Chapter 3, Problem 18M
Program Description Answer
Program Evaluation and Review Technique (PERT) is a method used to calculate the expected time for a particular task using optimistic, pessimistic, and realistic time estimates.
Hence, correct answer is “PERT”.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
While working on a project, it might be challenging for a software engineer to provide an accurate cost estimate for that project.
The method of managing projects involving software development is slightly distinct from the process of managing other sorts of projects.
The method of managing projects involving the creation of software is slightly distinct from the process of managing other kinds of projects.
Chapter 3 Solutions
Pearson eText for Essentials of Systems Analysis and Design -- Instant Access (Pearson+)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- step by step guide tor method to develop a smart list ( include a detailed plan for the implementation with specific technique/technology/software/ application/ hardware etc.)arrow_forwardSoftware Engineering As a programmer, you are offered promotion to a project management position but you feel that you can make a more effective contribution in a technical rather than a managerial role. Discuss in detail whether you should accept the promotion.arrow_forwardExplain the importance of code refactoring in software development. Provide a real-world scenario where code refactoring led to significant improvements in a project.arrow_forward
- Project Management Tech Solutions is a company which develops software solutions for clients. Each project is associated with only one client. A minimum of two staff members must be allocated to each project. A staff member can work on many projects at the same time. Contract staff can be hired for certain projects illustrate with a diagram how this can be implemented with generalisationarrow_forwardIt's difficult for a software engineer to calculate a project's cost properly.arrow_forwardWhat is the difference between a project and routine work?arrow_forward
- Project Management System A Project management company approached your IT company for a system to keep track of their projects. It is possible for an employee to work on more than one project. Each employee will have only one job title, e.g., System analyst, Project manager, Programmer etc. The company will be working on many projects at the same time. Each project will have only one client. Each project must be managed by only one Project manager. Create a class diagram to keep track of their projects. Indicate possible attributes, operations, relationship names and multiplicities.arrow_forwardComputer Science A research report contains a comparision between project leader and manager Where best use Performance Charactrastics Specifications Skills Responsabilitearrow_forwardshort answer please compare and contrast the definition of a project versus a program.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Enhanced Discovering Computers 2017 (Shelly Cashm...Computer ScienceISBN:9781305657458Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. CampbellPublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Information Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305657458/9781305657458_smallCoverImage.gif)
Enhanced Discovering Computers 2017 (Shelly Cashm...
Computer Science
ISBN:9781305657458
Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337101356/9781337101356_smallCoverImage.jpg)
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305971776/9781305971776_smallCoverImage.gif)
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285452340/9781285452340_smallCoverImage.gif)
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning