Given this set of daily service operations, and assuming a processing order of A-B -C-D-E:
a. Give one reason that each arrangement might be preferred over the other.
b. Determine the number of repetitions for each service if four cycles are used.
c. Determine the number of repetitions for each service if two cycles are used.
a)
To determine: Reason each arrangement might be preferred over the other.
Introduction: A production cycle is a period through which the objects of labor like raw materials and goods stay in the creation procedure from the earliest starting point of assembling through the yield of completed item. Additionally the working time, the creation cycle incorporates interferences underway inferable from physical, synthetic, and organic forms or the character of the objects of work or the innovation and association of generation.
Explanation of Solution
Given Information:
Process order: A-B-C-D-E
Service Operation | Number of Daily Reps |
A | 22 |
B | 12 |
C | 4 |
D | 18 |
E | 8 |
The following are the reasons each arrangement might be preferred over the other:
- Two cycles have low amounts of substitutions.
- Four cycles have low inventory and are considered as high on suppleness.
b)
To determine: The number of repetitions for each service if four cycles used.
Introduction: A production cycle is a period through which the objects of labor like raw materials and goods stay in the creation procedure from the earliest starting point of assembling through the yield of completed item. Additionally the working time, the creation cycle incorporates interferences underway inferable from physical, synthetic, and organic forms or the character of the objects of work or the innovation and association of generation.
Answer to Problem 5P
Explanation of Solution
Calculate the number of repetitions for each service if four cycles used.
It is calculated by dividing each product’s daily quantity by 4.
Hence the number of repetitions for service operation A is 5.5, B is 3, C is 1, D is 4.5 and E is 2.
Determine the processing order if four cycles used.
Cycle | 1 | 2 | 3 | 4 |
A | 6 | 6 | 5 | 5 |
B | 3 | 3 | 3 | 3 |
C | 1 | 1 | 1 | 1 |
D | 4 | 4 | 5 | 5 |
E | 2 | 2 | 2 | 2 |
c)
To determine: The number of repetitions for each service if two cycles used.
Introduction: A production cycle is a period through which the objects of labor like raw materials and goods stay in the creation procedure from the earliest starting point of assembling through the yield of completed item. Additionally the working time, the creation cycle incorporates interferences underway inferable from physical, synthetic, and organic forms or the character of the objects of work or the innovation and association of generation.
Answer to Problem 5P
Explanation of Solution
Calculate the number of repetitions for each service if two cycles used.
It is calculated by dividing each product’s daily quantity by 2.
Hence the number of repetitions for service operation A is 11, B is 6, C is 2, D is 9 and E is 4.
Determine the processing order if two cycles used.
Cycle | 1 | 2 |
A | 11 | 11 |
B | 6 | 6 |
C | 2 | 2 |
D | 9 | 9 |
E | 4 | 4 |
Want to see more full solutions like this?
Chapter 14 Solutions
EBK OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Business in Action
Principles Of Operations Management
Operations Management: Processes and Supply Chains (11th Edition)
Business in Action (8th Edition)
Operations Management, Binder Ready Version: An Integrated Approach
- What types of scheduling decisions are management likely to encounter in the following operations? Describe the scheduling decisions in terms of the types of resources to be scheduled and the associated customers or jobs scheduled. Further specify the kinds of objectives that might be appropriate for the situation(s) you chose. a. Hospital b. University c. Moviemaking d. Make-to-order factory Note: you do not have to cover all situations. Please feel free to choose one which you are familiar with.arrow_forwardThe following memo is from an exasperated manager to her staff. Obviously, this manager does not have the time to clean up her writing or another set of eyes to review her written material before mailing it. From: Albertina Sindaha, Operations Manager To: All Emplovees Subject: Cleanup! Message You were all supposed to clean up your work areas last Friday. but that didn't happen. A few people cleaned their desks, but no one pitched in to clean the common areas. So we're going to try again. As you know, we don't have a big enough custodial budget anymore. Everyone must clean up himself. This Friday I want to see action in the copy machine area, things like emptying waste baskets, and you should organize paper and toner supplies. The lunch room is a disaster area. You must do something about the counters, the refrigerator, the sinks, and the coffee machine. And any food left in the refrigerator on Friday afternoon should be thrown out because it stinks by Monday. Finally, the office…arrow_forwardTwo operations A and B in a process have cycle times of 2 seconds and 15 minutes, respectively. Which of the following can be a likely solution? Review Later a) Run operation A to make one unit every 15 minutes b) Provide a supermarket between A and B c) Run a batch of 100 pieces every 15 minutes for operation A d) All of the abovearrow_forward
- Discuss how duality principles are applied in operations research, particularly in scheduling problems.arrow_forwardPositively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (i.e., not including queue time), are given for each line in the following table: Process Old Line New Line Rate per Machine (parts/hour) # Machines per Station Time (minute) Rate per Machine (parts/hour) # Machines per Station Time (minute) Punching 15 4 4.0 120 1 0.50 Braking 12 4 5.0 120 1 0.50 Assembly 20 2 3.0 125…arrow_forwardConsider a process consisting of five resources that are operated 8 hours per day. Theprocess works on three different products, A, B, and C: Demand for the three different products is as follows: product A, 40 units per day;product B, 50 units per day; and product C, 60 units per day.a. What is the bottleneck?b. What is the flow rate for each flow unit, assuming that demand must be served in the mixdescribed above (i.e., for every four units of A, there are five units of B and six units of C)?arrow_forward
- Choice Bank receives credit card applications that need to be reviewed for a decision. There are two types of applications; preapproved, and non-preapproved. Preapproved applications only need a quick review and therefore take 6 minutes to process. Applications that are not preapproved need a secondary credit check and take 15 minutes to process. 8. The bank receives 10 preapproved applications every hour and 6 applications that are not preapproved every hour. What is the utilization of the process?arrow_forwardlocal market research fim has just won a contract for several thousand small projects involving data gathering and statistical analysis. In the past, the firm has assigned each project to a single member of its highly trained professional staff. This person would both gather and analyze the data Using this approach, an experienced person can complete an average of 10 such projects in an eight-hour day. The firm's management is thinking of assigning two people to each project in order to allow them to specialize and become more efficient The process would require the data gatherer to fill out a matrix on the computer, check it and transmit it to the statistical analysis program for the analyst to complete. Data can be gathered on one project while the analysis is being completed on another, but the analysis must be complete before the statistical analysis program can accept the new data. After some practice, the new process can be completed with a standard time of 20 minutes…arrow_forwardFor tis week I will request from you to solve this mini case. The CEO of the Baker Inc, wants to implement a new accounting system, to improve work flow through the company’s sales, cash receipts, accounts payable, and cash disbursement procedures. The CEO is, however, concerned about the potential disruption that the implementation will have on operations. In an announcement letter to Baker’s employees, the CEO stated that: “I have contracted Flybynight Consulting Group to do the needs analysis, system selection, and design work. The programming and implementation will be performed in-house using existing IT department staff. The development process will be unobtrusive to user departments because Flybynight knows what needs to be done. They will work independently, in the background, and will not disrupt departmental and internal audit work flow with time consuming interviews, surveys, and questionnaires. This promises to be an efficient process that will produce a system that will…arrow_forward
- Cubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes taking order from the customer. After this, Tim prepares bread and Kim prepares filling for the order. These activities are performed in parallel, and take 6 and 12 minutes respectively. Jim then assembles the bread and filling, which takes 4 minutes of his time. Finally, Tim spends 1 minutes in delivering the order and taking payment. What is maximum number of sandwiches Cubway can make per hour? (In other words, what is the capacity of the process in sandwiches per hour?)arrow_forwardDiablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and assembledin five different workstations (V, W, X, Y, and Z) using a small batch process. Each workstation is staffedby a worker who is dedicated to work a single shift per day at an assigned workstation. Batch setuptimes have been reduced to such an extent that they can be considered negligible. A flowchart denotesthe path each product follows through the manufacturing process as shown in Figure 5.2, where eachproduct’s price, demand per week, and processing times per unit are indicated as well. Inverted trianglesrepresent purchased parts and raw materials consumed per unit at different workstations. Diablo canmake and sell up to the limit of its demand per week, and no penalties are incurred for not being able tomeet all the demand.Which of the five workstations (V, W, X, Y, or Z) has the highest utilization, and thus serves as the bottle-neck for Diablo Electronics?arrow_forwardKarina Nieto works for New Products Inc., and one of hermany tasks is assigning new workers to departments. Thecompany recently hired six new employees and would likeeach one to be assigned to a different department. The em-ployees have completed a two-month training session ineach of the six departments from which they received theevaluations shown below (higher numbers are better).Determine how the new employees should be assigned todepartments so that overall performance is maximized.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,