Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month aggregate plan. Demand and capacity (in units) are forecast as follows:

Chapter 13, Problem 19P, Dwayne Cole, owner of a Florida firm that manufactures display cabinets, develops an 8-month

The cost of producing each unit is $1,000 on regular time, $1,300 on overtime, and $1,800 on a subcontract. Inventory carrying cost is $200 per unit per month. There is no beginning or ending inventory in stock, and no backorders are permitted from period to period.

Let the production (workforce) vary by using regular time first, then overtime, and then subcontracting.

a) Set up a production plan that minimizes cost by producing exactly what the demand is each month. This plan allows no backorders or inventory. What is this plan’s cost?

b) Through better planning, regular time production can be set at exactly the same amount, 275 units, per month. If demand cannot be met there is no cost assigned to shortages and they will not be filled. Does this alter the solution?

c) If overtime costs per unit rise from $1,300 to $1,400, will your answer to (a) change? What if overtime costs then fall to $1,200?

Blurred answer
Students have asked these similar questions
A manager is attempting to put together an aggregate production plan for the coming nine months. She has obtained forecasts of aggregate demand for the planning horizon. The plan must deal with highly seasonal demand; demand is relatively high in months 3 and 4, and again in month 8, as can be seen below:     The company has 20 permanent employees, each of whom can produce 10 units of output per month at a cost of $6 per unit. Inventory holding cost is $5 per unit per month, and back-order cost is $10 per unit per month. The manager is considering a plan that would involve hiring two people to start working in month 1, one on a temporary basis who would work until the end of month 5. The hiring of these two would cost $500. Beginning inventory is 0.Start with 20 permanent workers. Prepare a minimum cost plan that may use some combination of hiring ($250 per worker), subcontracting ($8 per unit, maximum of 20 units per month, must use for at least three consecutive months), and overtime…
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 160 units per month. There are 10 units backlogged from before. Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory is zero. Month                                    Forecast 1                                             180 2                                             170 3                                             140 4                                             150 5                                             130 6                                             150 a. Prepare an aggregate plan with inventory and backlog allowed. Overtime and subcontracting are not allowed.b. Prepare an aggregate plan if the management decided to switch to…
AlwaysRain Irrigation, Incorporated would like to determine capacity requirements for the next four years. Currently two production lines are in place for making bronze and plastic sprinklers. Three types of sprinklers are available in both bronze and plastic: 90-degree nozzle sprinklers, 180-degree nozzle sprinklers, and 360-degree nozzle sprinklers. Management has forecast demand for the next four years as follows:   YEARLY DEMAND 1 (IN 000s) 2 (IN 000s) 3 (IN 000s) 4 (IN 000s) Plastic 90 32 44 55 56 Plastic 180 15 16 17 18 Plastic 360 50 55 64 67 Bronze 90 7 8 9 10 Bronze 180 3 4 5 6 Bronze 360 11 12 15 18 Both production lines can produce all the different types of nozzles. The bronze machines needed for the bronze sprinklers require two operators and can produce up to 12,000 sprinklers. The plastic injection molding machine needed for the plastic sprinklers requires four operators and can produce up to 200,000 sprinklers. Three bronze machines and only one…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY