Question
Chapter 27, Problem 27.1APE
a)
To determine
Lead Time: Lead time is the time consumed for the creation of a product. It refers to the time period between the time the order is placed and the product is completed. Lesser lead time creates a more competitive edge for the company.
Lead Time = Wait time + Process time + Queue time + Move time + Inspection Time
To Compute: The value added, non value added and lead time of this process.
b)
To determine
To Compute: The value added ratio (rounded to one place).
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Compute Lead Time
Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes:
milling and finishing. Parts are produced in batch sizes of 90 parts. A part requires 5 minutes in milling and 9 minutes in finishing. The move time between the two
operations for a complete batch is 10 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size
is reduced to 5 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round
percentages to one decimal place.
Traditional Philosophy Lean Manufacturing Philosophy
Value-added time
14
V min
14
V min
Non-value-added time
1,246 X min
46 x min
Total lead time
1,260 X min
70
V min…
Lead Time
Pockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is
4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing.
a. Compute the value-added, non-value-added, and total lead time of this process.
Value-added lead time
Non-value-added lead time
Total lead time
b. Compute the value-added ratio. Round to one decimal place.
%
minutes
minutes
minutes
Compute Lead Time
Jackson Fabricators Inc. machines metal parts for the
automotive industry. Under the traditional manufacturing
approach, the parts are machined through two processes:
milling and finishing. Parts are produced in batch sizes of
70 parts. A part requires 3 minutes in milling and 9 minutes
in finishing. The move time between the two operations for
a complete batch is 10 minutes.
Under the lean philosophy, the part is produced in a cell
that includes both the milling and finishing operations. The
operating time is unchanged; however, the batch size is
reduced to 4 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total
lead times, and the value-added ratio under the traditional
and lean manufacturing methods. If required, round
percentages to one decimal place.
Value-added time
Non-value-added time
Total lead time
Value-added ratio (as a percent)
Traditional Philosophy Lean Manufacturing Philosoph
min
min
0000
min
min
%
min
min
%
Chapter 27 Solutions
EBK FINANCIAL & MANAGERIAL ACCOUNTING
Ch. 27 - Prob. 1DQCh. 27 - Prob. 2DQCh. 27 - Why is a product-oriented layout preferred by lean...Ch. 27 - Prob. 4DQCh. 27 - Prob. 5DQCh. 27 - Why would a lean manufacturer strive to produce...Ch. 27 - Prob. 7DQCh. 27 - Prob. 8DQCh. 27 - Prob. 9DQCh. 27 - Why is the direct labor cost category eliminated...
Ch. 27 - Prob. 11DQCh. 27 - Prob. 12DQCh. 27 - Prob. 13DQCh. 27 - Prob. 27.1APECh. 27 - Prob. 27.1BPECh. 27 - Prob. 27.2APECh. 27 - Lean features Which of the following are features...Ch. 27 - Lean accounting The annual budgeted conversion...Ch. 27 - Prob. 27.3BPECh. 27 - Prob. 27.4APECh. 27 - Prob. 27.4BPECh. 27 - Process activity analysis Lexter Company incurred...Ch. 27 - Prob. 27.5BPECh. 27 - Prob. 27.1EXCh. 27 - Prob. 27.2EXCh. 27 - Lean principles Active Apparel Company...Ch. 27 - Lead time analysis Palm Pals Inc. manufactures toy...Ch. 27 - Reduce setup time Hammond Inc. has analyzed the...Ch. 27 - Calculate lead time Flint Fabricators Int....Ch. 27 - Calculate lead time Williams Optical Inc. is...Ch. 27 - Prob. 27.8EXCh. 27 - Prob. 27.9EXCh. 27 - Prob. 27.10EXCh. 27 - Prob. 27.11EXCh. 27 - Lean principles for a restaurant The management of...Ch. 27 - Prob. 27.13EXCh. 27 - Prob. 27.14EXCh. 27 - Prob. 27.15EXCh. 27 - Prob. 27.16EXCh. 27 - Prob. 27.17EXCh. 27 - Prob. 27.18EXCh. 27 - Prob. 27.19EXCh. 27 - Prob. 27.20EXCh. 27 - Process activity analysis The Brite Beverage...Ch. 27 - Prob. 27.22EXCh. 27 - Prob. 27.23EXCh. 27 - Prob. 27.1APRCh. 27 - Lead time Sound Tek Inc. manufactures electronic...Ch. 27 - Lean accounting Formula One Displays Inc....Ch. 27 - Pareto chart and cost of quality report for a...Ch. 27 - Prob. 27.1BPRCh. 27 - Lead time Master Chef Appliance Company...Ch. 27 - Lean accounting Com-Tel Inc. manufactures and...Ch. 27 - Pareto chart and cost of quality report for a...Ch. 27 - Prob. 27.1CPCh. 27 - Prob. 27.2CPCh. 27 - Prob. 27.3CPCh. 27 - Prob. 27.4CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 4 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Traditional Philosophy Lean Manufacturing Philosophy min min min % min min min %arrow_forwardCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 85 parts. A part requires 4 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Traditional Philosophy Lean Manufacturing Philosophy min min 1,201 ✓ min % 0900 70 min…arrow_forwardCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time fill in the blank 1 min fill in the blank 2 min Non-value-added time fill in the blank 3 min fill…arrow_forward
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 90 parts. A part requires 4 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 9 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 3 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy min. Value-added time. Non-value-added time Total lead time Value-added ratio (as a percent) min min min % 0000 min min %arrow_forwardCompute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 5 minutes 8 minutes 4 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes. Value-added time 3 minutes The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Non-value-added time Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and…arrow_forwardCompute Lead Time Isaacson Dental Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 50 units. The process time for each step is as follows: 6 minutes 12 minutes 9 minutes 3 minutes Process Step 1 Process Step 2 Process Step 3 Process Step 4 The time required to move each batch between steps is 6 minutes. In addition, the time to move raw materials to Process Step 1 is also 6 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 50 units to 2 units. The time required to move each batch between steps and the inventory locations will be reduced to 1 minute. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches.…arrow_forward
- 1. ABC Co. manufactures desks in the finishing and assembly process. Desks are manufactured in 20 unit batches. The finishing time is 12 minutes and the assembly time is 8 minutes per desk. It takes 20 minutes to move a batch of desks from finishing to assembly. (a) Compute the value added, non-value added, and total lead time of this process. (b) Compute the value-added ratio (round to one decimal place if necessary). (c) A study was conducted resulting in the following changes: Desks made in 30 unit batches Finishing time reduced to 8 minutes Move time reduced to 16 minutes Compute the total lead time and value added ratio after the process changes: 2. Johnny Co. operates under the lean philosophy. As a result, it has a production cell for its power drills. The…arrow_forwardCalculate Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 64 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 7 minutes 5 minutes 4 minutes 9 minutes. The time required to move each batch between steps is 12 minutes. In addition, the time to move raw materials to Process Step 1 is also 12 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 12 minutes. The new lean layout will allow the company to reduce the batch sizes from 64 units to 4 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Determine the value-added, non-value-added, and total lead…arrow_forwardPockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is 4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process. Line Item Description Lead Time Value-added lead time fill in the blank 1 minutes Non-value-added lead time fill in the blank 2 minutes Total lead time fill in the blank 3 minutes b. Compute the value-added ratio. Round to one decimal place.fill in the blank 1 of 1%arrow_forward
- Lead Time Rough Riders Inc. manufactures jeans in the cutting and sewing process. Jeans are manufactured in 50-jean batch sizes. The cutting time is 6 minutes per jean. The sewing time is 15 minutes per jean. It takes 5 minutes to move a batch of jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time minutes Non-value-added lead time minutes Total lead time minutes b. Compute the value-added ratio. Round to one decimal place. %arrow_forwardMCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 11 minutes Inspection time: 12 minutes Rework time: 12 minutes 1. MCE is 0.42 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time fill in the blank minutes Actual cycle time 0.3 minutes MCE fill in the blankarrow_forwardEyring Manufacturing produces a component used in its production of washing machines. The time to set up and produce a batch of the components is two days. The average daily usage is 800 components, and the maximum daily usage is 875 components. Required: Compute the reorder point assuming that safety stock is carried by Eyring Manufacturing. How much safety stock is carried by Eyring?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License