Chapter 13, Problem 16P
Summary Introduction
To determine: The minimum cost using transportation method.
Introduction: Aggregate planning using transportation method helps to attain the minimum cost with the optimal plan. The major advantage of transportation method is to achieve the optimal solution using optimal plans.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Question 1
(b)
A company is considering to invest in eight projects. The estimated cost of each project, the perceived priority points, the estimated number of new jobs each project would create are provided in the Table 1.
Table 1
Project
Cost ($)
Priority Points
New Jobs
X1
X2
X3
X4
X5
X6
X7
X8
5000
4500
600
2000
6000
800
3200
2500
3176
2774
3513
2928
4607
862
3829
2708
5
1
2
1
3
1
7
2
4. The company wants to create at least 8 new jobs from these projects.
5. Only one of the two projects, i.e., X3 and X5 should be funded at this time but not both.
6. The company believes that if it decides to invest in project X7 then it should also invest in project X8, and vice versa.
[DO NOT SOLVE THE ABOVE MODEL YOU DEVELOPED IN QUESTION 1 (b).…
QUESTION THREEa) Zambia Breweries has a backlog of 250 crates of Fanta drinks at the end of December. The demand of Fanta drinks is expected to be 400 crates in January, 500 crates in February and 550 crates in March. Each worker can produce 50 crates of drinks per month with regular wage costing the company K10 000 per worker per month. Hiring cost has been calculated to be K25 000 per. Hiring cost has also been calculated to be K50 000 per worker. Backlog cost have been determined to cost the company K250 per worker. There are no cost associated with carrying the inventory.
Develop a level of production plan (aggregate plan) and determine the cost.
b) Explain why aggregate planning is necessary in production and operation management.c) Define the meaning and what happens at each of these aggregate capacity planning;i) Matching Demand approachii) Level Capacity approach.
QUESTION:
Present a closing statement explaining the benefits to Stayer of applying activity-based costing to its R&D activity for both in-house and outside charging purposes.
Chapter 13 Solutions
OPERATIONS MGMT. INSTANT ACCESS
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1VCCh. 13 - Prob. 2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Question The following describes the expenditure cycle for a hypothetical company. The company has a centralized computer system with terminals located in various departments. The terminals are networked to a computer application, and digital accounting records are hosted on a server in the data processing department. Each day, the computer in the data processing center scans the inventory records looking for items that must be replenished. For each item below its reorder point, the system creates a digital purchase order and prints two hard copies. A technician in the data center sends the purchase orders to the purchasing department clerk. Upon receipt of the purchase orders, the purchasing clerk reviews and signs them. He sends Copy 1 to the supplier and files Copy 2 in the purchases department. A few days later, the supplier ships the order and thegoods arrive at the receiving department. The receiving clerk reviews the digital purchase order from his terminal, inspects the…arrow_forwardQuestion 1At Tropico, the activities required to service a car at a dealer can be viewed as a mini-project summarised in the following table: The variability in times required to perform each activity is due to the different types, sizes, and conditions of the cars to be serviced. Round off to two decimal places were fractional.A. Draw the activity network diagram for this problem (either AON or AOA) (5 marks)B. Determine the Expected Time and Variance for each activity. (4 marks)C. Show the activity schedule (ES, EF, LS, and LF) as well as slack times. (5 marks)D. Use the ES, EF, LS, and LF from your activity schedule or table to determine the critical path for the project. (2 marks)E. What are the expected time and the variance of the project? (2 marks)F. What is the probability the project will be finished within 10 minutes? (2 marks)arrow_forwardQuestion Consider the following transactions occurring during a given fortnight. Remi's wage for his casual job is $600, paid on his bank transaction account (transaction 1); his scholarship allowance for studying is $150, paid on his bank transaction account (transaction 2); he pays a rent of $250 through a bank account transfer (transaction 3); the coupons on his portfolio of bonds pays $70 on his transaction account (transaction 4); he receives $350 in his transaction account for selling shares he had bought at $300 (transaction 5); he buys a TV worth $920 with his debit card (transaction 6). Draw Remi's balance sheet and represent how the six transactions above have affected it. Use one single balance sheet, indicate the value of the variations (sign followed by a number) and use only one name for each item [example: equity name appears only once even if several transactions are under equity] No explanations are required. How much of the funding of the TV comes from…arrow_forward
- QUESTION TWO A property development company is planning to build a block of student apartments in Lusaka’s Mass Media area. The company is yet to decide what size of block to build: a small, medium, or large. The payoffs of each size will depend on the demand for student accommodation in the area, which could be low, medium, high. The Developer estimates a 25%, 35%, and 40% chance of low, medium, and high demand, respectively. Below is a payoffs matrix (in K’000) showing the annual payoffs for the decision problem. Size of Block Market Demand Low Medium High Small 400 400 400 Medium 200 500 500 Large -400 300 800 Required: Identify the decision alternatives and uncertain conditions surrounding them? What is the optimal decision if the Developer is conservative? What is the optimal decision if the Developer is a risk taker? What is the optimal decision if the Developer wishes to minimize the Expected Opportunity Loss on the decision to…arrow_forwardQuestion 1 Part 1 Read the case below and answer true/false Case Assignment: CEC Entertainment, Inc (Chuck E. Cheese’s)For more than 35 years, Chuck E. Cheese’s has been one of the nation’s go-to venues for children’s birthday parties and rainy afternoon outings. Operating under the slogan “Where a kid can be a kid,” there are more than 575 Chuck E. Cheese’s locations in 47 states and 10 foreign countries or territories. Their goal is to provide a fun and safe environment for children to play and families to create memories, but in 2015 Chuck E. Cheese’s made improvements notfor the children, but for the parents. “Your average kid who comes to Chuck E. wants to come 11 times a year; they come three times a year. The difference between that and the 11 times a year they want to come is the mom and dad veto,” said Tom Leverton, CEO of CEC Entertainment, Inc. “What we’ve been doing over the past couple of years especially is trying to address the mom and dad…arrow_forwardIf a company wants to have a sports day at the resort where you work, with lunch followed by a dinner and casino night, with whom do they need to coordinate? Question 14 options: a) With the caterer and the sports complex manager. b) With the company contact, resort restaurant, and tennis pro. c) With the sales department, convention services, and banquet manager. d) With caterers, guest services, and the media manager.arrow_forward
- Problem 16A: ROLLED DOWN unit forecast for part C is 22, F is 2, I is 254, and L is 3.arrow_forwardQUESTION ONEProduct X is made of two units of Y and three units of Z. Y is made of one unit of A and two units of B. Z is made of two units of A and four units of C. the lead time for each material is given in table 1.Table 1. Lead time Components X 1Y 2Z 3A 2B 1C 3 Required;a) Construct the bill of material (BOM)b) If 100 units of X are required, how many units of each components areneeded? c) Develop a time-phased product structure, showing when each item shouldbe ordered. And in what quantity? d) Develop Gross Requirements Plan for each component.arrow_forwardQuestion One (maximum 1 page)Procurement of common use items (such as pens, bond paper, toner, etc) has for a long time, been characterised with inefficiency and little fundamental regard of value for money considerations. This has adversely impacted on the quality of service delivery in the public sector in Zambia. There have been public complaints on overpricing and acquisition of substandard goods and services supplied to government line ministries by suppliers and services providers.As a Procurement/Project Manager under one of the line ministries, discuss and propose a suitable contract to manage the supply of common use items in order to realise value for money. State clearly with justifications, how value for money will be realised and measured.arrow_forward
- Question: Consider the following linear program: Max Z = 2*x + 3*y subject to 3*x + 4*y >= 12 3*x + 2*y >= 9 y>= 1 x,y >= 0 The number of feasible corner points is: 0 1 2 3 None of the other answers are correct.arrow_forwardQUESTION: Although Ken Brown is the principal owner of Brown Oil, his brother Bob is credited with making the company a financial success. Bob is vice president of finance. Bob attributes his success to his pessimistic attitude about business and the oil industry. Given the information, it is likely that Bob will arrive at a different decision. What decision criterion should Bob use, and what alternative will he select? INFO NEEDED TO COMPLETE: Kenneth Brown is the principal owner of Brown Oil, Inc. After quitting his university teaching job, Ken has been able to increase his annual salary by a factor of over 100. At the present time, Ken is forced to consider purchasing some more equipment for Brown Oil because of competition. His alternatives are shown in the following table: Equipment Favorable Market $ Unfavorable Market $ Sub 100 300,000 -200,000 Oiler J 250,000 -100,000 Texan 75,000 -18,000 For example, if Ken purchases a Sub 100 and if there is a favorable market,…arrow_forwardQuestion: A renowned multinational shipping company is opening its new branch office in Lahore. You are working in the company as IT Manager. Your Chief Information Officer (CIO) have nominated you as the project manager for deploying IT infrastructure in the new office. During the project, you need to procure 20 boxes (1000 feet each) of Cat 6 Network Cables, 150 Information Outlets (I/O’s), 150 faceplates, 150 back boxes, 4 Patch panels (24 ports each), 4 Cable Managers and One communication rack. The company you are working for is a multinational company and has a very strict procurement procedure and procurement audit is mandatory at the end of the project. What steps you should follow for procurement of these items for your project. You also need to develop the Bill of Quantity (BOQ) of the products that you want to procure. Also develop a Purchase order for the same.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson