Using the information in Problem 14.3, construct a gross material requirements plan.

•• 14.3 The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.

  1. a. Construct a product structure. Identify all levels, parents, and components.
  2. b. Prepare a time-phased product structure.
Blurred answer
Students have asked these similar questions
Problem 13-3 (Static) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.   Item   Lead Time   Amounton Hand   Direct Components End   1   −   L(2), C(1), K(3) L   2   10   B(2), J(3) C   3   15   G(2), B(2) K   3   20   H(4), B(2) B   2   30     J   3   30     G   3   5     H   2   −            Click here for the Excel Data File   a. If 40 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)
The following table lists the components needed to assemble an end item, lead times (in weeks),and quantities on hand. Item Lead Time Amount on Hand Direct ComponentsEnd 1 — L(2), C(1), K(3)L 2 10 B(2), J(3)C 3 15 G(2), B(2)K 3 20 H(4), B(2)B 2 30J 3 30G 3 5H 2 —a. If 40 units of the end item are to be assembled, how many additional units of B are needed?(Hint: You don’t need to develop an MRP plan.)b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latestweek that the order can be started and still be ready to ship on time? (Hint: You don’t need todevelop an MRP plan.)
Once a material requirements plan (MRP) has been estab-lished, what other managerial applications might be found for the technique?

Chapter 14 Solutions

OPERATIONS MGMT.(EBOOK)W/MYOMLAB>IC<

Ch. 14 - Prob. 11DQCh. 14 - Identify five specific requirements of an...Ch. 14 - What are the typical benefits of ERP?Ch. 14 - What are the distinctions between MRP, DRP, and...Ch. 14 - As an approach to inventory management, how does...Ch. 14 - What are the disadvantages of ERP?Ch. 14 - Use the Web or other sources to: a. Find stories...Ch. 14 - Prob. 18DQCh. 14 - Use the Web or other sources to identify what an...Ch. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Using the information in Problem 14.3, construct a...Ch. 14 - Refer again to Problems 14.3 and 14.4. In addition...Ch. 14 - Refer again to Problems 14.3 and 14.5. In addition...Ch. 14 - As the production planner for Scott Sampson...Ch. 14 - Prob. 9PCh. 14 - a. Given the product structure and master...Ch. 14 - Prob. 11PCh. 14 - Based on the data in Figure 14.13, complete a net...Ch. 14 - Prob. 13PCh. 14 - A part structure, lead time (weeks), and on-hand...Ch. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Data Table for Problems 14.17 through 14.20 14.17...Ch. 14 - Develop an EOQ solution and calculate total...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - Prob. 21PCh. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Karl Knapps, Inc., has received the following...Ch. 14 - Coleman Rich, Ltd., has received the following...Ch. 14 - Prob. 25PCh. 14 - Prob. 26PCh. 14 - Using the data for the coffee table in Problem...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - When 18,500 Orlando Magic Fans Come to Dinner...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...Ch. 14 - MRP at Wheeled Coach Video Case Wheeled Coach, the...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY