Chapter 22, Problem 22.6E
Explanation of Solution
Fixed-price contracts:
- Fixed-price contracts will increase the likelihood of product risks as they remove options from the development process.
- The contractor is naturally reluctant to increase the effort or time expended on the project as it will reduce their profits on the work because the contract is fixed-price...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Fixed-price contracts, where the contractor bids a fixed price to complete a system development, may be used to move project risk from client to contractor. If anything goes wrong, the contractor has to pay. Suggest how the use of such contracts may increase the likelihood that product risks will arise.
A project estimator is working on estimates for a project that is very similar to a previous project, in that it has many of the same features and those features have similar costs. Each feature or deliverable will represent the same percentage of the total cost as it did for the previous project. He is using the _________ method of top-down estimating.
a. ratio
b. consensus
c. apportion
d. function point
e. learning curves
Technical feasibility is a measure of how well a proposed system solves the problems and takes advantages of the opportunities envisioned for the system
True or false
Chapter 22 Solutions
EBK SOFTWARE ENGINEERING
Ch. 22 - Explain why the intangibility of software systems...Ch. 22 - Explain why the best programmers do not always...Ch. 22 - Prob. 22.4ECh. 22 - Suggest why the probability of risks arising and...Ch. 22 - Prob. 22.6ECh. 22 - Prob. 22.7ECh. 22 - What problems do you think might arise in extreme...Ch. 22 - Write a case study in the style used here to...Ch. 22 - Your manager asks you to deliver software to a...
Knowledge Booster
Similar questions
- elements of Feasibility studies that should be undertaken while performingFeasibility study analysisarrow_forwardTrue or False. In the project life cycle model, the V model does not emphasize on the verification and validation activities throughout the life cycle.arrow_forwardFeasibility analysis is typically done during which systems development stage? a. investigation h. analysis c. design d. all of the abovearrow_forward
- Feasibility analysis is typically done during which systems development stage? a. investigation b. analysis c. design d. all of the abovearrow_forwardA competent software manager knows how to leverage the organizational cause-and-effect relationship. Which of the following are true regarding organizational cause and effect inter-relationships? Project size has a positive correlation with its estimation accuracy. Software complexity has a negative correlation with support cost The level of organizational maturity has a negative correlation with number of inherent product faults The total number of inherent product faults has a positive correlation with the total number of customer failures coming from the field Complexity of a software piece has a negative correlation with its defect density During a peer review, examination rate has a negative correlation with defect density (which is defined as a number of found defects per thousand lines of code).arrow_forwardQ- a) What is PERT and CPM in project management show the difference between them b) Consider the following engineering project. 1-What is the critical path 2- Compute the ES, EC, LS, LC and the slack time, and display all the values in a table. Activity Immediate Time (week) predecessor Activity A A A, B D B E A, C, D 8 3- Suppose that activity C has been completed within 5 weeks, what is the effect on the project completion time? 65arrow_forward
- Question 2 As the project progresses, it is vital that the project manager is able to guarantee the performance of the end product. Discuss how the true cost of defects can often be higher than the initial apparent cost, giving examples from the case study. Discuss the main components of a quality management system setting each component in the context of the case studyarrow_forwardSuppose you are working as a lead developer for a software house (This software house is a new startup so the developers are not well trained) and you are asked to deliver the project before the estimated time with the same available resources (i.e. neither the salary nor the practitioners are added).In this kind of situation: Which type of risks are identified? Discuss how would you plan the situation being a team leader (hint: Contingency plan)?arrow_forwardSystem development cost is impacted by the development model used. Which of the following development models is considered the highest in terms of cost compared to the other models? Select One Waterfall model Spiral model Incremental model Agile mode Which of the following statements is TRUE about Waterfall development model? Select One In waterfall model, system components can be developed separately. Takes into consideration the change of the requirements during the development process. Waterfall model is very efficient for projects that have well-known requirements at the beginning of the project. Waterfall model focuses on the constant re-evaluation of the design and risks involved. Agile model is similar to Extreme Programming model in terms of: Select One Agile model and Extreme Programming model have a fixed number of development iterations Agile model is not similar to Extreme Programming model in any way. To make sure requirements change is handled in…arrow_forward
- Explain the distinctions between planning for the short term, the intermediate term, and the long term.arrow_forwardPreparing feasibility studies, which include technical, economic, legal, operational, and schedule feasibility, is an important step in the system development life cycle. We go over these possibilities in depth in the interactive tutorials.Briefly discuss these possibilities. Also included in the economic feasibility section is a detailed cost-benefit analysis.arrow_forwardExplain why earned value management (EVM) should be used to keep track of money and how well a project is doing, and provide your best guess as to why it is not. Which of these four metrics—cost variance, schedule variance, cost performance index, and schedule performance index—should be treated as positive or negative, and how?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Fundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781285196145Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos CoronelPublisher:Cengage LearningDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning