Chapter 3, Problem 32P
a)
Summary Introduction
To calculate:The project completion date.
Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.
b)
Summary Introduction
To calculate:The lowest cost of crashing so that the project is completed in 10 weeks.
c)
Summary Introduction
To Find:The lowest cost of crashing the project completion time to 7 weeks.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
you decide to estimate duration and standard deviation of a project using PERT method. the project has 3 steps the following are the optimistic, most likely and pessimistic durations in weeks:step 1: 2,5,10Step 2: 1,3,13Step3: 7,8,11,what is the estimated duration and standard deviation of the project duration?Estimated Duration =16 standard Deviation =4.9Estimated Duration =18 standard Deviation =4.9Estimated Duration =18 standard Deviation =2.49Estimated Duration =16 standard Deviation =24
11. Using​ PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is
24
​months, and the project variance is
4.
Part 2
​a) The probability that the project will be completed in
20 months​ = ______
​(round your response to four decimal​ places)
A project has the following tasks and duration estimates given. These three tasks are done in succession on a project.
Â
Task
Optimistic Estimate
Most Likely Estimate
Pessimistic Estimate
Alpha
30 days
40 days
50 days
Beta
20 days
25 days
28 days
Charlie
4 days
10 days
12 days
Delta
25 days
30 days
50 days
Â
What is the expected duration for the project? (3 points)
Â
Â
Â
What is the variance for the project? (3 points)
Â
Â
Â
What is the standard deviation of the project? (3 points)
Â
Â
What is the range of the duration of the project given 3 sigma? (3 points)
Chapter 3 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (10th Edition)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?arrow_forwardThe following table describes project XYZ Â Â Duration Predecessor Variance A 5 Â 2 B 3 A 1 C 13 A 6 D 18 B 2 E 10 B 4 F 4 D, E 1 G 11 C, E 5 H 9 F, G 2 I 2 H 1 Â Based on the information provided, perform the following tasks: Identify the crucial path and project duration Calculate probability that the project in going to be completed after the day 45arrow_forward2. Compute the followings: (a) The probability that the project will finish by the end of day 50 (b) The probability that the project will finish at day 52 (c) The probability that the project will finish before the start of day 49. (d) The completion date with at least a 95% confidence levelarrow_forward
- Management Firm is a consulting company that specializes in the development of decision support systems.     Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation  2 8 12 B Web scraping  4 9 11 C Testing A, B 1 1 1  (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)  (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)arrow_forwardd) Risk is defined as the uncertain event or condition that if occurs has a positive or negativeeffect on the project's objective. The project objectives can be classified into three; cost,schedule and performance. There are 5 steps on risk identification process which startfrom identification and end with monitoring.Based on these three project objectives please explain the project risk managementprocess.explain it briefly and include examplearrow_forwardDan, the project manager, has indicated in a planning meeting that the team should identify and avoid any circumstances of ‘scope creep.’ What does Dan means? Select one: a. He does not want the team members to discuss the project scope with other project stakeholders b. He wants to be the only person responsible for scope management throughout the project duration c. He wants the team members to make any changes to the project scope that they deem necessary d. He does not want the continuous or uncontrolled growth and changes in the project's scope at any point after the project beginsarrow_forward
- Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?arrow_forwardUse the information in this table to calculate the weighted score for project 2 Criteria Weight Project1 Project2 Project3 Project4 Supports of key business objectives 5% 90 90 50 20 Has strong internal sponsor 10% 70 90 50 20 Has strong customer support 5% 50 90 50 20 Realistic level of technology 10% 25 90 50 70 Can be implemented in one year or less 30% 20 20 50 90 Provides positive NPV 10% 50 70 50 50 Has low risk in meeting scope, time, and cost goals 30% 20 50 50 90arrow_forwardThe project manager of a task force planning the construction of a domed stadium had hopedto be able to complete construction prior to the start of the next college football season. Afterreviewing construction time estimates, it now appears that a certain amount of crashing will beneeded to ensure project completion before the season opener. Given the following time and costestimates, determine a minimum-cost crashing schedule that will shave five weeks off the projectlength. Note: No activity can be crashed more than two weeks.CRASHING COSTS ($000)Activity Immediate Predecessor Normal Time (weeks) First Week Second WeekA — 12 $15 $20B A 14 10 10C — 10 5 5D C 17 20 21E C 18 16 18F C 12 12 15G D 15 24 24H E 8 — —I F 7 30 —J I 12 25 25K B 9 10 10M G 3 — —N H 11 40 —P H, J 8 20 20End K, M, N, Parrow_forward
- Briefly explain the goal of the project then discuss the importance of the following  in a Project Proposal, providing two examples for each element:  A. Expected benefits.  B. Risksarrow_forwardI also know answer is d, but please explain each and every option why other option are incorrect too. Which of the following statements regarding PERT analysis is true?  Each activity has two estimates of its duration. Project variance is the sum of all activity variances. Project standard deviation is the sum of all critical activity standard deviations. Only critical activities contribute to the project variance. none of these is true.arrow_forwardScope creep and feature creep are two unfavorable outcomes that may result from this. To make the distinction between the two ideas evident, explain them. What is the primary reason behind these two issues? What happens in this project's worst-case scenario if these two unfavorable circumstances arise?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY