![Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)](https://www.bartleby.com/isbn_cover_images/9780135639221/9780135639221_largeCoverImage.gif)
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
11th Edition
ISBN: 9780135639221
Author: Jay Heizer, Barry Render
Publisher: PEARSON+
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 12DQ
Students are sometimes confused by the concept of critical path, and want to believe that it is the shortest path through a network. Convincingly explain why this is not so.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Students are sometimes confused by the concept of critical path, and want to believe that it is the shortest path through a network. Convincingly explain why this is not so.
Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations.
Activity
Predecessor
Duration in Weeks
A
-
5
B
-
3
C
A, B
8
D
C
3
E
-
4
F
E
10
G
F
8
H
E
18
I
D
20
J
D, G, I
7
K
I
5
L
H
10
6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation:
the first pic:
First: Draw the precedence diagram.
Second: Using the notation given identify the duration of the project: you can type it.
Third: identify the critical part and explain the critical path.
Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found.
6B. Draw the project’s Gantt chart
First: The…
In the cpm network diagram given below:
a-Find the critical path and show it on the diagram.
b-(2-3) Determine the floats of its activity.
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The utility data for a network are given below. Determine the total, free, independent and interfering floats and identify the critical path. Activity 0-1 1-2 1-3 2-4 2-5 3-4 3-6 4-7 5-7 6-7 Duration 2 8. 10 6. 7 5 8. 3. 3.arrow_forward(a) The critical path for the network activities shown below is? (b) What is the completion time in weeks? Refer attached image Activity Preceding Time A - 8 B - 10 C A , B 5 D B 8 E C , D 6arrow_forwardDraw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D…arrow_forward
- Make a list of the tasks that is necessary to build a duplex house (around 3000 sft) for you. Develop a table showing each task, its duration, preceding event(s), and expected duration. Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardDraw CPM network of activities tabulated below: 1. Calculate the expected duration and the standard deviation for the critical path.arrow_forward
- The following information is given for a CPM network: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A --- B, C 5 $ 60 2 $ 125 B A D, C 4 70 2 90 C A, B D 6 80 3 150 D B, C --- 3 40 1 60 What is the critical path of the network?arrow_forwardMake a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardThe following represent activities in a major construction project. Draw the network to represent this project. Activity Immediate Predecessor A - B - C A D B E B F C, E G D H F, Garrow_forward
- The following CPM network has estimates of the normal time in weeks listed for the activities: A(7) B(4) Node A B C D E F G C(2) D(5) F(2) Early Early Start Finish E(4) 1. Identify the critical path and show your answer. Please compute the early start, early finish, late start, late finish time for each node (activities) and Write your answer in the following table. (You may type your answer in a table in MS Word and then paste in the answer box below. Late Start Late Finish G (6) 2. What is the length of time to complete the project? 3. Which activities have slack, and how much?arrow_forwardQ1: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7| 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50%]arrow_forwardHow does activities along the critical path of a network diagram impacts the project as a whole?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY