Summary Introduction
To develop: A gross requirements plan for item C.
Introduction:
Gross requirements plan:
The gross requirements plan is the plan where the independent and dependent demand for a product or a component before the on-hand inventory and the
b)
Summary Introduction
To develop: A net requirements plan for item C.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the following product structure (bill of material).
One hundred and fifty (150) units of Product A are needed in week 10. Assuming no on-hand inventory of A exists, explode the bill of material, and use the following information to construct a net requirements plan for all the items. You must use the template provided by the instructor and provide all the information needed on the template. There are no scheduled receipts for all the items.
Item
On-hand
Inventory
Lead time
(weeks)
A
0
2
B
20
2
C
10
1
D
0
3
E
5
1
F
10
3
Item:
LT=
1
2
3
4
5
6
7
8
9
10
11
12
Gross Requirements
Scheduled Receipts
Projected on Hand
Net Requirements…
The BOM for product A is given below:Assume the master schedule calls for 200 units of product A in week 5 and 250 units in week 6. a. Develop a materials plan for this product. b. What actions should be taken immediately? c. Project the inventory ahead for each part. d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?
Product M is made of two units of N and two of P. N is made of two units of R and four units of S. R is made of one unit of S and three units of T. P is made of two units of T and four units of U.
a. Show the bill-of-materials (product structure tree).
b. If 100 Ms are required, how many units of each component are needed?
c. Show both a single-level parts list and an indented parts list.
Chapter 14 Solutions
PRIN OF OPS MGMT W/MYOMLAB&ACCESS BADGE
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. A. Design a product structure noting the quantities for each item and show the low-level coding. B. Determine the gross quantities needed of each item if you are to assemble 50 brackets. C. Compute the net quantities if there are 25 of the base and 100 of the clamp in stock.arrow_forwardProduct A consists of subassemblies B and C. Subassembly B requires two parts of D and one part of E. Subassembly C requires one part of D and one part of F.a. Draw a product structure tree (BOM) for this product.b. How many parts are needed to make 300 units of finishedproduct?arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Spring Subscript left parenthesis 2 right parenthesisSpring(2) II Housing Subscript left parenthesis 1 right parenthesisHousing(1) III Casting Subscript left parenthesis 2 right parenthesisCasting(2) IV Shaft Subscript left parenthesis 2 right parenthesisShaft(2) Bracket Base(1) Clamp(1) Handle(1) Clamp(4) Bearing(1) Handle(1) Casting(2) IIIIIIIV Part 3 b) Determine the…arrow_forward
- As the production planner for Xiangling HuProducts, Inc., you have been given a bill of material fora bracket that is made up of a base, two springs, and fourclamps. The base is assembled from one clamp and twohousings. Each clamp has one handle and one casting. Eachhousing has two bearings and one shaft. There is no inventoryon hand. a) Design a product structure noting the quantities for eachitem and show the low-level coding.b) Determine the gross quantities needed of each item if youare to assemble 50 brackets.c) Compute the net quantities needed if there are 25 of thebase and 100 of the clamp in stock.arrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearing and 2 shaft. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Bracket II Spring Subscript left parenthesis 1 right parenthesis III Clamp Subscript left parenthesis 3 right parenthesis IV Bearing Subscript left parenthesis 2 rightarrow_forward
- As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. This exercise contains only parts b and c. Part 2 The product structure is as follows: Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(1) Shaft(1) Clamp(4) Bearing(2) Handle(1) Casting(1) Part 3 b) Determine the gross quantities needed of each item if you are to assemble 100 brackets. Base: enter your response here units (enter your response as a whole number). Spring: enter your response here units (enter your response as a whole number). Clamp: enter your response here units (enter your response as a whole number). Housing: enter your response here units (enter your…arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 3 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. This exercise contains only parts b and c. Part 2 The product structure is as follows: Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(2) Shaft(2) Clamp(3) Bearing(2) Handle(1) Casting(1) Part 3 b) Determine the gross quantities needed of each item if you are to assemble 125 brackets. Base: 33 units (enter your response as a whole number). Spring: enter your response here units (enter your response as a whole number). Clamp: enter your response here units (enter your response as a whole number). Housing: enter your response here units (enter your response as a whole…arrow_forwardExplain the significance of a Requirements Management Plan (RMP) in complex projects. How does it ensure requirements are well-defined and properly managed?arrow_forward
- The three tables above show the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the net requirement of part A in Week 4?arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forwardDiscuss Material Requirement Planning -MRP with the aid of a diagram What is a Bill-of-Material?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY