Using Enumeration Method - list all paths and total duration.
Activity
Predecessor
Normal time
Normal cost
Crash time
Crash cost
Max Crash Time
Slope
A
-
12
$200
9
$350
B
A
8
$300
8
$300
C
A
9
$250
7
$450
D
B
6
$400
5
$600
E
B,C
5
$150
4
$225
F
C
10
$500
9
$650
G
D,E,F
8
$400
6
$900
How many doors will be needed to the entrance of the transit center if the hourly passenger volume is expected to be 8,750? Design for a LOS C. Assume each door is 2.5 ft wide. Round up your answer to the nearest integer (i.e. door).
The hourly passenger volume is expected to be 8,750. The transit center is being design with 6, 2.5 ft doors. What is the expected level of service of the doorways?
Chapter 14 Solutions
Traffic and Highway Engineering
Knowledge Booster
Similar questions
- Design Hourly Volume (DHV) is the projected hourly volume that is used for design. This volume is taken as a percentage of choose one of the following the average annual traffic the average weekley traffic the average daily traffic none of the given choicesarrow_forwardFind the station kilometer of point B with curb radii of R1 and R2 according to the information given.arrow_forwardUsing Enumeration Method - list all paths and total duration. Use the chart provided for the infomation needed Activity Predecessor Normal time Normal cost Crash time Crash cost Max Crash Time Slope A 5 $200 4 $350 B A 8 $220 8 $220 C B 6 $250 4 $650 D A 9 $500 5 $600 E A,C 10 $150 9 $500 F E 10 $500 9 $650 G D,F 8 $400 6 $900arrow_forward
- There are five machines located at the points (0, 0), (2, 0), (0, 2), (2, 3) and (4,3) respectively. A repair shop is planned in the facility. The foreman claims that for any number of expected repair trips between these machines and the repair shop, the optimal location of the new facility can never be at the location (2,1). State whether this claim is true or false.arrow_forwardThe through movement passenger car equivalents (pcphpl) for each approach of Vine and Maple Streetsintersections obtained from a traffic survey as shown in the following diagram. Vine Street for NSmovements 1s 48 ft wide and Maple Street for EW movements is 60 ft wide. There are two throughmovement lanes and one left-tum lane in each approach. The yellow times for Vine Street and MapleStreet through movement and left-tum phases are 4 second and 3 seconds per g_hase, respectively. TheAll-red for each phase is 2.0 seconds and the ost time is 5 seconds per phase. Pedestrian walkmgspeed is 3.5 ft/sec. Assuming equal distribution of traffic on the two through-movement lanes in eachapproach and a saturation flow rate of 1,900 pcphpl. A 3-phase fixed timing signal plan (namely, aprotected left-turn phase, a NS phase, and an EW phase) is suggested.I) In the diagram, the through movement volume is for 2 lanes and left tum volume is for one-lane.2) Determine one N-S or E-W left tum phase on the…arrow_forward(a) Calculate total of duration to complete the shopping complex project.(b) Show and state the critical path on the network.arrow_forward
- Draw the cross-section for a typical long roadway tunnel. The question above is for my transportation engineering class. That's the only information that was provided for the question. Thank you so much in advance! 2arrow_forwardFrom the following network data, determine the criticalpath, starting and finishing times, and TFs and FFs.arrow_forwardGive 1 concrete example of the following: Trip Generation Trip Distribution Modal Split Traffic Assignmentarrow_forward
- Using the following trip distribution matrix and road network: a) Identify the minimum path between each TAZ pair. b) Estimate the traffic flow on each linkarrow_forwardThe table below shows data obtained in a travel time study on a section of highway using the moving-vehicle technique. Estimate (a) the travel time and (b) the volume in each direction at this section of the highway. Choices for northward: Tn = 5.9, 6.2, 5.2, 4.9 Vn = 535, 505, 514, 555 Choices for southward: Ts = 6.2, 5.2, 4.9, 5.9 Vs = 555, 535, 505, 517 Help me pls. I will upvote, Badly need your help. Thankyou :)arrow_forwardWrite the three important timing facts that can be determined from a CPM Network?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningSolid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,