Concept explainers
a)
To determine: Theoptimal sequence for the jobs.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
b)
To draw: Gantt chart for the optimal sequence for the printing and binding jobs.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
c)
To determine: The length of the optimal sequence for the printing and binding jobs.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
d)
To determine: The idle time in the binding jobs.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
e)
To determine: The idle time in the binding jobs.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
Want to see the full answer?
Check out a sample textbook solutionChapter 15 Solutions
Principles Of Operations Management
- Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Determine a sequence that will minimize the total completiontime for these jobs. Illustrate graphically.arrow_forwardSix jobs are to be processed through a two-stepoperation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Determine a sequence that will minimize the total completiontime for these jobs. Illustrate graphically.arrow_forwardSolve this assignment problem in Excel to find the lowest cost solution and answer the following questions: 1.Which employee is assigned to job 1? Employee C (or) Employee B (or) Employee A 2. Which employee is assigned to job 2? Employee C (or) Employee B (or) Employee A 3.Which employee is assigned to job 3? Employee C (or) Employee B (or) Employee A 4.What is the minimum cost to complete all three jobs?arrow_forward
- De Law Construction has a gotten some construction jobs to build some starter housing units in a few areas. The building time for each housing unit to be completed as well as the date that each unit is to be completed is shown in the table below. Today is Day 471. Which of the sequences, EDD OR SPT should the company use to sequence the order in which they do the jobs, assuming that because of resource constraints it cannot do the jobs simultaneously? HOUSING UNIT Building Time (days) Due Date Marabella 39 Day 502 Tabaquite 23 Day 528 San Juan 30 Day 515 Mayaro 33 Day 498 D’Abadie 41 Day 535 Preysal 40 Day 510 Some time after starting the jobs according to the sequence you decided on, it was found that because of inclement weather the last three housing units in the sequence have been delayed. You now have to prioritise and decide in which order to expedite those three jobs, using the Critical Ratio model. It is now…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs,…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 11 10 22 B 10 8 13 C 8 4 19 D 6 4 16 E 1 3 30 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job ▼ A E B C D ▼ E C B D A ▼ A B C E D ▼ A B D C E ▼ C B D E Aarrow_forward
- The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forwardSix jobs are to be processed through a two-step opera- tion. The first operation involves sanding, and the second involves painting. Processing times are as follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B7 4 C5 7 D3 8 E2 6 F4 3 Determine a sequence that will minimize the total completion time for these jobs. Illustrate graphically.arrow_forward
- Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ▼ B C E F A D Part 2 2 ▼ F C A D B E Part 3 3 ▼ A B D F C E Part 4 4 ▼ E D C B F A Part 5 5 ▼ F C D A E B Part 6 6 ▼ D C F B E A Part 7 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = enter your response here hours (enter your response as a whole number). ... Question content area right Part 1 Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D…arrow_forwardPriority rules. Job times (including processing and setup) are shown in the following table for five jobs waiting to be processed at a work center.Job Job Time (hours) Due Date (hours)a 12 15b 6 24c 14 20d 3 8e 7 6Determine the processing sequence that would result from each of these priority rules:a. SPT b. EDDarrow_forwardThe following table contains information on the cost to run three jobs on four available machines.Determine an assignment planarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.