Essentials of Systems Analysis and Design (6th Edition)
Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
bartleby

Concept explainers

Question
Book Icon
Chapter 4, Problem 17PE
Program Plan Intro

Economic feasibility analysis of an information system:

Monetary benefits of an information system = $85,000 per year.

One-time costs = $75,000

Recurring cost = $35,000 per year.

Discount rate = 12%

Time period = 5 years

Explanation of Solution

Overall Return on Investment (ROI):

Overall return on investment can be calculated as:

Overall ROI = (Overall NPV / NPV of all costs)

Overall NPV = (NPV of all benefits – NPV of all costs)                     &#

Explanation of Solution

Break-Even Analysis (BEA):

  • Break even analysis is carried out by determining NPV of yearly cash flows.
  • The yearly cash flows are calculated by subtracting present values of recurring costs from the present value of yearly benefits.
  • The overall NPV cash flow is total cash flow of the preceding years.
  • After determining NPV yearly cash flows, it is found that break even occurs between year one and two.
  • This is because year two is the very first year where overall NPV is positive...

Blurred answer
Students have asked these similar questions
Suggest the suitable models for the following mentioned scenarios 1. Process Visibility is necessary 2. For Small and medium size interactive systems 3. To explore unknown requirements 4. To accommodate change at any time 5. Need to reduce the risk of overall project failure 6. Need of Risk Assessment
22. How is WINWIN Spiral Model different from Spiral Model? a. It defines tasks required to define resources, timelines, and other project related information. b. It defines a set of negotiation activities at the beginning of each pass around the spiral. c. It defines tasks required to assess both technical and management risks. d. It defines tasks required to construct, test, install, and provide user support.
Q- a) What is PERT and CPM in project management show the difference between them b) Consider the following engineering project. 1-What is the critical path 2- Compute the ES, EC, LS, LC and the slack time, and display all the values in a table. Activity Immediate Time (week) predecessor Activity A A A, B D B E A, C, D 8 3- Suppose that activity C has been completed within 5 weeks, what is the effect on the project completion time? 65
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781285196145
Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos Coronel
Publisher:Cengage Learning