Textbook Question
Chapter 3, Problem 5P
Draw the activity-on-node (AON) project network associated with the following activities for Carl Betterton’s construction project. How long should it take Carl and his team to complete this project? What are the critical path activities?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Draw the activity-on-node (AON) project networkassociated with the following activities for Carl Betterton’sconstruction project. How long should it take Carl and histeam to complete this project? What are the critical pathactivities?
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s)
A
(BCDEFG
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
c) The project length for the leadership training program development project =
d) Slack time for each of the activities is:
days.
B
A, D
с
E, F
Activity
A
B
CDEFG
Slack Time
Time (days)
3
GANGG
5
2
10
4
8
A farm owner is going to erect a maintenance building with connecting electrical gen-
erator and water tank. The activities, activity descriptions and estimated durations are
given in the following table. Construct the AOA network for this project, identify the
critical path and construct a Gantt chart for the project.
Description
Excavate
Erect building
Install generator
Install tank
Activity
A
Predecessor Duration
2
B
A
6
A
4
D
A
E
Install maintenance equipment
В
4
F
Connect generator and tank building
B,C,D
5
G
Paint finish
В
3
H
Check out facility
E,F
2
Chapter 3 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Draw the AON project network using the following information: How long would it take to complete this project? Which activities are included on the critical path?arrow_forwardConstruct an AON project network for the following set of activities. Analyze the project network, answer the following questions. Activity Activity Predecessor I 3 4 S 6 7 8 9 1 2 3 3 4.5.6 2 S Which of the following is a critical path? O2->5->8 1->4->8 Time (months) 4 7 8 3 9 O 1->3->7 O 1->3->6->8 2arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. Activity A B C ס ח ד 0 F B A, D C E, F G Slack Time Time (days) 4 6 1 103510arrow_forwardA project has seven (7) main activities labelled A through G as shown in the below table which also shows their estimated duration times ( in weeks) and immediate predecessors. Activity a b Immediate Remarks predeccessor A 1 2 3 a = optimistic time 2 3 4 m = most likely time C 4 A b = pessimistic time 8 9 10 E 2 5 8 C,D 4 6. G 1 2 3 E (a) Develop a project network for this problem.arrow_forwardA Company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Construct the project network and identify the critical path and its duration. Activity Predecessors Duration(wks) A: forecast sales volume - 10 B: study competitive market - 7 C: design item and facilities A 5 D: prepare production schedule C 3 E: estimate cost of production D 2 F: set sales price B,E 1 G: prepare budget E,F 14 (4) A project consists of the following activities, with the duration, in weeks, of each activity given in brackets. A(6), B(4) and C(7), the first activities of the project, can be executed concurrently. A and B precede D(2). B precedes E(1), F(5) and H(8). F and C precede G(3). E and H precede I(2) and J(4). C, F and J precede K(2). K precedes L(4).D, I, G and L are the terminating activities if the project. Construct the precedence table, and hence draw the network for the project Determine the critical…arrow_forward
- Analyze projects using network-planning models?arrow_forwardUsing the network shown and the activity durations shown in the table below, what is the overall duration?arrow_forwardRoger Ginde is developing a program in supplychain management certification for managers. Ginde haslisted a number of activities that must be completed beforea training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in theaccompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forward
- The following is the data available for a project: Activity Predecessor Expected Duration (Days) A - 12 B A 9 C B,E 3 D - 10 E D 6 F E 3 G - 2 H G 9 I E,H 2 Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity. Draw the network diagram for the project and determine the critical patharrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forwardDraw the network diagram, and find out the critical path and project duration?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY