Using the data for the coffee table in Problem 14.31, build a labor
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Trending nowThis is a popular solution!
![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times:
TASK
PRECEDINGTASKS
PERFORMANCE TIME (SECONDS)
TASK
PRECEDINGTASKS
PERFORMANCETIME (SECONDS)
a
—
48
g
d
43
b
—
58
h
e
38
c
—
73
i
f
23
d
a
63
j
g
33
e
b
88
k
h, i
53
f
c
23
l
j, k
67
A) What is the efficiency of your line balance?
B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)
An assembly line is to be designed to operate 7.5 hours per day and supply a steady demand of 300 units per day.
a)assign tasks to workstations using the longest operating time
b)suppose demand increase by 10%.how would you react to this?assume you can operatee only 7.5 hours per day
TASK
PRECEDING TASKS
PERFORMANCE TIME(seconds)
a
-
70
b
-
40
c
-
45
d
a
10
e
b
30
f
c
20
g
d
60
h
e
50
i
f
15
j
g
25
k
h,i
20
l
j,k
25
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).
A) is the bottleneck.
b) The bottleneck time isminutes per unit (round your response to two decimal places).
c) The throughput time of the overall system is
enter your response here
minutes (round your response to two decimal places).
D) If the firm operates 8 hours per day, 20 days per month, the monthly capacity of the manufacturing process isunits (enter your response as a whole number).
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- At Feebo Company, components U, V, W, and X are assembled in a cell in daily quantities of 70, 140, 280, and 35, respectively. Assuming a 480-minute workday, assume lot-for-lot, LT = 0. What is the MMP sequence? For the toolbar, press ALT F10 (PC) or ALT-FN+F10 (Mac)arrow_forwardA.J.’s Wildlife Emporium manufactures two unique birdfeeders (Deluxe and Super Duper) that are manufactured and assembled in up to three different workstations (X, Y, Z) using a small batch process. Each of the products is produced according to the flowchart in Figure. Additionally, the flowchart indicates each product’s price, weekly demand, and processing times per unit. Batch setup times are negligible.A.J. can make and sell up to the limit of its weekly demand and there are no penalties for not being able to meet all of the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $16 per hour. The plant operates 40 hours per week, with no overtime. Overhead costs are $2,000 per week. Based on the information provided, as well as the information contained in the flowchart, answer the following questions. a. Using the traditional method, which bases decisions solely on a product’s contribution to profits and overhead, what is the…arrow_forwardExplain what are the risks of automating a production process and what are the risks for a service process?arrow_forward
- Why is it more efficient for the work cells to prepare “modules” and deliver them to the assembly line thanit would be to produce the component (e.g., interior upholstery) on the line?arrow_forwardSlugger, Inc. assembles Baseball Bats with aluminum handles in an assembly line using four workstations. Management wants an output rate of 550 bats per day using a 11.5-hour workday. What is the cycle time?arrow_forwardK Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $15.00 Flexible Manufacturing System (FMS) 75,000 $225,000 $14.75 Dedicated Machine (DM) 75,000 $500,000 $13.00 Based on the total cost, the process that is best suited for the current contracted volume is Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new volumo inarrow_forward
- Bryan is Professor Russell’s graduate assistant. He wouldlike to leave for Spring Break tomorrow, but first he has tograde the midterm exams from four classes. These classesare new for Bryan, so he estimates his grading efficiency tobe 80%. Professor Russell has estimated the time requiredto create the key and the time to grade each paper as shownbelow. Bryan anticipates that he’ll need five hours of sleep,an hour to pack, an hour to get to the airport, an hour topost the grades, and three twenty minute breaks during theday for meals. Can Bryan finish his work and make it tothe airport on time in a 24 hour day?arrow_forwardThe following table shows the process times in minutes (or minutes/unit - how many minutes to process one unit) of a six-station serial production line (1-2-3-4-5-6). Station 1 2 3 4 5 6 Which station(s) is (are) the bottleneck(s)? Station 2 Station 5 Stations 3 and 4 Stations 2 and 5 Process Time (minutes/unit) 8 11 7 7 11 4arrow_forwardA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q a) is the bottleneck. 6 units/hr Sawing 2.4 units/hr Sanding Drilling 2 units/hr Welding 5 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr OUarrow_forward
- A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.1 units/hr Sawing 5 units/hr Sanding Drilling 5 units/hr Welding 2.5 units/hr a) Sawing is the bottleneck. b) The bottleneck time is 28.57 minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places). Assembly 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hrarrow_forwardTask: Draw a BPMN diagram for the financial workflow business process illustrated on pages 133-134 in Chapter 5 (pictures uploaded).arrow_forwardDave Grubbs of Grubbs Auto Body has five cars waiting for Economy Detailing. An Economy Detailing consists of a wash and then a hand wax. Cars cannot be waxed until they are washed. ROUND UP (39/5) & (39/10). Wash (hours) Wax (hours) (J)aguar 39/5 5 (C)adillac 5 3 (F)ord 1 39/10 (H)onda 2 1 (L)exus 4 4 What schedule produces the shortest time span in which these orders can be completed? Sequence: ____ , _____ , _____ , ______ , ______ Create a Gantt chart for the optimal sequence (shortest time span). How many hours does it take to complete the five orders? For the schedule in question “a”, how many hours is the waxing task idle? When will Dave finish the Cadillac? What is the average order completion time?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY