Question
Chapter 15, Problem 1.1VC
Summary Introduction
Case summary:
The case deals about the conversion of concert to a basketball. The details about the center were given. The available crew size is given as 16. The following information is given in the case:
To draw: The Gantt chart to help Person C to organize his crew to perform the concert-to-basketball conversion.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question Scenario:
Early one Monday morning in Jamaica, Susan, a Restaurant Manager starts getting ready for the morning’s work operations. She is particularly happy because tonight he has a date with Marvin, the new Chef that was recently hired. The problem, as Susan sees it, is that Roberta, another Restaurant employee has been just a little too friendly with Marvin lately and that really upsets Susan. Susan has redone the work schedule, assigning Roberta the clean-up shift in the night and cutting back on her hours of work. She is hoping that Roberta would simply quit and out of her way. However, that plan doesn’t seem to be working. Despite a lighter pay cheque and frequent reprimand through the disciplinary process of creating reasons to write to her about her conduct and performance. Roberta has decided to quit her studies due to her inability to fund her tuition. A few days later, Susan noticed Marvin and Roberta having lunch together in the staff dining room. Susan got furious…
Question 1
Â
Activity
Â
Activity Description
Immediate Predecessors
Estimated Duration
A
Excavate
—
2 weeks
B
Lay the foundation
A
4 weeks
C
Put up the rough wall
B
10 weeks
D
Put up the roof
C
6 weeks
E
Install the exterior plumbing
C
4 weeks
F
Install the interior plumbing
E
5 weeks
G
Put up the exterior siding
D
7 weeks
H
Do the exterior painting
E, G
9 weeks
I
Do the electrical work
C
7 weeks
J
Put up the wallboard
F, I
8 weeks
K
Install the flooring
J
4 weeks
L
Do the interior painting
J
5 weeks
M
Install the exterior fixtures
H
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Â
Â
Â
Â
Â
Â
Â
Â
Â
Â
Â
Â
Â
Using the PERT method, draw the network map.Â
Calculate the earliest start, earliest finish, latest start, latest finish, and slack times for each activity. Display results in a table format.Â
Calculate the critical path.…
QUESTION TWOÂ
As an operations management intern at a Limpopo-based company, HGK Holdings, your role is to assist the operationsanalyst with reconfiguring a brownfield project at HGK’s industrial estate in the Limpopo province, code-named LPCHP1. The reconfiguration involves the installation of an advanced biomass unit which generates electrical andthermal energy by burning wood pellets produced as a by-product of the wood processing industry in the province.The process is commonly called cogeneration or CHP (combined heat and power) and it is expected to save cost andincrease operational efficiency at HGK Holdings. The electrical and thermal energy generated is expected to be utilisedin the operations of HGK Holdings.
REQUIRED:Answer each of the following questions:
2.1. With the aid of an appropriately labelled Input-Transformation-Output diagram, comprehensively discuss thetransformation process underpinning the operations of LP-CHP1. In your discussion, highlight the transformedand…
Chapter 15 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management Plus MyLab Operations Management with Pearson eText - Access Card Package (10th Edition)
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Activity Weeks A Inspect the new building, list all required data communicationsfacilities 3 B Order and deliver all data communications facilities anddevices 10 C Identify, order and deliver replacement PCs, printers, serversand other hardware 8 D Order and deliver all required office equipment 11 E Test new hardware with all communications equipment 1 F Test new hardware with all existing operating and applicationssoftware 2 G Test all applications software and databases on the newhardware 2 H Move all staff to new premises 1    Tasks B, C and D can all run simultaneously but are all dependent on task A.Task E is dependent on tasks B and CTask F is dependent only on task CTask G is dependent on tasks E and F.Task H cannot start until tasks D and G are completed. a) Draw a full Activity on Node diagram for this project, showing clearly theearliest and latest start and end dates (as week numbers), and the float, foreach node. No start or end nodes are required.…arrow_forwardQuestion text Which of the following detail the exact manner in which any work is to be performed? a. Methods b. Procedures c. Programmes d. Purposearrow_forwardWhat is work breakdown structure (WBS)?arrow_forward
- Question 5 Work Breakdown Structure (WBS) is defined as deliverable-oriented of projectelements that organizes and defines the total work scope of project. Elaboratethe statement"deliverable-oriented grouping of project elements thatorganizes and defines the total work scope of the project.arrow_forwardQUESTION 1:  Differentiate between a project and a program and highlight two major characteristics of a PROJECTarrow_forwardQUESTION FOUR  .     4a     Poorly defined Scope of work (SOW) is a recipe for disaster and introduces a                    project to Risk  during the contracting and procurement process. Critically analyze                   these  statements in  the light of  Fixed Price (FP) Contract  4b.     Project Risk, Stakeholder Influence, and the Cost to manage the risk events are both a           function of time based on the project life cycle using a diagram/graph appraise the            statement. And prove that it is better to identify risk at the beginning of project than                        later in the life cycle of a projectarrow_forward
- Question 12 A project oriented process flow is more flexible than an assembly line orientation.  Group of answer choices a. True b. Falsearrow_forwardAssignment 2 – Activity Title: Practical HRM in Aviation Objective/s:i. To gain insight of the HRM system of world’s renowned airlinesii. To improve analytical skills of the students Instruction: Select an airline and cover the following aspects: ii. Job descriptions and job specifications of at least 4 different positions in the companyarrow_forwardQuestion 22: Briefly describe a project you worked on that required data gathering, importing, cleaning (i.e. merging other data, creating new variables, etc.), analysis, and output. If you have not had any experience with this please describe a project that might require these steps and how you would go about doing it.arrow_forward
- Question: what is the probability that the project will take less than 42 weeks ?( Show work/explain reasoning to receive full credit)arrow_forwardWork-in-Process Inventory, September 1 5,500 tonsWork-in-Process Inventory, September 30 3,400 tonsUnits started during September ?Units completed and transferred during September 7,300 tonsarrow_forwardExplain work breakdown structure (WBS)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.