Question
Chapter 18, Problem 1PA
Summary Introduction
To determine: Architect’s flow rate?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
state whether or not each situation would be considered “compensable time” (and why or why not).
An employee of a fast food chain has to arrive at work 15 minutes early to change into the“mascot” costume and it typically takes another 15 minutes at the end of the shift to change outof the costume and properly store it. Due to the cost of the costume, employees are notallowed to take the costume home. The “mascots” typically work from 10am – 2pm, to coverthe lunch rush periods. How much time would be “compensable” for the mascots, assumingthe conditions/schedule listed above?2) George is a Radiology Technician at a local hospital and when on call, is required to be nofurther than 30 minutes away from the facility. Is the “on call” time, compensable?
Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table.
Job
Time Since Order Arrived
(days ago)
Processing Time
(days)
Due Date
(days from now)
A
6
18
48
B
4
22
52
C
1
30
70
D
10
14
28
E
7
12
56
F
5
20
62
Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule.
Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule.
Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
An architect has five projects to complete. She estimates that three of the projects willrequire one week to complete and the other two will require three weeks and four weeks.During the time these projects are completed (and assuming no other projects areworked on during this time), what is the architect’s flow rate (projects per week)?
Chapter 18 Solutions
Operations Management
Ch. 18 - Prob. 1CQCh. 18 - Prob. 2CQCh. 18 - Prob. 3CQCh. 18 - Prob. 4CQCh. 18 - Prob. 5CQCh. 18 - Prob. 6CQCh. 18 - With weighted shortest processing time, jobs are...Ch. 18 - Prob. 8CQCh. 18 - Prob. 9CQCh. 18 - Prob. 10CQ
Ch. 18 - Prob. 11CQCh. 18 - Prob. 12CQCh. 18 - Prob. 13CQCh. 18 - Prob. 14CQCh. 18 - Prob. 15CQCh. 18 - Prob. 16CQCh. 18 - Prob. 1PACh. 18 - Prob. 2PACh. 18 - Prob. 3PACh. 18 - Prob. 4PACh. 18 - Prob. 5PACh. 18 - Prob. 6PACh. 18 - Prob. 7PACh. 18 - Prob. 8PACh. 18 - Prob. 9PACh. 18 - Prob. 10PACh. 18 - Prob. 11PACh. 18 - Prob. 12PACh. 18 - Prob. 13PACh. 18 - Prob. 14PACh. 18 - Prob. 15PACh. 18 - Prob. 1CCh. 18 - Prob. 2CCh. 18 - Prob. 3CCh. 18 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- state whether or not each situation would be considered “compensable time” (and why or why not). Toby works as Call Center Representative. He works from 7am – 4:30am, Monday – Friday with 30minutes for lunch. He also typically takes several “mini-breaks” during the day to smoke. These breakstypically range from 5-10 minutes in length and he would typically take at least, one in the morning andone in the afternoon. Toby prefers to eat his lunch at his desk, however he also tends to answerquestions from his manager and even his co-workers throughout his lunch, because he is the seniorrepresentative on that team. This occurred for at least a year. Toby recently was let go because due toa downsizing in the department. Toby called his former manager, Kelly and stated that he was owed 30minutes of pay for the past year because technically he was doing work while eating. Kelly stated thatthis was not correct, he was on a lunch break and answering questions was completely voluntary. Shewent on…arrow_forwardThe manager of the Personnel Department at City Enterprises has been reading about time-driven ABC and wants to apply it to her department. She has identified four basic activities her employees spend most of the their time on: Interviewing, Hiring, Assessment, and Separation Processing. The department employs 5 staff who perform these activities. The manager provides the following estimates for the amount of time it takes to complete each of these activities: Interviewing: 45 minutes. Hiring: 60 minutes. Assessment: 75 minutes. Separation Processing: 90 minutes. Employees in Personnel work 35-hour weeks with four weeks for vacation. Of the 35 hours, five are reserved for administrative tasks, training, and so on. The costs of the Personnel Department, including any allocated costs from other staff functions, are $972,000. During the year, Personnel conducted 1,200 interviews, made 375 hires, made 3,000 assessments, and had 250 separations. The manager of the Personnel…arrow_forwardFive jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta R 20 10 S 25 30 T 30 20 U 35 35 V 15 25 Part 2 A. V−S−U−T−R B. V−R−U−S−T C. R−V−T−S−U D. S−U−T−V−R E. R−S−T−U−Varrow_forward
- How do you find the flow rate to get the costs of direct labor in this problem? I know the formula for costs of direct labor is number of employees x wage rate / flow rate but I'm unsure with how to find the flow rate.arrow_forwardConsider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardConsider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forward
- Consider the following process at a pharmacy. Customers drop off their prescriptions either in the drive-through counter or in the front counter of the pharmacy. Customers can request that their prescription be filled immediately. In this case, they must wait between 15 minutes and one hour depending on the current workload. Most customers are not willing to wait that long, so they opt to nominate a pick-up time at a later point during the day. Generally, customers drop their prescriptions in the morning before going to work (or at lunchtime) and they come back to pick up the drugs after work, typically between 5pm and 6pm. When dropping their prescription, a technician asks the customer for the pick-up time and puts the prescription in a box labelled with the hour preceding the pick-up time. For example, if the customer asks to have the prescription be ready at 5pm, the technician will drop it in the box with the label 4pm (there is one box for each hour of the day). Every hour, one…arrow_forwardThe Hickory Company manufactures wooden desks. Manage-ment schedules overtime every weekend to reduce the backlogon the most popular models. The automatic routing machineis used to cut certain types of edges on the desktops. The fol-lowing orders need to be scheduled for the routing machine: The due dates reflect the need for the order to be at its nextoperation.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of average flowtime and average past due hours.b. Comment on the performance of the two rules relative tothese measuresarrow_forwardIn the winter, Scott works four 10-hour days instead of five 8-hour days, so he has a long weekend every week. In this way, Scott takes advantage of a ________. Question 38 options: A) shared work week B) flextime work week C) new-age work week D) compressed work week E) enriched work weekarrow_forward
- An independent accountant is planning to prepare tax returns for six of her clients.Prior to her actually preparing each return, her secretary checks the client’s file to besure all the necessary documentation is there and obtains all the tax forms needed forthe preparation of the return. Based on past experience with the clients, her secretaryestimates that the following times (in hours) are required for preparation of the returnand for the accountant to complete the necessary paperwork prior to filing each return:Client Secretary Time Accountant Time1 1.2 2.52 1.6 4.53 2.0 2.04 1.5 6.05 3.1 5.06 0.5 1.5In what order should the work be completed in order to minimize the total timerequired for all six clients?arrow_forwardWhy does the theory of constraints advocate that a manager’s attention be directed tothe bottleneck of a process?a. It is useful to lower the utilization of the bottleneck.b. The bottleneck has considerable influence on the average flow rate of a process.c. It is important to minimize the buffer inventory in front of the bottleneck.d. First-come-first-served scheduling of jobs at the bottleneck ensures that all jobs havethe same expected waiting time before they are processed at the bottleneck.arrow_forwardSouth Beach University is conducting an online exam. There are 1,200 students taking this exam. Students are required to download the exam questions from the university’s learning management system (LMS), solve the questions, type their workings and answers in a computer word processing application, and submit the files back to the LMS. It is estimated that the LMS takes an average of 30 seconds to process a submission. For example, if a student submits his files at time T and the LMS is able to start processing his submitted files right away, it is estimated that the LMS accepts the submission at T + 30 seconds. The cut-off time of the exam is 12pm on the exam day, that is, if a submission cannot be accepted by the LMS by 12pm, it is considered late submission. Due to the capacity of the LMS servers, a maximum of 150 submissions can be processed at any point of time. Submissions are processed on a first-come-first-serve basis. If the number of submissions exceeds the capacity, some…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY