Operations Management, Student Value Edition & Student Cd For Operations Management
11th Edition
ISBN: 9780133407983
Author: HEIZER, Jay
Publisher: Pearson College Div 2013-03-08
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 26P
The Tesla 6 is a new custom-designed sports car. An analysis of the task of building the Tesla 6 reveals the following list of relevant activities, their immediate predecessors, and their duration:2
2 Source: Adapted from James A. D. Stoner, Management, 6th ed. (Upper Saddle River, NJ: Pearson 1995).
- a. Draw a network diagram for the project.
- b. Mark the critical path and state its length.
- c. If the Tesla 6 had to be completed 2 days earlier, would it help to:
- i) Buy preassembled transmissions and drivetrains?
- ii) Install robots to halve engine-building lime?
- iii) Speed delivery of special accessories by 3 days?
- d. How might resources be borrowed from activities on the noncritical path to speed activities on the critical path?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Draw a network diagram showing the linkage between these activities from start to finish. For the diagram, each activity should be labelled alphabetically ie. A, B, C… etc.
PERT Formula:
TE = (O + 4T + P) / 6
TE = Pert Expected Time Duration,
O = Optimistic estimate,
P = Pessimistic estimate,
T = Most Likely (Typical) estimate
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
Duration
Duration in Weeks
A
—
2
3
4
B
—
4
5
7
C
B
1
2
3
D
C & E
0.5
1
1.5
E
B
0.5
1
1.5
F
C
2
3
4
G
F
2
3
4
Exercise 8: Given the following network,
refer to the pic please
(a) What is the critical path?
(b) How long will it take to complete this project?
(c) Can activity B be delayed without delaying the completion of the project? If so, how
many days?
3.7 Task time estimates for a production line setup project at Robert Klassen’s Ontario factory are as follows: Activity A, B,C,D,E,F,G. Time(in hours) 6.0,7.2,5.0,6.0,4.5,7.7,4.0 Immediate Predecessors -,-,A)B,C)B,C)D)E,F) a. Draw the project network using AON. b. Identify the critical path. c. What is the expected project length? d. Draw a Gantt chart for the project.
Chapter 3 Solutions
Operations Management, Student Value Edition & Student Cd For Operations Management
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities of a project and their durations. Table 1Activity Preceding Activity Duration (Days)A – 9B – 3C A 8D A 2E A 3F C 2G C 6H C 1J B,D 4K F,J 1L E,H,G,K 2M E,H 3N L,M 4 i. Draw the project network.ii. Determine its critical path and completion time.iii. Calculate the total float for the non-critical chains. 2. a) Outline FOUR different types of stockholding casts. b) i) Explain the periodic review system of inventory control.ii) State TWO disadvantages of the periodic review system. c) Explain FOUR major functions of an office. d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team. 3. a) State FOUR objectives of maintenance in a manufacturing plant. b) Explain the purpose of the…arrow_forwardTable 7.8 contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $15,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week 9.a. What is the shortest time duration for this project regardless of cost?b. What is the minimum total cost associated with completing the project in 9 weeks?c. What is the total time of the minimum-cost schedule?arrow_forwardTo be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeksarrow_forward
- The Virginia Department of Transportation is undertaking aconstruction project to widen a large section of interstate, highway near Washington, DC, which includes the construc-tion of a number of new bridges, interchanges, and over-passes. The first step in the project is the appointment of a project manger and the development of a project team, someof which will be departmental employees and others will beprivate consultants and operatives. The team for a project thissize also requires a large support staff with varying technicalskills. Once the team is selected and the staff is in place the first task is to select a primary contractor to manage and over-see the actual construction. The following activities are stan-dard for the planning and scheduling of this process: Construct the CPM/PERT network for this project and de-termine the project schedule. Identify the critical path and determine the expected project duration time and variance.Determine the probability that the team and…arrow_forward(1) Define critical path, ES, EF, LS, LF, dummy activity and slack. (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical patharrow_forward5. The accompanying information is available about a project to organize an event to honor the mayor of West Allis at the Nathan Hale High School. a. Choose the correct network diagram for this project. b. Find the critical path.arrow_forward
- Construct a network diagram for this project? TABLE 1: Activities and duration project Duration in weeks __________________________________ Activity Proceeding activity Optimistic Most likely Pessimistic A - 2 3 3 B - 10 12 15 C A 4 5 8 D B 2 2 2 E A, D 3 3 3 F…arrow_forwardQ: (a) How value engineering can reduce overall project duration? Can you give any practical example? (b) What will be the difference in duration of dummy activity for simple and complex arrow networks? (c) Draw arrow network for the following given project. Picture of table is attached at the end.arrow_forward- Draw the project network diagram. - What completion date would you recommend?arrow_forward
- Consider the following data for a project to install a newserver at the Northland Pines High School: a. Draw the network diagram.b. Calculate the critical path for this project.c. How much slack is in each of the activities G, H, and I?arrow_forwardBRIEF DESCRIPTION OF THE PROJECT The construction industry represents the foundation of every infrastructure thatstands today. Each piece of architecture depicts its time, history, and style. It shows how far humans have gone and how brilliant our minds can build something complex out ofscratch. From past to present-day architecture, it signifies uniqueness and creativity thatmade them remarkable. Today’s architecture requires modern materials to beaccurate and sustainable.With that remark, Bio Industries is proposing Bio-Bricks. Bio-Bricks is anenvironmentally friendly brick that is made up of air-dried animal feces. The animalwastes are specifically from household pets such as dogs and cats, and animals fromfarms to support local farmers. 80% of the ingredient consists of animal feces, and the remaining 20% contains sand to harden the material. Consumers can alsocustomize the brick’s color and shape to satisfy their preferences and to let them expresstheir creativity. What are the…arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY