Principles of Operations Management: Sustainability and Supply Chain Management, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (10th Edition)
10th Edition
ISBN: 9780134467283
Author: HEIZER, Jay, RENDER, Barry, Munson, Chuck
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 12DQ
Students are sometimes confused by the concept of critical path, and want to believe that it is the shortest path through a network. Convincingly explain why this is not so.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
(a) The critical path for the network activities shown below is?
(b) What is the completion time in weeks?
Refer attached image
Activity
Preceding
Time
A
-
8
B
-
10
C
A , B
5
D
B
8
E
C , D
6
SUBJECT: SOFTWARE ENGINEERING
For a particular project, consider following list of Activities, their duration in Days and their Predecessor
Activity
Days
Precedents
a
3
-
b
15
A
c
5
A
d
60
A
e
6
D
f
40
B
g
10
c, e
h
7
F
i
6
G
j
12
h, i
By using network schedule technique, draw a Network Diagram of above enlisted activities.
Find Critical Path , earliest start, earliest finish , latest start and latest finish from Network Diagram.
The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity.
a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?
Chapter 3 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (10th Edition)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A project is represented by the following diagram: 2. The critical path for the network shown is: A. 1-3-6-7. B. 1-2-4-7. C. 1-4-7. D. 1-3-4-7. E. 1-2-5-7.arrow_forwardDetermine the critical path after you have found ES, EF, LS, LF and slack. State the path and time expected to be taken.arrow_forwardFor the activity times and network model below, What is the expected completion time? ________ What is the critical path? ____________ Activity Time A 3 B 2 C 2 D 4 E 3 F 2arrow_forward
- Draw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D…arrow_forward1. Draw the network diagram and determine the critical path for the project below:arrow_forwardDraw a network diagram for the project. Find the minimum project completion time. Identify the critical activities and critical path.arrow_forward
- Make a list of the tasks that is necessary to build a duplex house (around 3000 sft) for you. Develop a table showing each task, its duration, preceding event(s), and expected duration. Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardSuppose you are a project manager, and you have to manage a project with activities and their respective durations in weeks as listed in Table below. Construct a precedence network diagram to analyze your project. please do it hand writtenarrow_forwardThe following information is given for a CPM network: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A --- B, C 5 $ 60 2 $ 125 B A D, C 4 70 2 90 C A, B D 6 80 3 150 D B, C --- 3 40 1 60 What is the critical path of the network?arrow_forward
- The following information is available about a project to organize an event to honor the mayor of West Allis at the Nathan Hale High School:a. Draw the network diagram. b. Find the critical path.arrow_forwardThe following information is available about a project to organize an event to honor the mayor of West Allis at the Nathan Hale High School: a. Draw the network diagram.b. Find the critical path.arrow_forwardBased on the table above, draw a complete Activity-in-the-Box network diagram using the ID's to represent each activity.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY