Refer to the table in Problem 3.8.
- a. Draw the AON network for the construction activity.
- b. Draw the AOA network for the construction activity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You are alone at home and have to prepare a bread sandwich for yourself. The following preparation activities and time taken are given in the table below:
Determine the following:a. Create the network diagram for the table aboveb. Determine the critical activities and preparation time for tasks given in the table
Engineering Management ,i need solutions in 10 minutes please.
MCQ/ For the construction project represented by the activity network as shown below. Find one of the critical paths CP from the choices below.
A-1-3-6-8-9
B-1-2-4-6-9
C-1-2-4-6-7-9
D-1-2-4-6-8-9
E-1-3-4-6-9
F-1-3-45-7-9
Hi there! Could you please help me at my activity. I kinda have difficulties in doing the network diagram. The question below is the thing that is about to have an answer. The image will show the table above and below that we need to consider to be able to solve the problem. Hope for soonest reply. Thanks!
ACTIVITY 2:
Consider the following immediate preceding activity table. Draw the network and calculate the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activity. Obtain the critical path.
Note: the things to consider in the picture is only the activity 2. No need to consider the summative test 3 below. Thanks a lot!
Chapter 3 Solutions
OPERATIONS MGMT - FIRST DAY
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - Prob. 2PCh. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Prob. 8PCh. 3 - Task time estimates for the modification of an...Ch. 3 - The activities described by the following table...Ch. 3 - The following is a table of activities associated...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- *(e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a table) for each of the activities by d: early start (ES), early finish (EF), late start (LS), late finish (LF) and total floats and total slacks and provide them in a table form. Answer:arrow_forwardPrepare Arrow network for the data given below. (AOA) Also write down notations of all the activities on arrow network. Activity IPA A - B - C A D A,B E C,Darrow_forwardUsing AOA, diagram the network described belowfor Lillian Fok's construction project. Calculate its cr itical pathand project completion time.arrow_forward
- *(e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a table) for each of the activities by d: early start (ES), early finish (EF), late start (LS), late finish (LF) and total floats and total slacks and provide them in a table form.arrow_forwardSection A - Please answer # 1. Draw a Network Diagram (Network Programming)arrow_forwardDraw a network diagram for the following problem: The hospital administrator at St. Charles General must appoint head nurses to three newly established departments. The costs for all assignments are given in the following table. Find the best assignment of nurses to departments while minimizing the cost.arrow_forward
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?arrow_forwardThe Mobicom Corporation is in the design phase of a system project. The project manager wants to develop a network analysis diagram to plan the activities of designing the system outputs. The activities are as follows. ACTIVITY PRECEDING TIME[WEEKS] A ----- 5 B ---- 6 C ---- 4 D A,B 7 E C 8 F C,D 10 G D 8 Required Draw a network diagram for the design phasearrow_forwardDifferent construction activities are given in a table below. Please draw arrow network possible relationship. with best logical clear representation of activities is required.arrow_forward
- The following represent activities in a major construction project. Draw the network to represent this project. Activity Immediate Predecessor A - B - C A D B E B F C, E G D H F, Garrow_forwardBased on the table, redraw critical path of the network by clearly indicating the activities involved.arrow_forwardOPERATIONS Duration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 Use either PERT or CPM to (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Re-schedule the activities for smooth development (iii) Find the project schedule if only 4 men are availablearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY