Chapter 13, Problem 8P
The professor from problem 6 is considering reducing the time for completion of the project. He can hire a teaching assistant (TA) to help with the new course, but this will cost additional money. The TA can help reduce the times only for activities A. D, and C. In each case the TA can reduce the time required by one day for $150 and two days for $300.
- a. Which activity should the TA perform to reduce the project completion time by one day?
- b. Can the network be crashed by two days in total? Explain why or why not?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
For conducting a project seven activities should be performed but maximum availablemanpower is 17. Task duration and manpower requirement is given below. Project managersaid, “It is possible to complete the project without leveling the manpower". Evaluate thestatement of the PM. (Justified or Not-Justified)
7. For early completion of the project, emphasis on which of the following activities will be helpful?
Group of answer choices
An activity with the highest level of resource allocation
An activity with zero slack time
An activity with the highest time
An activity with the highest slack time
The company decided that the project in the previous problem had to be expedite in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.
Activity
Duration (Days)
Expedited Time (Days)
Normal Direct Cost ($)
Expedited Direct Cost ($)
A
32
26
200
500
B
21
20
300
375
C
30
30
200
200
D
45
40
200
800
E
26
20
700
1,360
F
28
24
1,000
1,160
G
20
18
400
550
What is the optimal time to complete the project?
What is the optimal project cost?
Chapter 13 Solutions
OPER MGMT IN SUPPLY CHAIN ACCESS CARD
Ch. 13 - How, precisely, does project scheduling differ...Ch. 13 - How would you, after the fact, audit a project to...Ch. 13 - Prob. 3DQCh. 13 - Contrast and compare CPM and PERT as...Ch. 13 - Define the terms critical path, ES, and LF.Ch. 13 - What is the management significance of finding the...Ch. 13 - Prob. 7DQCh. 13 - What is meant by the need to make trade-offs...Ch. 13 - Why are a forward pass and a backward pass needed...Ch. 13 - What is the definition of the earliest and latest...
Ch. 13 - A public accounting firm requires the following...Ch. 13 - The following activities are required in starting...Ch. 13 - A construction project has the following network...Ch. 13 - A plant start-up is based on the following...Ch. 13 - An entrepreneur is starting a new business. The...Ch. 13 - Prob. 6PCh. 13 - Construction of a building is based on the...Ch. 13 - The professor from problem 6 is considering...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Widgetco is making a prototype of a new product. The productconsists of two subassemblies. Before building either subassembly, the firm must purchaseraw materials and train workers. Before the subassemblies can be combined, subassembly2 must be inspected. The following table describes the project:Activity Description Requires Duration (Days)A Train workers 6B Purchase materials 9C Make subassembly 1 A,B 8D Make subassembly 2 A,B 7E Inspect subassembly 2 D 10F Combine subassemblies C, E 12G Subassembly 2 safety report E 6How quickly can Widgetco complete this project?(a) Define decision variables.(b) Write a suitable LP problem formulation.arrow_forwardWhat does Goldratt's Critical Chain explain? Select one: a. Theory of Constraints for better management of scope and development of more realistic work breakdown structures b. The principal foundation on the critical path method which is the longest path from start to finish, it indicates the minimum time required to complete the project. c. All of the above d. The principal foundation on the critical path method which is the longest path from start to finish, it indicates the maximum time required to complete the project. e. The Theory of Constraints for better management of schedules through fixing of bottlenecks in order to improve the throughput of overall system. This was the foundation to Critical Chain Project Management Method.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G Harrow_forward
- 4. Explain the risks associated with leveling resources, compressing or crashing projects, and imposed durations or “catch-up” as the project is being implemented.arrow_forwardRecently, you were assigned to manage a project to remodelthe seminar room for your company. You have constructed anetwork diagram depicting the various activities in the project(Figure 7.13). In addition, you have asked your team to estimatethe amount of time that they would expect each of the activitiesto take. Their responses are shown in the following table: a. What is the expected completion time of the project?b. What is the probability of completing the project in 21 days?c. What is the probability of completing the project in 17 days?arrow_forwardA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?arrow_forwardAssume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000’s) TBC 1 2 3 4 5 Task 1 40 10 15 10 5 Task 2 23 6 10 5 2 Task 3 15 9 4 2 Task 4 6 3 3 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000’s) 1 2 3 4 Task 1 15 21 12 6…arrow_forwardThe client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S) Immediate Predecessors A 2 10 2 0 None B 3 15 2 23 A C 5 25 4 30 B D 3 20 1 24 C E 6 30 4 45 C F 1 5 1 0 E G 7 35 6 50 F H 10 50 7 80 D, Garrow_forward
- Please, I need help because I have no idea how to do any of these. 11. Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Develop the project network. For question number 12, you need to refer to question number 11. Also the first picture is for #11 and second picture(image) is for #12 12. Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows: a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?arrow_forwardHi, I need help answering the last question. Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 3 $800 $1,200 - B 6 5 $300 $450 - C 6 5 $550 $775 - D 3 2 $750 $950 A E 6 3 $1,350 $2,250 C F 5 3 $675 $875 B What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)arrow_forwardThe university administration would like to add some additional parking locations. To make everyone happy, they would like each building to be within a 5 minute walk of one set of new parking spaces (the spaces will be added in blocks of 10 parking spaces). The university is considering six locations for the new parking spaces, but would like to minimize the overall cost of the project. In addition to the walking time requirement, the university would like to add at least 40 new parking spaces (at least 4 blocks of 10). To help with the decision, the management science department formulated the following linear programming model: Min 365x1 + 410x2 + 405x3+ 410x4 + 355x5 + 445x6s.t. x1 + x2 + x5 + x6 ≥ 1 {Residence Hall A constraint}x1 + x2 + x3 ≥ 1 {Residence Hall B constraint}x4 + x5 + x6 ≥ 1 {Science building constraint}x1 + x4 + x5 ≥ 1 {Music building constraint}x2 + x3 + x4 ≥ 1 {Math building constraint}x3 + x4 + x5 ≥ 1 {Business building constraint}x2 + x5 + x6 ≥ 1…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY