Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job. Frey estimates that the job will require the Mowing direct labor.

Frey apples overhead to jobs at 175% of direct labor cost, Frey would like to earn at least $80,000 profit on the architectural job. Based on past experience and market research, it estimates that the competition will bid between $285,000 and $350,000 for the job.

1. What is Frey;s estimated cost of the architectural job?

2. What bid would you suggest that Frey submit?

Check (1) $213,125

Chapter 19, Problem 18E, Exercise 19-18 Job order costing for services A1 Hansel Corporation has requested bids from several

Blurred answer
Students have asked these similar questions
Review Question 1Manufacturing Overhead Allocation Base and Calculating the Cost of Jobs.Pyramid Company expects to incur $3,000,000 in manufacturing overhead costs this year. During theyear, it expects to use 40,000 direct labor hours at a cost of $600,000 and 80,000 machine hours.Required:a. Prepare a predetermined overhead rate based on direct labor hours, direct labor cost, andmachine hours.b. Why might Pyramid Company prefer to use machine hours to allocate manufacturing overhead?c. Using each of the predetermined overhead rates calculated in part a and the data that follows forjob 128, determine the cost of job128.Direct materials $6,000Direct labor $4,000 (200 hours at $15 per hour) + (100 hours at $10 per hour)Machine time 700 hours
Question No.4 The Jewell plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows:   Maintenance   Rs.360,000 Inspection            750,000   The plant currently applies overhead using direct labor hours and expected capacity of 100,000 direct labor hours. The following data has been assembled for use in developing a bid for a proposed job. Bid prices are calculated as full manufacturing cost plus a 20% mark-up.   Direct materials       Rs.2,100 Direct labor                  5,625 Machine hours                450 Number of inspections       4 Direct labor hours           550   Total expected machine hours for all jobs during the year are 60,000, and the total expected number of inspections is 4,000.   Required: A: Compute the total cost of the potential job using direct labor hours to assign overhead. Determine the bid price for the potential job. B: Compute the total cost of the job using…
Exercise 9 Engineer Co. is submitting a bid for a major job and estimates the following direct labor costs: Engineers Drafters Staff Hourly Rate Hours 60 $ 250.00 40 $ 120.00 100 $ 20.00 Engineer Co. has no direct material costs and applies overhead at a rate of 150% of direct labor cost. It estimates the competition will bid between $63765 and $77935. a) What is the estimated cost of direct labor for the job? b) What is the estimated cost of the job(Labor & MOH)? c) What should it bid to earn a 30% profit on cost? JU X IX

Chapter 19 Solutions

FUNDAMENTAL ACCT PRIN TEXT+CONNECT CODE

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Text book image
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License