a)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
b)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be going on from the earliest due date to the latest due date.
c)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule which helps to arrange the sequence in the order. Here, the job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
d)
To determine: Sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration would be served first. Then, the process would be going on from largest to shortest duration.
Want to see the full answer?
Check out a sample textbook solutionChapter 15 Solutions
OPERATIONS MANAGEMENT CUSTOM 12E >C<
- Question 35 Consider the processing times and due dates of the following jobs: Job Processing time (days) Due date (days) 1 3 29 2 19 25 3 24 40 4 8 20 What is the average lateness if the earliest due date (EDD) is used to sequence the jobs? Group of answer choices 0.75 1.25 4.25 5.67arrow_forwardQuestion 34 Consider the processing times and priorities for four jobs: Job Processing time (minutes) Weight/Priority (cost per minute) A 10 6 B 2 1 C 50 2 D 16 10 Assume the weighted shortest processing time (WSPT) rule is used. Which job should be processed third? Group of answer choices A B C Darrow_forwardQuestion Three Processing times (including setup times), and due dates for five jobs waiting to be processed at a work center are given in the following table. By Using the SPT rule determine the following: The sequence of jobs The average flow time The average job tardiness The average number of jobs at the work center Job Processing Time (hours) Hour Due A 17 15 B 10 25 C 5 20 D 7 32 E 11 38arrow_forward
- Question3: Two processes are applied in the same order to the jobs coming to a workstation. The durations of both processes for the six jobs coming to the workstation are as seen in the table. In order to minimize the total time to be spent on the jobs, the order in which the jobs should be done will be determined by the "johnson" rule. Accordingly, in the table below, write the order in which the business should do the work, in order, with the first things to be done on the far left, and one action to be written in each blank.1-) When the jobs are done in this order, how many minutes will it take to complete all the jobs?2-)1. How many minutes of space will there be in total in the process and the 2nd process?arrow_forwardQuestion fourThree jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B1 5 42 7 73 3 5Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forwardQuestion 1 Four floral arranging jobs are to be carried out across three stations: A (Arrange), B (Bag), C (crop) shown. The station sequences and job times in minutes are shown below, along with the due dates for each job. Using an "earliest due date" job dispatching priority rule, which, if any, of the jobs in will be late? Tip: create a Gantt chart schedule before answering Questions 4 & 5. a. Jobs 2 & 3 b. Jobs 3 & 4 c. Job 3 d. Job 4 e. None of the jobs will be latearrow_forward
- Question p .Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this linearrow_forwardQuestion Scenario: Early one Monday morning in Jamaica, Susan, a Restaurant Manager starts getting ready for the morning’s work operations. She is particularly happy because tonight he has a date with Marvin, the new Chef that was recently hired. The problem, as Susan sees it, is that Roberta, another Restaurant employee has been just a little too friendly with Marvin lately and that really upsets Susan. Susan has redone the work schedule, assigning Roberta the clean-up shift in the night and cutting back on her hours of work. She is hoping that Roberta would simply quit and out of her way. However, that plan doesn’t seem to be working. Despite a lighter pay cheque and frequent reprimand through the disciplinary process of creating reasons to write to her about her conduct and performance. Roberta has decided to quit her studies due to her inability to fund her tuition. A few days later, Susan noticed Marvin and Roberta having lunch together in the staff dining room. Susan got furious…arrow_forwardQuestion 2 a Full explain this question and text typing work only thanksarrow_forward
- Question 32 The processing times of four jobs are given as follows: Job Processing time (minutes) A 10 B 30 C 16 D 24 Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time (SOP) order? Group of answer choices 166 41.5 38 20.5arrow_forwardQuestion 2 b Full explain this question and text typing work onlyarrow_forwardQuestion text Which of the following detail the exact manner in which any work is to be performed? a. Methods b. Procedures c. Programmes d. Purposearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.