Chapter 15, Problem 4CS
Summary Introduction
Case summary:
The case deals about the store that manufactures old Oregon tables. There are four employees (Person T, Person G, Person L, and Person C) who deal with the operations such as preparation, assembly, finishing, and packaging. Each one would deal with a specific operation. However, all the four are able to do all the four operations. Person R is hired to perform major duties and help when the employees are absent. The time taken by each employee to perform every task is as follows:
Preparation | Assembly | Finishing | Packaging | |
Person T | 100 | 60 | 90 | 25 |
Person G | 80 | 80 | 60 | 10 |
Person L | 110 | 90 | 80 | 10 |
Person C | 120 | 70 | 100 | 25 |
Person R | 110 | 80 | 100 | 10 |
To determine: The way to manufacture the tables using four or five employees.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5
(i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.
Question:-M
Full explain this question and text typing work only.
Question 5The management of CDC Construction Pioneers have decided to build 900 new apartments in the Kasoa area due to the influx of immigrant workers into the country. Two Architectural Companies have provided building plans and technical schematics for the project. Management are happy with the proposals of both Standard apartment and Deluxe apartment. After investigating the steps involved in construction, management determined that each apartment complex built will require some resources. Management analysed each of the bids and concluded that if the plans of Standard apartment are built, it requires 0.7 days in foundation works, 0.5 days in the masonry, 1 day in finishing, and 0.1 days in painting works. Deluxe apartment will require 1 day in foundation works, 0.83 days in the masonry, 0.67 days in finishing, and 0.25 days in the painting works. Management estimate that, 630 days for foundation works, 600 days for masonry, 708 days for finishing and 135 days for 11painting works…
Chapter 15 Solutions
Operations Management
Ch. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQCh. 15 - Prob. 10DQ
Ch. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 11PCh. 15 - Prob. 12PCh. 15 - Prob. 13PCh. 15 - Prob. 14PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 1EDCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Prob. 2.3VCCh. 15 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Question text Which of the following detail the exact manner in which any work is to be performed? a. Methods b. Procedures c. Programmes d. Purposearrow_forwardQuestion 5 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. In an ideal world, how many workers should Tim hire to make tacos?arrow_forwardQuestion 2 choose 1 solution: What about your team members? How will your plan help them deal with the current situation? Option 1: I think the best thing I can do for them is offer encouragement and let them know that we're in this together. Also, it'll be crucial that I keep them focused on the task by going over our departmental processes. Protocol will keep things running smoothly. And that's good for the team and the company. Option 2: I'll continue to schedule overtime as needed. It's a good incentive for my team members that helps offset the long hours they're working. Option 3: I'm making allowance for a team member to take his allotted bereavement days. It's obviously important that he does, considering he lost his father. Other than that, I'm putting all new requests on hold. It may not go over well with some of the employees, but it's the smart thing to do at this point with all we have going on. Why?arrow_forward
- Need help with question 3 show workinarrow_forwardQuestion description Carter Cleaning Company the performance appraisal After spending several weeks on the job, Jennifer was surprised to discover that her father had not formally evaluated any employee’s performance for all the years that he had owned the business. Jack’s position was that he had “a hundred higher-priority things to attend to,” such as boosting sales and lowering costs, and, in any case, many employees didn’t stick around long enough to be appraisable anyway. Furthermore, contended Jack, manual workers such as those doing the pressing and the cleaning did periodically get positive feedback in terms of praise from Jack for a job well done, or criticism, also from Jack, if things did not look right during one of his swings through the stores. Similarly, Jack was never shy about telling his managers about store problems so that they, too, got some feedback on where they stood. This informal feedback notwithstanding, Jennifer believes that a more formal appraisal approach…arrow_forwardQuestion 15 kk .Whether you believe a one-page website is the best option for your particular website you are building in the course. Be sure to both explain your position based on your experience and provide support for your position with what you found in your research. Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this linearrow_forward
- QUESTION 1: Differentiate between a project and a program and highlight two major characteristics of a PROJECTarrow_forwardQUESTION 17 The statement, "XYZ Bank is an Equal Opportunity Employer." is an example of a A. procedure. B. single-use plan. C. program. D. policyarrow_forwardQuestion 6 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. During off-peak afternoon hours, demand at Tasty Tim’s drops to 40 tacos each hour. How many employees should Tim schedule to work during the afternoon? Again, ignore any effects of idle time or inefficiency due to poor line balancing.arrow_forward
- QUESTION 2 One of the employees at eden co ltd,described working at the company as to work at eden,you've got to be interested in a lot of stuff. you've got to be prepared to catch people when they fall,because people are trying stuff all the time and you've got to be prepared for unexpected because part of the way we work is almost liberately created chaos by doing more stuff than we've possibly got time to do,which means more junior members have more chances to become leaders because the senior ones can't do it all. you've got to be optimistic and smiley and damed hardwork. one of the senior managers connected,we try not to be prescriptive about defining talent and we try to encourage people to take individual responsibility for their own career path here as much as we can help them to a career path (a) in your own opinion what factors have contributed to organization citizenship behaviour among staffs at eden? elaborate your answers (b)discuss the leadership style that has help to…arrow_forwardQuestion 3 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. What is the labor content of one of Tasty Tim’s tacos?arrow_forwardWork rules can be less than what the law of the land stipulates Question 6Select one: True Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.