Textbook Question
Book Icon
Chapter 14, Problem 4P

Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket in Problem 14.3. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1 week), casting (3 weeks), bearing (1 week), and shaft (1 week).

a) Prepare the time-phased product structure for the bracket.

b) In what week do you need to start the castings?

Blurred answer
Students have asked these similar questions
As the production planner for Xiangling Hu​ Products, Inc., you have been given a bill of material for a bracket that is made up of a​ base, 2 ​springs, and 4 clamps. The base is assembled from 1 clamp and 2housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. Your boss at Xiangling Hu​ Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 12.The lead times for the components are bracket​ (1 week), base​ (1 week), spring​ (1 week), clamp​ (1 week), housing ​(3​weeks), handle ​(2weeks​), casting ​(4​weeks), bearing​ (1 week), and shaft​ (1 week). Part 3 b) In what week do you need to start the​ castings?   The castings need to be started in week enter your response here ​(enter your response as a whole number​).
As the production planner for Xiangling Hu​ Products, Inc., you have been given a bill of material for a bracket that is made up of a​ base, 2 springs​, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand.   This exercise contains only parts b and c. Part 2 The product structure is as​ follows:   Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(1) Shaft(1) Clamp(4) Bearing(2) Handle(1) Casting(1) Part 3 ​b) Determine the gross quantities needed of each item if you are to assemble 100 brackets.   ​Base: enter your response here units ​(enter your response as a whole number​). ​Spring: enter your response here units ​(enter your response as a whole number​). ​Clamp: enter your response here units ​(enter your response as a whole number​). ​Housing: enter your response here units ​(enter your…
As the production planner for Xiangling Hu​ Products, Inc., you have been given a bill of material for a bracket that is made up of a​ base, 2 springs​, and 3 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand.   This exercise contains only parts b and c. Part 2 The product structure is as​ follows:   Bracket Base(1) Clamp(1) Handle(1) Casting(1) Spring(2) Housing(2) Shaft(2) Clamp(3) Bearing(2) Handle(1) Casting(1) Part 3 ​b) Determine the gross quantities needed of each item if you are to assemble 125 brackets.   ​Base: 33 units ​(enter your response as a whole number​). ​Spring: enter your response here units ​(enter your response as a whole number​). ​Clamp: enter your response here units ​(enter your response as a whole number​). ​Housing: enter your response here units ​(enter your response as a whole…

Chapter 14 Solutions

PRIN OF OPS MGMT W/MYOMLAB&ACCESS BADGE

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY