Question
Chapter 18, Problem 17PA
Summary Introduction
To determine: The lateness of Job C.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table.
Job
Time Since Order Arrived
(days ago)
Processing Time
(days)
Due Date
(days from now)
A
6
18
48
B
4
22
52
C
1
30
70
D
10
14
28
E
7
12
56
F
5
20
62
Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule.
Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule.
Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center
is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's
rule, which job should be scheduled first in the sequence?
O A. V
OB. U
O C. R
OD. S
O E. T
Job
R
S
T
Alpha
20
23
50
26
55
Beta
34
35
20
26
75
Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk
Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and
hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted.
Note that Courtney works an 8-hour day and today is a work day.
JOB
DUE DATE (HOURS
HENCE)
18
36
10
22
14
E
a) Sequence the jobs according to EDD.
According to the EDD rule, the sequence of jobs should be
b) What is the average completion (flow) time?
The average completion (flow) time is
c) What is the average job lateness?
The average job lateness is
d) What is the average number of jobs in the system?
The average number of jobs in the system is
place).
DURATION (HOURS
REQUIRED)
3
19
4
9
5
days (round your response to one decimal place)
days (round your response to one decimal place).
jobs (round your response to one decimal
Chapter 18 Solutions
OPERATION MANAGEMENT
Ch. 18 - Prob. 1CQCh. 18 - Prob. 2CQCh. 18 - Prob. 3CQCh. 18 - Prob. 4CQCh. 18 - Prob. 5CQCh. 18 - Prob. 6CQCh. 18 - With weighted shortest processing time, jobs are...Ch. 18 - Prob. 8CQCh. 18 - Prob. 9CQCh. 18 - Prob. 10CQ
Ch. 18 - Prob. 11CQCh. 18 - Prob. 12CQCh. 18 - Prob. 13CQCh. 18 - Prob. 14CQCh. 18 - Prob. 15CQCh. 18 - Prob. 16CQCh. 18 - Prob. 1PACh. 18 - Prob. 2PACh. 18 - Prob. 3PACh. 18 - Prob. 4PACh. 18 - Prob. 5PACh. 18 - Prob. 6PACh. 18 - Prob. 7PACh. 18 - Prob. 8PACh. 18 - Prob. 9PACh. 18 - Prob. 10PACh. 18 - Prob. 11PACh. 18 - Prob. 12PACh. 18 - Prob. 13PACh. 18 - Prob. 14PACh. 18 - Prob. 15PACh. 18 - Prob. 16PACh. 18 - Prob. 17PACh. 18 - Prob. 18PACh. 18 - Prob. 19PACh. 18 - Prob. 1CCh. 18 - Prob. 2CCh. 18 - Prob. 3CCh. 18 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following jobs are waiting to be processed at a small machine center. JOB 10 20 30 40 50 DUE DATE 260 256 260 265 275 DURATION (DAYS) According to the LPT rule, the sequence of jobs should be 10, 50, 40, 20, 30 b) What is the average completion (flow) time? The average completion (flow) time is 62.8 days (round your response to one decimal place) c) What is the average job lateness? The average job lateness is 11.0 days (round your response to one decimal place). d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). 28 12 8 18 22 D Points: 2 of 4 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPTarrow_forwardstate whether or not each situation would be considered “compensable time” (and why or why not). An employee of a fast food chain has to arrive at work 15 minutes early to change into the“mascot” costume and it typically takes another 15 minutes at the end of the shift to change outof the costume and properly store it. Due to the cost of the costume, employees are notallowed to take the costume home. The “mascots” typically work from 10am – 2pm, to coverthe lunch rush periods. How much time would be “compensable” for the mascots, assumingthe conditions/schedule listed above?2) George is a Radiology Technician at a local hospital and when on call, is required to be nofurther than 30 minutes away from the facility. Is the “on call” time, compensable?arrow_forwardTo control queue and make deadlines, two things are essential: must schedule and plan carefully , what are these ?arrow_forward
- In a POAM, an action is a scheduled event that indicates the completion of a task or group of tasks. True Falsearrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. Due date Duration (hours required) Job (hours hence) A 8 16 2 C 24 10 32 16 E 12 6 In what sequence would the jobs be ranked according to the following decision rules: FCFS, EDD, SPT, LPT? According to the FCFS rule, the sequence of jobs should be According to the EDD rule, the sequence of jobs should be According to the SPT rule, the sequence of jobs should be According to the LPT rule, the sequence of jobs should bearrow_forwardFive jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta R 20 10 S 25 30 T 30 20 U 35 35 V 15 25 Part 2 A. V−S−U−T−R B. V−R−U−S−T C. R−V−T−S−U D. S−U−T−V−R E. R−S−T−U−Varrow_forward
- Apply the four popular sequencing rules to the five jobs shown in the table below. For each sequence determine: The average completion time (sum of total flow time/number of jobs) Utilisation measure (Total job work time/Sum of total flow time) Average number of jobs in system (Sum of total flow time/Total job work time) Average job lateness (Total late days/Number of jobs) Job Due Job Work (Processing) Time Date (Days) (Days) 8 6 18 15 23 Job ABCDE 6 W ∞ NO 6 2 8 3 9arrow_forwardIn her last semester at SPC, Polly Hedron needs to take Statistics, Composition 2, and Ethics. Because Polly is registering early, she has 17 choices for her section of Statistics, 11 choices for her section of Composition, and 19 choices for her section of Ethics. From how many possible schedules can Polly choose? (You may presume that none of these sections interfere with each other) Your Answer:arrow_forwardJoe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of the process includes washing and drying the clothes; the second step is pressing the clothing. Joe wants to minimize the amount of time it takes to do all the jobs. The five jobs waiting to be processed are shown here. Job Wash andDry (hours) Press(hours) A 5 4 B 3 4 C 2 3 D 7 5 E 4 2 Wash and Dry Using FCFS, assume the jobs arrive in the order shown (A, then B, then C, etc.). Show the beginning time for each job and ending time for the whole process adding hours throughout the process. A -0 number of hours B-5 number of hours C-8 number of hours D-10 number of hours E-17 number of hours A B C D E 0 enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours Pressarrow_forward
- Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Job CR 103 Job Due Date Duration (days) 103 214 10 205 223 7 309 217 11 412 219 5 517 217 15 Assume that all jobs arrived on day 180; today's date is 200.arrow_forwardCalculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 245. Job Date Job Received Due Date Duration (days) 1 215 300 30 2 230 310 25 3 228 290 35 4 235 305 40 5 245 315 45arrow_forwardPayroll: Risks and Controls Below are some of the processes that are typically executed before, during, and after a payroll cycle: Employees record their hours worked. The supervisor reviews and approves each employee's time records with their signature. An officer from the Human Resources department updates employee files after receiving authorized records of overtime and leaves (vacations, illness, etc.) from the supervisor. Afterward, approved records are sent to the payroll officer in the accounting department. The payroll officer calculates the gross payment, applies deductions, and calculates the net payment. Subsequently, the final payroll is sent for the controller's approval. Payments are issued to employees using their preferred delivery method (check or direct deposit). Entries are generated for the corresponding payroll transactions. Withholdings for payroll taxes, Social Security, and Medicare are respectively remitted to the Department of Treasury and the Internal…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY