Chapter 15, Problem 23P
Summary Introduction
To determine: Thesequence that would minimize the total completion time.
Introduction: The Gantt chart is the kind of chart that is used to represent the amount of job done within a particular period. It is used to graphically represent the amount of job planned and done in a certain period.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Six jobs are to be processed through a two-stepoperation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
Determine a sequence that will minimize the total completiontime for these jobs. Illustrate graphically.
Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding, and the second involves painting. Processing times are as follows: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B7 4 C5 7 D3 8 E2 6 F4 3 Determine a sequence that will minimize the total completion time for these jobs. Illustrate graphically.
Two jobs must be processed through four machines in the same order. The processing times in the required sequence are (given)
Determine how the two jobs should be scheduled in order to minimize the total makespan, and draw the Gantt chart indicating the optimal schedule.
Chapter 15 Solutions
MyOMLab Principles of operations management : Sustainability and supply chain management (Book & eText Access Card)
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also shown.a. Develop a Gantt chart to determine the total time required to process all six jobs. Use the following sequence of jobs: 1, 2, 3, 4, 5, 6.b. Can you develop a better sequence to reduce the total time required for processing?arrow_forwardThe following set of seven jobs is to be processed through two work centers at George Heinrich’s printing company. The sequence is first printing, then binding.Processing time at each of the work centers is shown in thefollowing table: a) What is the optimal sequence for these jobs to bescheduled?b) Chart these jobs through the two work centers.c) What is the total length of time of this optimal solution?d) What is the idle time in the binding shop, given the optimal solution?e) How much would the binding machine’s idle time be cutby splitting Job Z in half?arrow_forwardPriority rules. Job times (including processing and setup) are shown in the following table for five jobs waiting to be processed at a work center.Job Job Time (hours) Due Date (hours)a 12 15b 6 24c 14 20d 3 8e 7 6Determine the processing sequence that would result from each of these priority rules:a. SPT b. EDDarrow_forward
- A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. Activity Time (minutes) A. Property survey 24 B. Credit report 19 C. Title search 18 D. Final decision 20 The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day? Numbers only, keep three decimals if not exact, either round up or down is okarrow_forwardDe Law Construction has a gotten some construction jobs to build some starter housing units in a few areas. The building time for each housing unit to be completed as well as the date that each unit is to be completed is shown in the table below. Today is Day 471. Which of the sequences, EDD OR SPT should the company use to sequence the order in which they do the jobs, assuming that because of resource constraints it cannot do the jobs simultaneously? HOUSING UNIT Building Time (days) Due Date Marabella 39 Day 502 Tabaquite 23 Day 528 San Juan 30 Day 515 Mayaro 33 Day 498 D’Abadie 41 Day 535 Preysal 40 Day 510 Some time after starting the jobs according to the sequence you decided on, it was found that because of inclement weather the last three housing units in the sequence have been delayed. You now have to prioritise and decide in which order to expedite those three jobs, using the Critical Ratio model. It is now…arrow_forwardThe following set of seven jobs is to be processed through two work centers at George Heinrich's printing company. The sequence is first printing, then binding. Processing timeat each of the work centers is shown in the following table: a) What is the optimal sequence for these jobs to be scheduled?b) Chart these jobs through the two work centers.c) What is the total length of time of this optimal solution?d) What is the idle time in the binding shop, given the optimal solution?e) How much would the binding machine's idle time be cut by splitting Job Z in half?arrow_forward
- Given the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true? Job Processing time (days) Due date (in days) A 10 10 B 5 8 C 15 25 D 8 15 a.Jobs B and D will have no tardiness b.The tardiness for Job A is 12 days c.The average tardiness is 19.75 d.The average completion time is 6.5arrow_forwardFive jobs must be scheduled for batch processing on a mainframe computer system. The processing times and the promised times for each of the jobs are listedhere.Job 1 2 3 4 5Processing time 40 min 2.5 hr 20 min 4 hr 1.5 hrPromised time 11:00 A.M. 2:00 P.M. 2:00 P.M. 1:00 P.M. 4:00 P.M.Assume that the current time is 10:00 A.M.a. If the jobs are scheduled according to SPT, find the tardiness of each job and themean tardiness of all jobs.b. Repeat the calculation in part (a) for EDD schedulingarrow_forwardThree jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B 1 5 4 2 7 7 3 3 5 Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forward
- Suppose that 12 jobs must be processed through six machines. If the jobs may beprocessed in any order, how many different possible schedules are there? If youwere to run a computer program that could evaluate 100 schedules every second,how much time would the program require to evaluate all feasible schedules?arrow_forwardThomas has four assignments due in class tomorrow, and his class times are as follows. Class Time Marketing 304 8 am OM 385 10 am Finance 216 2 pm Psychology 4:30 pm Each class lasts one hour, and Thomas has no other classes. It is now midnight, and Thomas estimates that the marketing, OM, finance, and psychology assignments will take him six, three, four, and two hours, respectively. Use the Excel Sequencing template to determine how he should schedule the work. Can he complete all of it on time? (Hint: Using SPT and EDD. First, convert times to due dates past midnight).arrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ▼ B C E F A D Part 2 2 ▼ F C A D B E Part 3 3 ▼ A B D F C E Part 4 4 ▼ E D C B F A Part 5 5 ▼ F C D A E B Part 6 6 ▼ D C F B E A Part 7 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = enter your response here hours (enter your response as a whole number). ... Question content area right Part 1 Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY