Chapter 16, Problem 7P
To determine
The rate of runoff for a storm of 100-year frequency and average velocityfor 196-acre rural drainage area.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
3. The figure below shows 5 different isohyets in a watershed. Find the average rainfall using the
isohyetal method
Given: The left-most side area (Zone A) can be assumed to receive a rainfall of 1 cm. The area between
the isohyets are given in the following table:
A
Zone
A
B
C
D
E
F
B
1 cm
D
E
1.5 cm
4 cm
Area (km²)
80
75
95
82
68
5
2.5 cm
3.5 cm
Calculate the runoff depth for the 100 year storm event over a catchment
basin using the SCS Runoff Method. The design rainfall for 100 year storm
event is 6 inches. NOTE: Round off your weighted CN to the nearest
WHOLE NUMBER.
SOIL GROUP
C
D
C
D
LAND USE
20%
15%
40%
25%
HINT: Determine first the weighted CN by weighted CN
CN to determine the runoff depth.
Σ(%land
use
CURVE NUMBER
94
93
83
80
X CN) then use the weighted
A certain watershed in Region VIII with an area of 60 ha flat heavy soil is to be converted
into a mixed subdivision consisting of:
40% apartment dwelling areas
20% business neighborhood areas
20% playgrounds and parks
20% light industrial areas
Using the rational method, estimate the percent change in peak runoff flow rates before
and after the development.
Refer to the table below for the values of runoff coefficients.
Values of Runoff coefficients, C (Chow, 1962)
Runoff
coefficient, C
Runoff
coefficient, C
Type of drainage area
Type of drainage area
Lawns:
Sandy soil, flat, 2%
Sandy soil, average, 2–7%
Sandy soil, steep, 7%
Heavy soil, flat, 2%
Heavy soil, average, 2–7%
Heavy soil, steep, 7%
Industrial
0.05–0.10
0.10-0.15
0.15-0.20
0.13-0.17
0.18-0.22
0.25-0.35
0.50–0.80
0.60–0.90
0. 10-0.25
0.20-0.35
Light areas
Heavy areas
Parks, cemeteries
Playgrounds
Railroad yard areas
Unimproved areas
Streets:
Asphaltic
Concrete
0.20-0.40
Business:
Downtown areas
Neighborhood areas
0.10-0.30…
Chapter 16 Solutions
Traffic And Highway Engineering
Knowledge Booster
Similar questions
- You have been given a 1-hour unit hydrograph (1 unit = 1 cm) and have been asked to use it to derive the surface runoff hydrograph for a 2-hour storm for which the total depth of rainfall excess was X cm and the intensity was constant. To derive it, you can: Multiply the ordinates of the 1-hour unit hydrograph by X/2 Find the 2-hour unit hydrograph and then multiply its ordinates X/2 Consider the storm as having two 1-hour periods of depth X/2 , multiply each 1-hour UH by X/2, lag them by 1 hour, and then add their ordinates. Multiply the ordinates of the 1-hour unit hydrograph by 2Xarrow_forwardProblem 1. The following are the ordinates of the hydrograph flow from a catchment area of 770 km2 due to a 6-hr rainfall. a. Derive the ordinates of the 6-hr unit hydrograph. Assume that the graph of the baseflow is linear with respect to time. b. Plot the direct runoff hydrograph. c. Determine the rainfall excess in terms of (i) volume in m3 and (2) depth in cm. d. Plot the unit hydrograph. Time from the beginning of the storm (hr) 0 6 12 18 24 30 36 42 48 54 60 66 72 Discharge (cumecs) 40 65 215 360 400 350 270 205 145 100 70 50 42arrow_forwardThe ordinates of the direct runoff hydrograph (D.R.O) resulting from a complex storm are shown in the table below. Determine the ordinates of the unit hydrograph by using the deconvolution method. If values of effective rainfall (R) equal to (Ri=1.06 cm, R-1.93 cm, and R=1.81 cm). 1 2 3 Time (hr) 4 5 6 7 8 9 428 1923 5297 9131 10625 7834 3921 1846 1402 Part B: D.R.O (m³/s) 10 11 830 313arrow_forward
- 2. The Friends Creek watershed has five rainfall gauges at the locations shown in the figure below. Total rainfall recorded at each gauge during a storm event is listed in the table. + Friends Creek C E w B Gage Rainfall (cm) A B C D E 6.0 7.8 9.2 4.1 3.0 Compute the mean areal rainfall (in centimeters) for this storm using: (a) Arithmetic averaging (b) The Thiessen methodarrow_forwardA catchment area is presented in the Figure 1. Six rainfall gauges A, B, C, D, E and F are spread over this watershed and nearby. The inter isohyets areas I, II, II, IV and V are given as 20, 50, 70, 90, and 10 km? respectively. All the rainfall and isohyets are given in cm. Estimate the mean precipitation over this catchment area using arithmetic mean and isohyetal methods.arrow_forwardFollowings are given for a watershed: Rational method coefficient C = 0.37 Time of concentration = 30 min Watershed Area = 4.7 km^2 Rainfall intensity is 1.8 cm/hr Part 1: CIA=? (Must show calculation details for Part 1) (For Parts 2 to 4, pick only one choice and fill that blank) Part 2: If rainfall duration is 15 min, the peak flowrate is: a. b. uncertain, but it is smaller than C. uncertain, but it is greater than Part 3: If rainfall duration is 30 min, the peak flowrate is: d. e. uncertain, but it is smaller than f. uncertain, but it is greater than Part 4: If rainfall duration is 60 min, the peak flowrate is: g. h. uncertain, but it is smaller than_ i. uncertain, but it is greater thanarrow_forward
- The ordinates of a 6h-UH of a watershed having a drainage area of 393 km^2 are given below. For a storm over the watershed having excess rainfall of 5 cm for the first six hours and 15 cm for the second six hours, compute the direct runoff hydrograph ordinates and plot the hydrograph. Compute the depth of direct runoff in cm. Assuming constant baseflow of 100 m^3/s, compute the storm hydrograph ordinates and plot the hydrograph. (List all the DRH ordinates in order, separated by a single space.)arrow_forwardA catchment has a runoff coefficient of 0.20, area = 1.5 km² with a general slope of 0.001 and maximum length of travel of overland flow of 1.25 km. Information on the storm of 50 years return period is given as follows: Duration (min) 15 30 45 60 80 Rainfall (mm) 40 60 75 100 120 Estimate the peak flow to be drained by a culvert for a 50 year stormarrow_forwardIn the table below data for precipitation and runoff both in depths of cm are given for June during ten years from 2010 to 2018. Develop a linear equation relating precipitation and runoff.arrow_forward
- The ordinates of a hydrograph of surface runoff resulting from 4.5cm of rainfall excess of duration 8 hours in a catchment are as follows. Determine the ordinates of the 8h unit hydrograph for this catchment. Tabulate your solution and plot the 8H-UH.arrow_forwardFor a precipitation event in a watershed of interest, Table 1 shows the Unit Hydrograph for the watershed on the left, and the excess rainfall at times 1, 2, and 3 on the right. Using the convolution method, find the direct and total runoff from the watershed. Assume the watershed has a constant baseflow of 8 ft³/sec. Table 1. Excess rainfall and Unit Hydrograph Unit Excess Time Time Hydrograph Rainfall (hrs) (ft³/(sec*in)) (hrs) (in) 1 36 1 0.3 2 92 2 0.2 3 63 3 1.1 4 18 5 5arrow_forwardQUESTION 3 10 A storm with 10 cm precipitation produced a direct surface runoff of 5.8 cm in the equivalent depth unit. The time distribution of the storm is given in Table below. Estimate the @-index of the storm and the excess rainfall hyetograph. Time from start (hr) Incremental 0.4 rainfall in each hr (cm) 4 6. 0.9 1.5. 3.3 T.7 1.6 1.0 0.5arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning