•• 3.2 Robert Day has decided to run for a seat as Congressman from the House of Representatives, District 34, in Connecticut. He views his 8-month campaign for office as a major project and wishes to create a work breakdown structure (WBS) to help control the detailed
LEVEL | LEVEL ID NO. | ACTIVITY | |||
1 | 1.0 | Develop political campaign | |||
2 | 1.1 | Fund-raising plan | |||
3 | 1.11 | ----- | |||
3 | 1.12 | ----- | |||
3 | 1.13 | ----- | |||
2 | 1.2 | Develop a position on major issues | |||
3 | 1.21 | ----- | |||
3 | 1.22 | ----- | |||
3 | 1.23 | ----- | |||
2 | 1.3 | Staffing for campaign | |||
3 | 1.31 | ----- | |||
3 | 1.32 | ----- | |||
3 | 1.33 | ----- | |||
3 | 1.34 | ----- | |||
2 | 1.4 | Paperwork compliance for candidacy | |||
3 | 1.41 | ----- | |||
3 | 1.42 | ----- | |||
2 | 1.5 | Ethical plan/issues | |||
3 | 1.51 | ----- |
Help Mr. Day by providing details where the blank lines appear. Are there any other major (level-2) activities to create? If so, add an ID no. 1.6 and insert them.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
- Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With the passage to time, it focused only on chocolate production, and manufactured many innovative products. After the Second World War, it managed to export its products to 90 countries. In2006, its sales reached 5 billion dollars, and employed over 14,300 people.
The objective of the project is to deploy an ERP system covering sales and procurement process. The following is the required schedule of the event. (Marks-10)
Activity
Duration- Weeks
Immediate Predecessors
A–Select consultant for selecting system
2
_____________
B–Meet with consultant to discuss ERP
4
A
C–Meet with Board of Directors to explain proposal
1
A
D–Develop request for proposals to give to vendors
3
B,C
E–Obtain vendor proposals
4
D
F–Develop organization business cases including training
8
E
G–Present business cases to Board of Directors
1
F…
Q.1.2 Using a suitable example each, describe what the following project planning process activities involve:
a. Establish project objective;
b. Define scope;
c. Create a Work Breakdown Structure (WBS);
d. Estimate activity durations;
e. Sequencing activities.
1. Prepare the Activity Node Diagram and identify the Critical Path2. Prepare Gantt ChartThankss
Chapter 3 Solutions
Operations Management, Student Value Edition & Student Cd For Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 2- How might the project team recommending an ERP design strategy justify its recommendation as compared with other types of design strategies?arrow_forwardQ1: What basic features are necessary for an ERP product? And, are these features important?arrow_forwardExplain in detail each element of an MRP system ?arrow_forward
- A. target Completion Date B. Critical Path Method C. create two ways of network Diagramarrow_forwardProblem 13-3 (Static) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amounton Hand Direct Components End 1 − L(2), C(1), K(3) L 2 10 B(2), J(3) C 3 15 G(2), B(2) K 3 20 H(4), B(2) B 2 30 J 3 30 G 3 5 H 2 − Click here for the Excel Data File a. If 40 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)arrow_forwardInstruction: a. Construct AON diagram for the following data.b. Identify critical path.c. Conduct CPM analysis by identifying ES, EF, LS, LF, Slack time to confirm the critical path.arrow_forward
- Q.1. Draw AOA diagram and find the critical path. Q.2. What will be the project duration?arrow_forwardmake the project start date 3 Jan 2022 Level the following multi-project operation. Work package Description Duration (weeks) Predecessors Resources A1 Analysis & design – Proj 1 4 - SAD B1 Production – Proj 1 7 A1 PROD C1 Testing – Proj 1 3 B1 TEST D1 Install – Proj 1 2 C1 INSTALL A2 Analysis & design – Proj 2 4 A1 SAD B2 Production – Proj 2 5 A2 PROD C2 Testing – Proj 2 3 B2 TEST D2 Install – Proj 2 1 C2 INSTALL A3 Analysis & design – Proj 3 8 A2 SAD B3 Production – Proj 3 12 A3 PROD C3 Testing – Proj 3 5 B3 TEST D3 Install – Proj 3 3 C3 INSTALL A4 Analysis & design – Proj 4 8 A3 SAD B4 Production – Proj 4 10 A4 PROD C4 Testing – Proj 4 4 B4 TEST D4 Install – Proj 4 2 C4 INSTALL show the schedual before the leveling show the schedual of the project after leveling…arrow_forwardWork Breakdown Structure (WBS) for "Enhancing Rural Communities Health & Agriculture Development Project" Question: Use the Information and create a WBS chart for the project Project Initiation 1.1 Project Approval and Kickoff 1.2 Team Assignment and Roles Definition 1.3 Initiate Stakeholder Meetings and Engagements Project Planning 2.1 Define Project Objectives and Goals 2.2 Develop Project Management Plan 2.3 Risk Assessment and Management Strategy 2.4 Resource Identification and Allocation 2.5 Budget Planning and Allocation 2.6 Communication Plan Development 2.7 Schedule Planning and Timeline Setting 2.8 Scope Management Plan 2.9 Quality Assurance Plan 2.10 Change Control Management Plan Healthcare Improvement 3.1 Community Health Assessment 3.2 Medical Staff Recruitment and Training 3.3 Medical Resource Procurement and Distribution 3.4 Health Education Campaigns 3.5 Healthcare Facility Improvement Agricultural Development 4.1 Soil and Water Analysis 4.2 Agricultural…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY