CORPORATE FINANCE CUSTOM W/CONNECT >BI
CORPORATE FINANCE CUSTOM W/CONNECT >BI
11th Edition
ISBN: 9781307036633
Author: Ross
Publisher: MCG/CREATE
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 13, Problem 24QP

Project Evaluation This is a comprehensive project evaluation problem bringing together much of what you have learned in this and previous chapters. Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas 10 produce a new tine of RDSs. This will be a five-year project. The company bought some land three years ago for $7 5 million in anticipation of using it as a toxic dump site for waste chemicals, but it built a piping system to safely discard the chemicals instead. The land was appraised last week for $7.1 million. In five years, the aftertax value of the land will be $7.4 million, but the company expects to keep the land for a future project. The company wants to build its new manufacturing plant on this land; the plant and equipment will cost $40 million 10 build. The following market data on DEI’s securities is current:

Debt: 260,000 6.8 percent coupon bonds outstanding, 25 years to maturity, selling for 103 percent of par; the bonds have a$1,000 par value each and make semiannual payments.
Common stock: 9,500,000 shares outstanding, selling for $67 per share; the beta is 1.25.
Preferred stock: 450,000 shares of 5.25 percent preferred stock outstanding, selling for $84 per share and having a par value of $100.
Market: 7 percent expected market risk premium; 3.6 percent risk-free rate.

DEI use G.M. Wharton as its lead underwriter. Wharton charges DEI spreads of 6.5 percent on new common stock issues, 4.5 percent on new preferred stock issues, and 3 percent on new debit issues. Wharton has included all direct and indirect issuance costs (along with its profit) in setting these spreads. Wharton has recommended to DEI that it raise the funds needed to build the plant by issuing new shares of common stock. DEI’s tax rate is 35 percent. The project requires $1,400,000 in initial net working capital investment to get operational. Assume Wharton raises all equity for new projects externally.

  1. a. Calculate the project's initial Time 0 cash now, taking into account all side effects.
  2. b. The new RDS project is somewhat riskier than a typical project for DEI, primarily because the plant i~ being located overseas. Management has told you to use an adjustment factor of + 2 percent to account for this increased riskiness. Calculate the appropriate discount rate to use when evaluating DEI’s project.
  3. c. The manufacturing plant has an eight-year tax life, and DEI uses straight-line depreciation. At the end of the project (i.e., the end of Year 5), the plant and equipment can be scrapped for $8.5 million. What is the aftertax salvage value of this plant and equipment?
  4. d. The company will incur $7,900,000 in annual fixed costs. The plan is to manufacture 18,000 RDSs per year and sell them at $10,900 per machine; the variable production costs are $9,450 per RDS. What is the annual operating cash now (OCF) from this project?
  5. e. DEI’s comptroller is primarily interested in the impact of DEI’s investments on the bottom line of reported accounting Statement. What will you tell her is the accounting break-even quantity of ROSs sold for this project?
  6. f. Finally, DEI’s president wants you to throw all your calculations, assumptions, and everything else into the report for the chief financial officer all he want he to know is what the RDS project’s internal rate of return (IRR) and net present value (NPV) are. What will you report?

a.

Expert Solution
Check Mark
Summary Introduction

To determine: The Initial Time 0 Cash Flow.

Introduction:

The cost of equity is the yield than an investor anticipates from the security as returns for the risk they accept by spend in the specific security. Additionally it is the return an investor needs before they prefer for an alternative investment which pays higher than the correct.

The cost of debt is the effective interest rate of cost which a business earns on their current debts. Debt involves in the formation of capital structure. As the debt is considered as an deduction expenditure, the cost of debt is usually determined as after-tax cost in order to formulate similar to the cost of equity.

Answer to Problem 24QP

The Initial Time 0 Cash Flow is -$50,794,407.64

Explanation of Solution

Determine the Value of Debt

ValueofDebt=[FaceValue×BondsOutstanding×BondQuote]=[$1,000×260,000×103%]=$267,800,000

Therefore the Value of Debt is $267,800,000

Determine the Value of Common Stock

ValueofCommonStock=[SharePrice×CommonStockOutstanding]=[$67×9,500,000]=$636,500,000

Therefore the Value of Common Stock is $636,500,000

Determine the Value of Preferred Stock

ValueofPreferredStock=[SharePrice×PreferredStockOutstanding]=[$84×450,000]=$37,800,000

Therefore the Value of Preferred Stock is $37,800,000

Determine the Total Market Value

TotalMarketValue=[ValueofDebt+ValueofCommonStock+ValueofPreferredStock]=[$267,800,000+$636,500,000+$37,800,000]=$942,100,000

Therefore the Total Market Value is $942,100,000

Determine the Weight of Debt

WeightofDebt=[ValueofDebtTotalMarketValue]=[$267,800,000$942,100,000]=0.28425or28.43%

Therefore the Weight of Debt is 28.43%

Determine the Weight of Common Stock

WeightofCommonStock=[ValueofCommonStockTotalMarketValue]=[$636,500,000$942,100,000]=0.67561or67.56%

Therefore the Weight of Common Stock is 67.56%

Determine the Weight of Preferred Stock

WeightofCommonStock=[ValueofPreferredStockTotalMarketValue]=[$37,800,000$942,100,000]=0.04012or4.01%

Therefore the Weight of Preferred Stock is 4.01%

Determine the Weighted Average Floatation Costs

FloatationCosts(fT)=[(WeightDebt×RateDebt)+(WeightEquity×RateEquity)+(WeightPreferred×RatePreferred)]=[(28.43%×3%)+(67.56%×6.5%)+(4.01%×4.5%)]=[0.85%+4.39%+0.18%]=5.42%

Therefore the Weighted Average Floatation Costs is 5.42%

Determine the Amount Raised

AmountRaised=[CostofNewPlant1Weighted Average Floatation Costs]=[$40,000,00015.42%]=$42,294,407.64

Therefore the Amount Raised is $42,294,407.64

Determine the Initial Time 0 Cash Flow

InitialCashFlowYear0=[AppraisedCostofLandAmountRaised+InitialNWC]=[$7,100,000$42,294,407.64+$1,400,000]=$50,794,407.64

Therefore the Initial Time 0 Cash Flow is -$50,794,407.64

b.

Expert Solution
Check Mark
Summary Introduction

To determine: The Discount Rate of the Project.

Answer to Problem 24QP

The Discount Rate of the Project is 11.81%

Explanation of Solution

Determine the Cost of Equity using CAPM

CostofEquity(Re)=[RiskfreeRate(Rf)+Beta(β)×MarketRiskPremium(Rm)]=[3.6%+1.25×7%]=[0.036+0.0875]=0.1235or12.35%

Therefore the Cost of Equity is 12.35%

Determine the After-tax Cost of Debt

Using excel function =rate we find the pre-tax and after-tax cost of debt as,

Excel Spreadsheet:

CORPORATE FINANCE CUSTOM W/CONNECT >BI, Chapter 13, Problem 24QP , additional homework tip  1

Therefore the After-tax Cost of Debt is 4.26%

Determine the Cost of Preferred Stock

CostofEquity(Rp)=[ValueofPreferredStockPricepershare]=[($100×5.25%)$84]=[$5.25$84]=0.0625or6.25%

Therefore the Cost of Preferred Stock is 6.25%

Determine the WACC

WACC=[(Weightd×Rated)+(Weighte×Ratee)+(Weightp×Ratep)]=[(28.43%×4.26%)+(67.56×12.35%)+(4.01×6.25%)]=[1.21%+8.34%+0.25%]=9.81%

Therefore the WACC is 9.81%

Determine the Discount Rate of Project

DiscountRate=[WACC+AdjustmentFactor]=[9.81%+2%]=11.81%

Therefore the Discount Rate of Project is 11.81%

c.

Expert Solution
Check Mark
Summary Introduction

To determine: The After-Tax Salvage Value.

Answer to Problem 24QP

The After-Tax Salvage Value is $10,775,000

Explanation of Solution

Determine the Annual Depreciation

AnnualDepreciation=[CostofMachineryLifeofProject]=[$40,000,0008]=$5,000,000

Therefore the Annual Depreciation is $5,000,000

Determine the Book Value at the end of Year 5

BookValueYear5=[CostofMachinery(Depreciation×5)]=[$40,000,000($5,000,000×5)]=[$40,000,000$25,000,000]=$15,000,000

Therefore Book Value at the end of Year 5 is $15,000,000

Determine the After-Tax Salvage Value

AftertaxSalvageValue=[ScrapValue+(Tax×(BookValueScrapValue))]=[$8,500,000+(35%×($15,000,000$8,500,000))]=[$8,500,000+(35%×$6,500,000)]=[$8,500,000+$2,275,000]=$10,775,000

Therefore After-Tax Salvage Value is $10,775,000

d.

Expert Solution
Check Mark
Summary Introduction

To determine: The Annual Operating Cash Flows.

Answer to Problem 24QP

The Annual Operating Cash Flows is $13,580,000

Explanation of Solution

Determine the Annual Operating Cash Flows

OCF=[((PriceperunitVariableCost)×Units)FixedCosts×(1Tax)+(Depreciation×Tax)]=[(($10,900$9,450)×18,000)$7,900,000×(135%)+($5,000,000×35%)]=[$11,830,000+1,750,000]=$13,580,000

Therefore the Annual Operating Cash Flows is $13,580,000

e.

Expert Solution
Check Mark
Summary Introduction

To determine: The Accounting Break-Even Sales Figure.

Answer to Problem 24QP

The Accounting Break-Even Sales Figure is 8,897 units

Explanation of Solution

Determine the Accounting Break Even Sales Figure

AccountingBreakEven=[(FixedCosts+Depreciation)(PriceperunitVariableCost)]=[($7,900,000+$5,000,000)($10,900$9,450)]=[$12,900,0001450]=8,896.551or8,897units

Therefore the Accounting Break Even Sales Figure is 8,897 units

f.

Expert Solution
Check Mark
Summary Introduction

To determine: The Net Present Value (NPV) and Internal Rate of Return (IRR).

Answer to Problem 24QP

The Net Present Value (NPV) is $9,591,825.14 and Internal Rate of Return (IRR) is 18.17%

Explanation of Solution

Determine the Net Present Value (NPV) and Internal Rate of Return

Using excel spreadsheet we calculate the Net Present Value (NPV) and Internal Rate of Return as,

Excel Spreadsheet:

CORPORATE FINANCE CUSTOM W/CONNECT >BI, Chapter 13, Problem 24QP , additional homework tip  2

Excel Workings:

CORPORATE FINANCE CUSTOM W/CONNECT >BI, Chapter 13, Problem 24QP , additional homework tip  3

Therefore the Net Present Value (NPV) is $9,591,825.14 and Internal Rate of Return (IRR) is 18.17%

Conclusion

Since the net present value (NPV) is positive the project should be accepted.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Mercedes is considering upgrading their existing manufacturing line with state-of-the-art robotics. They will start with a pilot project at a single plant, and will assess profitability and potential scalability following the pilot. Your branch has been chosen as the pilot project test site, and you (the manager of the plant) need to assess your budget before launch the pilot. The installed cost of the new machinery is $200,000 and is expected to last for 10 years. The salvage value is expected to be $2.5×10,000 in today's dollars. Revenue is expected to increase by $40,000 while operating costs are expected to increase $5000 (both actual). Determine the present worth of the project, assuming an (actual) MARR of 12% , a CCA rate of 12% and a corporate tax rate of 25%
IT Software Project As a senior analyst for the company you have been asked to evaluate a new IT software project. The company has just paid a consulting firm $100,000 for a test marketing analysis.  After looking at the project plan, you anticipate that the project will need to acquire computer hardware for a cost of $450,000. The Australian Taxation Office rules allow an effective life for the computer hardware of five years. The equipment can be depreciated on a straight-line (prime cost) basis and there is no expected salvage value after the five years. Your company does not have any available space where the project can be located for five years and you anticipate to rent the required office space it would cost $65,000 per year for the life of the project. You expect that the project will need to hire 3 new software specialists at $50,000 (each specialist) per year (start in year 1) for the full five years to work on the software. The project will use a van currently owned by the…
Suppose you have been hired as a financial consultant to Defense Electronics, Incorporated (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a five-year project. The company bought some land three years ago for $3.8 million in anticipation of using it as a toxic dump site for waste chemicals, but it built a piping system to safely discard the chemicals instead. The land was appraised last week for $6.9 million on an aftertax basis. In five years, the aftertax value of the land will be $7.3 million, but the company expects to keep the land for a future project. The company wants to build its new manufacturing plant on this land; the plant and equipment will cost $33.5 million to build. The following market data on DEI’s securities are current:     Debt: 145,000 bonds with a coupon rate of 6.9 percent outstanding, 22…

Chapter 13 Solutions

CORPORATE FINANCE CUSTOM W/CONNECT >BI

Ch. 13 - Calculating Cost of Equity The Dybvig Corporations...Ch. 13 - Prob. 2QPCh. 13 - Calculating Cost of Debt Shanken Corp. issued a...Ch. 13 - Calculating Cost of Debt For the firm in the...Ch. 13 - Calculating WACC Mullineaux Corporation has a...Ch. 13 - Taxes and WACC Miller Manufacturing has a target...Ch. 13 - Finding the Capital Structure Farnas Llamas has a...Ch. 13 - Book Value versus Market Value Filer Manufacturing...Ch. 13 - Calculating the WACC In the previous problem,...Ch. 13 - Prob. 10QPCh. 13 - Finding the WACC Given the following information...Ch. 13 - Finding the WACC Titan Mining Corporation has 8.7...Ch. 13 - SML and WACC An all-equity firm is considering the...Ch. 13 - Calculating Flotation Costs Suppose your company...Ch. 13 - Calculating Flotation Costs Southern Alliance...Ch. 13 - WACC and NPV Och, Inc., is considering a project...Ch. 13 - Prob. 17QPCh. 13 - Flotation Costs Goodbye, Inc., recently issued new...Ch. 13 - Calculating the Cost of Equity Floyd Industries...Ch. 13 - Firm Valuation Schultz Industries is considering...Ch. 13 - Prob. 21QPCh. 13 - Flotation Costs and NPV Photochronograph...Ch. 13 - Flotation Costs Trower Corp. has a debt-equity...Ch. 13 - Project Evaluation This is a comprehensive project...Ch. 13 - Prob. 1MCCh. 13 - Prob. 2MCCh. 13 - Go to www.reuters.com and find the list of...Ch. 13 - You now need to calculate the cost of debt for...Ch. 13 - You now have all the necessary information to...Ch. 13 - You used Tesla as a representative company to...
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License