Chapter 14, Problem 32P

Using the data for the coffee table in Problem 14.31, build a labor schedule when the labor standard for each top is 2 labor-hours; each leg including brass cap installation requires, 1 4 hour, as does each pair of braces. Base assembly requires 1 labor-hour, and final assembly requires 2 labor-hours. What is the total number of labor-hours required each day, and how many employees are needed each day at 8 hours per day?

Blurred answer
Students have asked these similar questions
An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times:   TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67     A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)
An assembly line is to be designed to operate 7.5 hours per day and supply a steady demand of 300 units per day.  a)assign tasks to workstations using the longest operating time b)suppose demand increase by 10%.how would you react to this?assume you can operatee only 7.5 hours per day TASK PRECEDING TASKS PERFORMANCE TIME(seconds) a - 70 b - 40 c - 45 d a 10 e b 30 f c 20 g d 60 h e 50 i f 15 j g 25 k h,i 20 l j,k 25
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately​ from, and simultaneously​ with, the sawing and​ sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations​ (the operations are in​ parallel).   A) is the bottleneck. ​b) The bottleneck time isminutes per unit ​(round your response to two decimal​ places). ​c) The throughput time of the overall system is enter your response here minutes ​(round your response to two decimal​ places). D) If the firm operates 8 hours per​ day, 20 days per​ month, the monthly capacity of the manufacturing process isunits ​(enter your response as a whole​ number).

Chapter 14 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY