EBK PRINCIPLES OF OPERATIONS MANAGEMENT
10th Edition
ISBN: 8220102744059
Author: HEIZER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 27P
Grace Greenberg, production planner for Science and Technology Labs, in New Jersey, has the master production plan shown below:
Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Develop an ordering plan and costs for Grace, using these techniques:
a) Lot-for-lot.
b) EOQ.
c) POQ.
d) Which plan has the lowest cost?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
M. de Koster, of Rene Enterprises, has the master production plan shown here: Lead time = I period; setup cost= $200; holding cost = $10 perweek; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:a) Lot-for-lot. b) EOQ.c) POQ. d) Which plan has the lowest cost?
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week
8.
Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
Item
Lead Time
On-Hand Inventory
Components
Stepper
2
20
A(2),
B(2),
C(2)
A
1
10
D(1),
F(2)
B
2
20
E(2),
F(3)
C
2
10
D(2),
E(1)
D
1
15
E
2
5
F
2
20
c) Develop a net material requirements plan for F (enter your responses as whole numbers).
Week
Lead Time
Item
1
2
3
4
5
6
7
8
(weeks)
F
Gross req
2
On hand
Net req
enter your response here
enter your response here
Order receipt
enter your response here
enter your…
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 10. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
Item
Lead Time
On-Hand Inventory
Components
Stepper
2
10
A(2),
B(2),
C(1)
A
1
10
D(1),
F(2)
B
2
20
E(1),
F(3)
C
3
10
D(2),
E(3)
D
2
15
E
2
5
F
2
20
c) Develop a net material requirements plan for F (enter your responses as whole numbers).
Week
Lead Time
Item
3
4
5
6
7
8
9
10
(weeks)
F
Gross req
enter your response here
enter your response here
2
On hand
enter your response here
enter your response here
Net req
enter your response here
enter your response here
Order…
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Assume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forwardDescribe the link between inventory levels and production schedule?arrow_forwardExplain the economic order quantity (EOQ) and its impact on cost of operations.arrow_forward
- Using the gross requirements schedule below*, prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a periodic order quantity). What is the cost of this ordering system? Period 1 2 3 4 5 6 7 Gross requirements 25 20 40 0 10 50 30 The cost of this ordering system is $ Prepare a net requirements plan (enter your responses as whole numbers). *Holding cost = $1/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 25 units. Period Gross requirements On-hand at beginning of period On-hand at end of period Net requirements Order receipt Order release (enter your response as a whole number). 25 1 25 2 20 3 40 4 5 0 10 8 0 6 50 9 10 30 65 7 30 8 9 10 0 30 65arrow_forwardComplete the MPS record below for an end item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Order Policy: 100 units Lead Time: 2 weeks Quantity on Hand: 80 Week 1 2 3 4 5 6 7 8 9 10 Forecast 25 25 35 45 25 20 45 55 Customer orders 25 30 7 11 (booked) Projected on-hand inventory MPS quantityarrow_forwardBest-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan. Week Gross requirements 1 30 Week Gross requirements On-hand at beginning of week 40 On-hand at end of week Order receipt Order release Total relevant cost for this plan is = $ 2 3 30 1 30 4 2 5 40 70 20 Also, for this plan the Holding cost = $2.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40 units. Use the table below to develop a PPB solution for MRP (enter your responses as whole numbers). 3 30 6 7 8 4 5 40 (enter your response as a whole number). 6 ॥ 70 9 10 70 7 20 10 11 8 D 12 50 9 10 11 12 10 70 50arrow_forward
- State the types of data that would be carried in the bill-of-materials i le and the inventoryrecord file.arrow_forward4.7 Complete the following table. Lead time for the part is two weeks. The lot size is 50. What is the projected available at the end of week 3? When is it planned to release an order? Week Gross Requirements Scheduled Receipts 1 2 3 4 30 25 10 10 10 50 Projected Available 10 Net Requirements Planned Order Receipt Planned Order Releasearrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 9. Subscripts indicate quantity required for each parent. Assumelot-for-lot ordering. c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 2 3 4 5 6 7 8 9 (weeks) F Gross req Insert answer insert answer 2 On hand insert answer insert answer Net req insert answer insert answer Order receipt insert answer insert answer Order release insert answer insert answerarrow_forward
- This question is based on the following information pertaining to material Pogi: Usage 50 – 100 lbs. per day Lead time 8 – 12 days Size of the order 600 lbs. No. of days in a year 340 What is the average stock level? A. 1,250 B. 1,200 C. 1,000 D. 9252. What is the maximum stock level? 2,500 2,000 1,400 1,2003. What is the minimum stock level? 450 800 850 1,000 4. What is the re-order level? 1,200 1,600 1,750 1,800arrow_forwardthe information whether to accept additional orders from the customers or not is called available to promise quantity is provided by--------- a) MPS b) MRP c) ERP d) DRP Which one option is correct?arrow_forwardItem X is a standard item stocked in a company's inventory of spare parts. Each year, the firm uses about 2,000 units of Item X, which costs Php 1,000 per unit. Storage costs, which include insurance and cost of capital, amount to 18 percent of item unit cost. Placing an order for more of Item X costs Php 400. The company operates 360 days per year and Item X is received 9 days after placement of order.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY