Concept explainers
Managing Hard Rock’s Rockfest
At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rock’s constant growth in hoteb and cafes, remodeling of existing cafes,
“Without Microsoft Project.” says Hard Rock Vice-President Chris Tomasso, “there is no way to keep so many people on the same page.” Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its activities. For the first 3 months Tomasso updates his Microsoft Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9-month mark, he checks and corrects his schedule twice a week.
Early in the project management process, Tomasso identifies 10 major tasks (called level-2 activities in a work breakdown structure, or WBS):† talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. Table 3.8 identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates, Tomasso enters all these into the Microsoft Project software.‡ Tomasso alters the Microsoft Project document and the time line as the project progresses. “It’s okay to change it as long as you keep on track.” he states.
The day of the rock concert itself is not the end of the project planning. “It’s nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an ‘anticipated’ surprise. We had a helicopter on stand-by ready to fly the hand in.” says Tomasso.
On completion of Rockfest in July. Tomasso and his team have a 3-month reprieve before starting the project planning process again.
†The level-1 activity is the Rockfest concert itself
‡There are actually 127 activities used by Tomasso; the list is abbreviated for this ease study.
TABLE 3.8 Some of the Major Activities and Subactivities in the Rockfest Plan
4. Why is a work breakdown structure useful in a project such as this? Take the 26 activities and break them into what you think should be level-2, level-3, and level-4 tasks.
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
OPERTATIONS MGMT:SUSTAINABILITY
- Use the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionarrow_forwardDefine Time–Cost Models and Project Crashing?arrow_forwardDraw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and Oarrow_forward
- Develop a CPM diagram for the activities/relationships listed below (assumedurations are in months). For each activity calculate the Early Start, Late Start, EarlyFinish, Late Finish, Total Float, and Free Float. Clearly identify the critical path forthe project (hint: a highlighter would be a good tool to use) How do you solve this? I don't understand how it's done.arrow_forwardQ3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramarrow_forwardWhich project life cycle model (traditional, agile...) is more appropriate for the public and/or private sector?arrow_forward
- What information is contained in the project vision document in requirement analysis?arrow_forwardA student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)arrow_forwardYou are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1arrow_forward
- Topic: Project management Please after reading activity use this work breakdown struction below to input in gantt chart, minimum 10 task WORK BREAKDOWN STRUCTURE Main objective : training for aquaponicsIdentify 30 entrepreneurs and 10 teachers5 day work shop, practical and theoretical 1st Phase: Identification of entrepreneurs, teachers and experts - Social Media and Radio Announcements - Registration - Locate interested experts to lecture 2nd Phase: Preparation of Training Area - Identify proper training area - Set up facility for training - Contact caterers for subsequent training.- Formulate 5 day Curriculum - 3rd Phase: Training - Lectures - Practical Lessons - Testing at end of training days.4th Closure: - Award Ceremony for high performance particpants- Gifting of Certificates - Ending Ceremony. 5. Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks).arrow_forwardSchedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 1 B A 4 C A 3 D B 2 E C,D 5 F D 2 G F 2 H E,G 3 Part (a) Draw the network : Part (b) What is the critical path? Part (c) How many weeks will it take to complete the project? Part (d) What activities have slack, and how much?arrow_forwardConstruct an activity network diagram using Table 3a. Activity A B C D E F G Predecessors - - A A,B D C,E E Expected Time(WKS) 7 9 12 8 9 6 5 Table 3a Activity Durations and relationship Conduct a forward and backwards pass for the activity network diagram that you have constructed and identify the critical path and its duration. Calculate the slack on all of the activities, and proceed to analyze how knowing the slacks can help to manage schedule risk the a project 3b. Assuming that there is the risk of exceeding the project schedule baseline for 7 weeks, critically evaluates the options available that could be used to bring the project on trackarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.