Textbook Question
Chapter 3, Problem 6P
Given the activities whose sequence is described by the following table, draw the appropriate activity-on-arrow (AOA) network diagram.
- a. Which activities are on the critical path?
- b. What is the length of the critical path?
ACTIVITY | IMMEDIATE PREDECESSOR(S) | TIME (DAYS) | ||
A | - | 5 | ||
B | 2 | |||
C | 4 | |||
D | 5 | |||
E | 5 | |||
F | 5 | |||
G | E, F | 2 | ||
H | 3 | |||
I | G, H | 5 |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Given the activities whose sequence is describedby the following table, draw the appropriate activity-on-arrow (AOA) network diagram.a) Which activities are on the critical path?b) What is the length of the critical path?
A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below.
Activity
Duration (days)
Preceding activities
A
3
None
B
3
None
C
4
A
D
8
A
E
2
B and C
Required:
1. Draw a network diagram representing the sequence of activities and the dependence between them.
2. Determine how long it will take to complete the job by conducting the forward pass
3. By conducting the backward pass, identify the critical path and the non-critical path(s).
Note:
The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.
Given the activities whose sequence is described by thefol lowing table, draw the appropriate activity-on-arrow (AOA)network diagram.a) Which activities are on the critical path?b) What is the length of the critical path?
Chapter 3 Solutions
OPERATIONS MANAGEMENT-ACCESS >CUSTOM<
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - Prob. 2PCh. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Prob. 8PCh. 3 - Task time estimates for the modification of an...Ch. 3 - The activities described by the following table...Ch. 3 - The following is a table of activities associated...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- An electronic contractor is examining the amount of time his crews take to complete wiring jobs. Some crews take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table. Days Activity a m b Immediate Predecessors A 2 5 8 - B 1 3 5 - C 1 2 3 - D 5 6 7 C E 1 3 5 B, D F 5 9 13 A, E G 1 2 3 A, E H 2 5 8 F I 9 10 11 G J 13 15 20 G K 4 7 10 H, I a) Develop a project network for this problem. b) Determine the expected duration and variance for each activity. c) Determine the EST, EFT, LST, LFT, and slack for each activity. d) What is the critical path and project completion time? e) What is the probability that the job will finish in 33 days or less? f) Submit your excel filearrow_forwardAn electronic contractor is examining the amount of time his crews take to complete wiring jobs. Some crews take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table. Days Activity a m b Immediate Predecessors A 2 5 8 - B 1 3 5 - C 1 2 3 - D 5 6 7 C E 1 3 5 B, D F 5 9 13 A, E G 1 2 3 A, E H 2 5 8 F I 9 10 11 G J 13 15 20 G K 4 7 10 H, I a) Develop a project network for this problem. b) What is the critical path and project completion time? c) What is the probability that the job will finish in 33 days or less?arrow_forwardAn electronic contractor is examining the amount of time his crews take to complete wiring jobs. Some crews take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table. Days Activity a m b Immediate Predecessors A 2 5 8 - B 1 3 5 - C 1 2 3 - D 5 6 7 C E 1 3 5 B, D F 5 9 13 A, E G 1 2 3 A, E H 2 5 8 F I 9 10 11 G J 13 15 20 G K 4 7 10 H, I Use excel to answer the following; a) Develop a project network for this problem. b) Determine the expected duration and variance for each activity. c) Determine the EST, EFT, LST, LFT, and slack for each activity.arrow_forward
- An electronic contractor is examining the amount of time his crews take to complete wiring jobs. Some crews take longer than others. For an upcoming job, a list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table. Days Activity a m b Immediate Predecessors A 2 5 8 - B 1 3 5 - C 1 2 3 - D 5 6 7 C E 1 3 5 B, D F 5 9 13 A, E G 1 2 3 A, E H 2 5 8 F I 9 10 11 G J 13 15 20 G K 4 7 10 H, I a) Develop a project network for this problem. b) Determine the expected duration and variance for each activity. c) Determine the EST, EFT, LST, LFT, and slack for each activity. d) What is the critical path and project completion time? e) What is the probability that the job will finish in 33 days or less?arrow_forward1. For the following Activity table draw the CPM diagram Using Activity On Node. Show the ES, LS, EF, LF and Slack for each activity on the diagram. Indicate the Critical path. Activity Time (Days) Predecessor A 4 ------------ B 7 A C 8 A D 2…arrow_forwardUsing the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A - 32 B - 11 C - 12 D B,C 16 E A,B 23 F A 23 G D 22 H D 33arrow_forward
- The activities needed to replace a broken window pane are given below. Activity Duration (in mins) Preceding activities A Order glass 10 - B Collect glass 30 A C Remove broken pane 15 B,D D Buy putty 20 - E Put putty in frame 3 C F Put in new frame 2 E G Putty outside and smooth 10 F H Sweep up broken glass 5 C I Clean up 4 all (a) Construct an activity network for the project. (b) What is the minimum time to complete the replacement? (c) Show the Earliest Start Time and Latest Finish Time of each activity.arrow_forwardAn activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =43, LF C = 51; activity times are A = 4, B = 6, C = 8 a. 32 b. 35 c. 33 d. 37 e. Insufficient informationarrow_forwardPlease help in details!! Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown. Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 5 6 B 2 4 6 C A, B 6 7 8 D A, B 8 10 11 E B 2 4 6 F C 1 2 3 G D 6 10 12 H D, F 7 9 11 I E, G, H 3 4 5 (a) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (b) Based only on the critical path, what is the estimated probability that the project can be completed in 28 or fewer days? (Round your answer to four decimal places.)arrow_forward
- The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 8 10 12 — C 7 10 11 A B 6 12 18 — D 6 10 12 B The expected completion time of the critical path = weeks (round your response to two decimal places).arrow_forwardExercise 8: Given the following network, refer to the pic please (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so, how many days?arrow_forwardThe following information is known about a project:- Activity Activity time (Weeks) Immediate Predecessor(s) A 3 - B 11 - C 7 A D 13 B, C E 10 B F 6 D G 5 E H 8 F, G a) Draw the network diagram for this project b) Calculate for the slack time c) Find the critical path d) When is the project completion timearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY