Textbook Question
Chapter 13, Problem 3P
A construction project has the following network and activity times:
- a. Make a forward pass and a backward pass on the activity times.
- b. Find the slack for each activity.
- c. Prepare a Gantt chart for this project.
- d. Activity D will be delayed by one day. What effect will this have on the project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
PERT could be used to answer which of the following managementquestions?
A. Can we delay a particular activity and still finish the project on time?B. When are we scheduled to start a particular activity?C. Which activities should be finished on time?D. All of the above.
What is the optimal plan for expediting some activities so as to minimize the total cost of performing the project within the deadline?
The activities related to a project with their immediate predecessors have been provided in the table. You are required to perform a critical path analysis by computing the slack time.
Chapter 13 Solutions
OPER MGMT IN SUPPLY CHAIN ACCESS CARD
Ch. 13 - How, precisely, does project scheduling differ...Ch. 13 - How would you, after the fact, audit a project to...Ch. 13 - Prob. 3DQCh. 13 - Contrast and compare CPM and PERT as...Ch. 13 - Define the terms critical path, ES, and LF.Ch. 13 - What is the management significance of finding the...Ch. 13 - Prob. 7DQCh. 13 - What is meant by the need to make trade-offs...Ch. 13 - Why are a forward pass and a backward pass needed...Ch. 13 - What is the definition of the earliest and latest...
Ch. 13 - A public accounting firm requires the following...Ch. 13 - The following activities are required in starting...Ch. 13 - A construction project has the following network...Ch. 13 - A plant start-up is based on the following...Ch. 13 - An entrepreneur is starting a new business. The...Ch. 13 - Prob. 6PCh. 13 - Construction of a building is based on the...Ch. 13 - The professor from problem 6 is considering...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Slack time for each of the activities is? (Activity A-G)arrow_forwardA Gantt chart is a project schedule that superimposes project activities on a time line. Part 2 True Falsearrow_forwardThe following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A -- 4 B -- 3 C A 2 D B 7 E C, D 4 F B 5 G E,F 4 What is the minimum possible time required for completing the project?arrow_forward
- The following statement about a noncritical activity is FALSE: A. Delaying it beyond its slack will cause the delay of the whole project.B. It can be delayed.C. Both A and B.D. Neither A nor B.arrow_forward27. Consider a project with six activities: G, B, C, D, E, and F. Assume G and F can be started as soon as the project is kicked off. B can start as soon as G is completed, C can start as soon as both G and F are completed. D will start as soon as both B and C are completed. E will start as soon as D finishes. Which of the following choices is the correct collection of immediate precedence relationships in the project network? G--> B, F--> C, B --> D, C--> E, D--> E, F--> D G--> B, G--> C, B --> D, C--> D, D--> E, F--> C G--> B, G--> C, B --> D, C--> D, D--> E, D--> F None of choices G--> B, F--> C, B --> D, C--> D, D--> E, F--> D G--> B, G--> C, B --> D, C--> D, D--> E, D--> Farrow_forwardINSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward and backward passes, calculate total slack for each activity, identify the critical path, identify the total project length (or how long it will take to complete the project) based on days, calculate free slack for appropriate activities, and create the Gantt chart. When creating the Gantt chart, you must include slack into the schedule.arrow_forward
- Consider a project consisting of the following tasks: Task Duration (weeks) Dependencies A 6 – B 5 – C 1 A D 8 B E 3 B F 2 C, D G 7 E, F (a) Draw an activity-on-arc (AOA) graph for this project, including task durations. (b) Identify the critical path, and show your working.arrow_forwardTo help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. A project network with 10 activities and 13 directed arcs is shown. Activity Start is connected to activity A and to activity B. Activity A is connected to activity C and to activity D. Activity B is connected to activity E. Activity C is connected to activity H. Activity D is connected to activity F and to activity G. Activity E is connected to activity F and to activity G. Activity F is connected to activity H. Activity G is connected to activity Finish. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. The following table lists the activity time estimates (in weeks) for each activity. Activity Optimistic Most Probable Pessimistic A 4 5 6 B 2.5 3 3.5 C 5 6 7 D 5 5.5 9 E 5 7 9 F 2 3 4 G 9 11 13 H 7 8 15 Based only on the critical path, what is the estimated probability…arrow_forwarda) Draw a schedule showing the work package critical path and duration. b) Assume the wor kpackage has to be completed within 44 weeks.Calculate the most costeffective way of completing the work package within this time, giving the costincrease associated with this crash sequence. c) Discuss the main factors likely to be considered by the project manager whenconsidering time– cost trade-offs and time–quality trade-offs as ways of reducingthe overall time required to complete a project or work package.arrow_forward
- Explain how project scheduling software may help. Please explain my question.arrow_forwardThe following is NOT one of the advantages of CPM and PERT:a) Straightforward concept and not mathematically complex.b) Graphical networks help highlight relationships among project activities.c) Critical path & slack time analyses pinpoint activities that need tobe closely watched.d) Project documentation and graphs point out who is responsible for variousactivities.e) Precedence relationships must be specified and networked together.f) Applicable to a wide variety of projects.arrow_forward. True/False Statements (Tick the correct option) Selection of the critical path in network activity diagram for any project, is always focused onresult of the minimum time duration of the critical activities [ True / False ] Suppose, we have total 03 activities in the project “X”; namely L, M and N respectively. An activity “M” is the immediate successor of the activity “L”, while the activity “M” is the immediate predecessor for the activity “N”. According to this scenario, an activity “M” will be the last activity of the project “X” in the network activity diagram [True / False ] The dummy activity consumes both time and resources [True / False ] Towards the optimal solution through stepping stone method, when degeneracy problem is occurred, the next step is to focus on searching lowest value on the independent position in a non-allocated cells [True / False ] Hungarian algorithm, first convert any given assignment matrix into row reduction matrix [True / Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY