Textbook Question
Chapter 17, Problem 9P
PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.
Construct a network diagram for the information in the following table. Use either AOA or AON (see Example 5 for either type). What is the probability that the project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below? Times are in weeks.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Project Scope Management
Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality.
Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control."
Based on your Integrated Project:
Select two of the subdivisions above and discuss the primary issues that could arise from the process.
Your response should begin with a definition of the selected subdivision before detailing the selected process
Due to complexity of the project, there is the need to use ‘network analysis’, what is it?
Kimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table:
a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.
Chapter 17 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...
Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?arrow_forwardquetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?arrow_forwardUsing your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeksarrow_forward
- You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks Farrow_forwardBy using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Barrow_forwardUsing PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?arrow_forward
- Is forecasting important in a planning of a project? why? why not?arrow_forwardces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St Farrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A Carrow_forward
- (c) Illustrate with suitable examples, the COCOMO I and II model of project management.arrow_forwardThe project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistakearrow_forwardThe project manager serves as an expert on the theory and application of statistical techniques. Responsibilities include experimental design, data processing, and analysis. True Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY