1200 How many units should be shipped from Woodlands to Orchard in order to minimize transportation costs? O 500 O 1,200 O 1,000 O 800 O 1,500arrow_forward
- Question 4. Formulate this problem as a LP in which the objective is to minimize the total cost? What is the name of this problem? Three suppliers (S₁, S₂, S3) are used to provide four customers (T₁, T2, T3, T4) with their requirements for a particular commodity over a year. The yearly capac- ities of the suppliers and requirements of the customers are given below (in suitable units) Suppliers Capacities (per year) Customers Requirements (per year) S₁ Table 5.3 Supplier S₁ 135 56 The unit costs for supplying each customer from each supplier are given in Table 5.3 (in pounds per unit). T₁ 132 85 106 S₂ S₁ 93 T₁ T₂ T₁ T4 62 83 39 91 T₂ _a 91 89 Customer T3 97 100 T4 103 98 "A dash indicates the impossibility of certain suppliers for cer- tain depots or customers.arrow_forwardQuestion content area Part 1 Maria manages a bakery, that specializes in ciabatta bread, and has the following information on demand and costs: Ciabatta Bread Sold Per Hour (Q) Price (P) Total Cost (TC) 0 $6.00 $1.50 1 5.50 5.50 2 5.00 8.50 3 4.50 11.00 4 4.00 13.00 5 3.50 14.50 6 3.00 15.50 7 2.50 17.00 8 2.00 19.50 Part 2 a. To maximize profits, Maria should sell enter your response here loaves of ciabatta bread per hourarrow_forwardPls help ASAParrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY