Textbook Question
Chapter 14, Problem 4P
Your boss at Xiangling Hu Products, Inc., has just provided you with the
a) Prepare the time-phased product structure for the bracket.
b) In what week do you need to start the castings?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand.
Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 12.The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing
(3weeks), handle (2weeks), casting (4weeks), bearing (1 week), and shaft (1 week).
Part 3
b) In what week do you need to start the castings?
The castings need to be started in week
enter your response here
(enter
your response as a whole
number).
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base,
2
springs,
and
4
clamps. The base is assembled from
1
clamp
and
1
housing.
Each clamp has
1
handle and
1
casting.
Each housing has
2
bearings
and
1
shaft.
There is no inventory on hand.
This exercise contains only parts b and c.
Part 2
The product structure is as follows:
Bracket
Base(1)
Clamp(1)
Handle(1)
Casting(1)
Spring(2)
Housing(1)
Shaft(1)
Clamp(4)
Bearing(2)
Handle(1)
Casting(1)
Part 3
b) Determine the gross quantities needed of each item if you are to assemble
100
brackets.
Base:
enter your response here
units
(enter
your response as a whole
number).
Spring:
enter your response here
units
(enter
your response as a whole
number).
Clamp:
enter your response here
units
(enter
your response as a whole
number).
Housing:
enter your response here
units
(enter
your…
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base,
2
springs,
and
3
clamps. The base is assembled from
1
clamp
and
2
housings.
Each clamp has
1
handle and
1
casting.
Each housing has
2
bearings
and
2
shafts.
There is no inventory on hand.
This exercise contains only parts b and c.
Part 2
The product structure is as follows:
Bracket
Base(1)
Clamp(1)
Handle(1)
Casting(1)
Spring(2)
Housing(2)
Shaft(2)
Clamp(3)
Bearing(2)
Handle(1)
Casting(1)
Part 3
b) Determine the gross quantities needed of each item if you are to assemble
125
brackets.
Base:
33
units
(enter
your response as a whole
number).
Spring:
enter your response here
units
(enter
your response as a whole
number).
Clamp:
enter your response here
units
(enter
your response as a whole
number).
Housing:
enter your response here
units
(enter
your response as a whole…
Chapter 14 Solutions
PRIN OF OPS MGMT W/MYOMLAB&ACCESS BADGE
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z,70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units ofcomponent C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and areexpected to arrive in week 4. Lead times are two weeks for E and C, and one week for the othercomponents. Assume lot-for-lot ordering except for D, where multiples of 40 must be used.arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamps and 2 housings. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. This exercise contains only parts b and c. The product structure is as follows: Bracket Base(1) Clamp(2) Handle(1) Casting(2) Spring(1) Housing(2) Shaft(2) Clamp(3) Bearing(1) Handle(1) Casting(2) b) Determine the gross quantities needed of each item if you are to assemble 50 brackets. Base: ? Spring: ? Clamp: ? Housing: ? Handle: ? Casting: ? Bearing: ? Shaft: ?arrow_forwardA table is assembled using three components, as shown in the accompanying product structure tree.The company that makes the table wants to ship 100 units at the beginning of day 4, 150 units atthe beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections arescheduled at the beginning of day 2. There are 120 legs on hand. There are 60 braces on hand. Leadtimes (in days) for all items are shown in the following table. Prepare a material requirements planusing lot-for-lot ordering.arrow_forward
- Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of Jhave been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5.Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 unitsof B and 20 units of J now on hand. Lead times are two weeks each for E and B, and one week for J.E a. Prepare a material requirements plan for component J.b. Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned-order releasesthrough week 3 have all been executed. How many more Bs and Js will be on hand in week 6?arrow_forwardThe three tables above show the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the net requirement of part A in Week 4?arrow_forwardEach A (finished product) requires 1 of component B and 2 of component C. Each B requires 2 of part D and 1 of part E and each C requires 1 of part D and 1 of part F.If the demand for product A is 50 units., and there are 15 units of B on hand and 50 units of C, how many units of Part D will be needed?arrow_forward
- Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components a re bracket (I week), base (1 week), spring ( I week), clamp (I week), housing (2 weeks), handle (I week), casting (3 weeks), bearing (I week), and shaft (1 week).a) Prepare the time-phased product structure for the bracket.b) In what week do you need to start the castings?arrow_forwardA partially completed inventory record for the motor sub-assembly is shown in Figure 11.39.a. Complete the last three rows of the record by using theL4L rule.b. Complete the last three rows of the record by using thePOQ rule with P = 2. c. Complete the last three rows of the record by using thePOQ rule with P = 2.d. If it costs the company $1 to hold a unit in inventory fromone week to the next, and the cost to release an order is$50, which of the lot sizing rules used above will providethe lowest inventory holding + order release cost?arrow_forwardA partially completed inventory record for the motor sub-assembly is shown in Figure 11.39. a. Complete the last three rows of the record by using the L4L rule. b. Complete the last three rows of the record by using the POQ rule with P = 2. c. Complete the last three rows of the record by using the POQ rule with P = 2. d. If it costs the company $1 to hold a unit in inventory from one week to the next, and the cost to release an order is $50, which of the lot sizing rules used above will provide the lowest inventory holding + order release cost?arrow_forward
- Three products go through a two step process of pre-production and final assembly. The processing time is given in hours for each of the three products through the two processes is given in the table below. Using Johnson's rule, determine the sequence of the products through the production facility, and the completion time for pre-production and final assembly for the three products. Product Pre-Production Final Assembly A 4.1 3.6 B 2.5 3.8 C 4.9 4.3 Production sequence (letters only, no blanks or other separators): Pre-production end time (one decimal place): Final assembly completion time (one decimal place):arrow_forwardWhat involves scheduling several different models of a product to be produced over a given day or week on the same line in a cyclical fashion?arrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY