Let consider “xs1” and “xs2” be the number of pounds of silicon used in fertilizer 1 and fertilizer 2.
Let “xn1” and “xn2” be the number of pounds of nitrogen used in fertilizer 1 and fertilizer 2.
The objective is to maximize the profits of Bullco.
Therefore, the objective function is,
Maximum
Constraint 1:
At most, 100lb of silicon can be purchased.
Amount of silicon used to produce fertilizer 1 and 2
Constraint 2:
At most, 80lb of nitrogen can be purchased
Trending nowThis is a popular solution!
Chapter 3 Solutions
Student Suite Cd-rom For Winston's Operations Research: Applications And Algorithms
- Wilson Creek Farm has 200 acres of land available for planting. The owner is considering planting three crops: corn, soybeans, and wheat. The production yield, water requirements, and labor requirements for a salable crop are given here. The owner expects to have only 35,000 gallons of water available per week to use for the crops, and during the growing season he will only have 8000 person-hours of labor available. The expected profit per bushel of each crop is $1.00 for corn, $1.60 for soybeans, and $3.00 for wheat. The owner can use any mix of crops (i.e., he can plant the same crop on all 200 acres or he can plant all three crops in different proportions). d. Solve the problem using Excel Solver Tool. Add supporting pictures from the software for each step. Discuss your output in line with the given reports from Excel. Bushels/ Acre Water Required Produced (gal/acre/week) Crop 300 Corn Soybeans 200 Wheat 80 200 150 125 Person-Hours Labor Required/Acre 35 40 30arrow_forwardTruckco manufactures two types of trucks: 1 and 2. Each truck must go through the painting shop and assembly shop. If the painting shop were completely devoted to painting Type 1 trucks, then 800 per day could be painted; if the painting shop were completely devoted to painting Type 2 trucks, then 700 per day could be painted. If the assembly shop were completely devoted to assembling truck 1 engines, then 1,500 per day could be assembled; if the assembly shop were completely devoted to assembling truck 2 engines, then 1,200 per day could be assembled. Each Type 1 truck contributes $300 to profit; each Type 2 truck contributes $500. How much capacity in percent does a single truck of each type uses at each shop?arrow_forwardPneumatics Engineering purchased a machine that had a fi rst cost of $40,000, an expected useful life of 8 years, a recovery period of 10 years, and a salvage value of $10,000. The operating cost of the machine is expected to be $15,000 per year. The inflation rate is 6% per year and the company’s MARR is 11% per year. Determine the depreciation charge for year 3 according to the straight line method. (UNITS ARE REQUIRED)arrow_forward
- Leary Chemical manufactures three chemicals: A, B, and C. These chemicals are produced via two production processes: 1 and 2. Running process 1 for an hour costs $4 and yields 3 units of A, 1 of B, and 1 of C. Running process 2 for an hour costs $1 and produces 1 unit of A and 1 of B. To meet customer demands, at least 10 units of A, 5 of B, and 3 of C must be produced daily. Processes cannot be run simultaneously, and total number of operational hours is limited to 12 hours. Construct an LP model to determine a daily production plan that minimizes the cost of meeting Leary Chemical’s daily demands.arrow_forwardProblem 5. An Electricity board charges the following rates mentioned in the table for the use of electricity. All users are charged Taka 50 as a meter charge for every month. If any user wants to change/replace his meter, he will be charged taka 2000. The monthly bill will be generated based on ● Customer Category ● Consumed Units ● Phase ● For Category 3 and 5 along with other parameters, you need to also consider flat rate, peak time, and off-peak time. Take input from the user, how many units were consumed during flat rate, peak, or off-peak time. ● Meter Charge Write a program to read the name of the user, Customer Category, Phase, number of units consumed and print out the monthly bill. Note that ● Phase, flat rate, peak time and off-peak time will be appeared based on the customer category. ● The monthly bill will be calculated following the number of Days in a montharrow_forwardA company manufactures two types of trucks. Each truck must go through the painting shop and the assembly shop. If the painting shop were completely devoted to painting type 1 trucks, 800 per day could be painted, whereas if the painting shop were completely devoted to painting type 2 trucks, 700 per day could be painted. If the assembly shop were completely devoted to assembling truck 1 engines, 1500 per day could be assembled, whereas if the assembly shop were completely devoted to assembling truck 2 engines, 1200 per day could be assembled. It is possible, however, to paint both types of trucks in the painting shop. Similarly, it is possible to assemble both types in the assembly shop. Each type 1 truck contributes $1000 to profit; each type 2 truck contributes $1500. Use Solver to maximize the company’s profitarrow_forward
- The public utilities commission has decided that the electric company overcharged its customers for two months last year. To make up the difference to the customers, the commission orders the company to decrease each of the next month’s bills by 10%. The city also levies a 3%utility tax, which is to be applied to the bill before it is discounted. Also, the10% discount does not apply to the utility tax. Assume electricity costs $0.16per kilowatt-hour. Write a program to compute the next month’s electricity bill given the number of kilowatt-hours consumed as inputarrow_forwardProblem 2 Homely Development Corporation is considering bidding on a contract for a new office complex. The company needs to decide if it should bid on the contract. The codt of preparing the bid is $200,000. The company estimates that it has an 80% chance of winning the contract and 20% of losing the bid. If the company wins the bid it will have to pay $2,000,000 to become a partner in the contract. Once they are partners in the contract, they could conduct a market research study at $150,000. The research project could return with a forecast of a high market demand or low market demand. Regardless of the survey result must decide if they want to build the office complex or sell the rights to another company. Homely estimates that selling the contract rights will generate revenues of $3,500,000. If Homely decides to build the office complex they will generate $5,000,000 in revenue if demand is high and $3,000,000 if demand is low. Information for this project is listed below. Cost of…arrow_forwardThe Mayfree Appliance Company requires sheet metal for its appliances. The company can purchase long coils of sheet metal in two different widths: 65 inches and 40 inches. The company must purchase the coils by linear foot of length: $1.20 per foot for a 64-inch coil and $1.00 per foot for a 40-inch coil. (This implies that a square foot, say, of the wider coil is less expensive.) Up to 4000 feet of the 65-inch coil is available, and up to 6000 feet of the 40-inch coil is available. There are manufacturing requirements for six different widths: 50, 45, 40, 35, 20, and 10 inches. Mayfree’s requirements are expressed as lengths of the various widths. The company requires 1000 feet of 50-inch width, 2500 feet of 45-inch width, 3000 feet of 40-inch width, 2300 feet of 35-inch width, 1300 feet of 20-inch width, and 2000 feet of 10-inch width. Determine how much of each width coil Mayfree should purchase and how it should cut the coils into various widths to meet its requirements at minimal…arrow_forward
- A certain grade of steel is graded according to the following condition: 1. Hardness must be greater than 40 2. Carbon contents must be less than 0.8 3. Tensile strength must be greater than 5000 The grades are as follows: § Grade is 10 if all the three conditions are met. § Grade is 9 if conditions 1 and 2 are met. § Grade is 8 if conditions 2 and 3 are met. § Grade is 7 if conditions 1 and 3 are met. § Grade is 6 if only one condition is met. § Grade is 5 if none of the conditions are met. Write a C++ program which will require user to give values of hardness, carbon content and tensile strength of the steel under consideration then determine the grade of steel and outputs the grade of the steelarrow_forwardThe Callaghan family owns 410 acres of farmland in Co. Cork on which they grow wheat and oats. Each acre of wheat costs €105 to plant, cultivate, and harvest; each acre of oats costs €210. The Bradleys have a budget of €52,500 for next year. The government limits the number of acres of oats that can be planted to 100. The profit from each acre of wheat is €300; the profit from each acre of oats is €520. The Callaghans want to know how many acres of each crop to plant in order to maximize their profit. ii. Formulate a linear programming model for this problem.arrow_forwardA company uses four special tank trucks to deliver four different gasoline products to customers. Eachtank has five compartments with capacities: 500, 750, 1200, 1500, and 1750 gallons. The daily demands forthe four products are 10000, 15000, 12000, and 8000 gallons. Any quantities that cannot be delivered by thecompany’s four trucks must be subcontracted at the additional costs of 5, 12, 8, and 10 cents per gallon forproducts 1, 2, 3, and 4, respectively. The goal is to develop the optimal daily loading schedule for the fourtrucks that will minimize the additional cost of subcontracting. Formulate this problem as an integer linearprogram, and solve it (not by hand).arrow_forward
- Operations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole