Program Plan Intro
Baseline project plan:
- Baseline project plan is a document that contains the whole information collected from the first and second phases of a software development life cycle.
- A baseline is a reference point for the project schedule.
- After preparing baseline plan, organization can conduct reviews with end customers.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
As a senior studying IT at CTU, your supervisor has requested that you present
a plan for consideration and approval. Produce a research proposal of about
1600 words on a topic that interests you, paying special attention to the
following: Five sections make up a research paper: the introduction (1), the
methods (II), the issue statement (II), the goals (III), the significance (IV), and the
literature review (V).
Does the project sponsor play the same role at each stage of the SDLC?
A consultant was contracted to draw up a feasibility report on OWM project, discuss two possible technical problems you could envisage with this project.b. What are the main functional requirements of the OWM system? Identify any ambiguities in the user spec.
c. Discuss the methodology you will employ for the development of the system and why you choose to use that methodology.d. Draw an ERD (entity relationship diagram) for the OWM systeme. Discuss an appropriate software development tool, programming language and database application you will use to implement this project if you are awarded the contract.
Chapter 4 Solutions
Pearson eText for Essentials of Systems Analysis and Design -- Instant Access (Pearson+)
Ch. 4 - Prob. 1MCh. 4 - Prob. 2MCh. 4 - Prob. 3MCh. 4 - Prob. 4MCh. 4 - Prob. 5MCh. 4 - Prob. 6MCh. 4 - Prob. 7MCh. 4 - Prob. 8MCh. 4 - Prob. 9MCh. 4 - Prob. 10M
Ch. 4 - Prob. 11MCh. 4 - Prob. 12MCh. 4 - Prob. 13MCh. 4 - Prob. 14MCh. 4 - Prob. 15MCh. 4 - Prob. 16MCh. 4 - Prob. 17MCh. 4 - Prob. 18MCh. 4 - Prob. 19MCh. 4 - Prob. 20MCh. 4 - Prob. 21MCh. 4 - Prob. 22MCh. 4 - Prob. 1RQCh. 4 - Describe several project evaluation criteria.Ch. 4 - Prob. 3RQCh. 4 - Prob. 4RQCh. 4 - Prob. 5RQCh. 4 - Prob. 6RQCh. 4 - What are the potential consequences of not...Ch. 4 - Prob. 8RQCh. 4 - Prob. 9RQCh. 4 - Prob. 10RQCh. 4 - Prob. 11RQCh. 4 - Prob. 12PECh. 4 - Prob. 13PECh. 4 - Prob. 14PECh. 4 - Prob. 15PECh. 4 - Prob. 16PECh. 4 - Prob. 17PECh. 4 - Prob. 18PECh. 4 - Prob. 19PECh. 4 - Prob. 20PECh. 4 - Prob. 21PECh. 4 - Assume monetary benefits of an information system...Ch. 4 - Prob. 23PECh. 4 - Prob. 24PECh. 4 - Prob. 25PECh. 4 - Prob. 26PECh. 4 - Prob. 27PECh. 4 - Prob. 28PECh. 4 - Prob. 29DQCh. 4 - Prob. 30DQCh. 4 - Prob. 31DQCh. 4 - Prob. 32DQCh. 4 - Prob. 33CPCh. 4 - Prob. 34CPCh. 4 - Prob. 35CPCh. 4 - Prob. 36CQCh. 4 - Prob. 37CQCh. 4 - Identify a preliminary set of tangible and...Ch. 4 - Prob. 39CQCh. 4 - If you were assigned to help Jim with this...Ch. 4 - Prob. 41CQCh. 4 - Prob. 42CQCh. 4 - In Question 4, you analyzed the risks associated...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- SYSTEM ANALYSIS AND DESIGN ( COMPUTER SCIENCE) Instruction: As a system analyst, you are required to analyze and propose a system design for your client company to help in their daily business process. Choose ONE (1) of the following system and discuss the development process in detail. Online Tuition Center - Online Babysitter - Online Cleaning Service Online Event Management - Online Emergency Management - Online Personal Shopper Question 1 a) Identify the appropriate system development method and explain why it is suitable for the system. b) List all the possible functions applicable to the system. c) Create a Gantt chart for the system analysis and design proposal. You may use the outline provided as a guideline for your Gantt Chart Outline for Gantt chart System Investigation - Introduction - System Request Form - Project Proposal - Feasibility Studies - Fact Finding Techniques Used - List of End-user Requirement System Analysis - Proposed Actors & Use cases - Proposed Use case…arrow_forwardi. At what stage of the SDLC do you intend to carry out Requirements validation of your projectarrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: - Issue 1 85 occurrences; Issue 2 - 125 occurrences; Issue 3 - 28 occurrences; Issue 4 - 395 occurrences; Issue 5 - 185 occurrences; Issue 6- 128 occurrences; Issue 7 – 85 occurrences; Issue 8 169 occurrences; Issue 9 - 148 occurrences; Issue 10 209 occurrences. - - Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forward
- As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forwardUse an acceptable example to illustrate each of the following steps so that you can better understand how they work (project where they can be used) When gathering information on the objectives of a project, some of the approaches that could be used include prototyping, interviews, group work, and ethnography. h. The viewpoint takenarrow_forwardYou have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: i. Letters of invitation are to be sent with relevant information. ii. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. iv. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. v. Extra expenses incurred at the workshop are also to be noted. vi. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the beginning of the…arrow_forward
- Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 В A 4 none 6 D none 2 D 5 F В, С, Е 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A 9 B E в 4 D 2 G E 8. *Note: please use this format. Early Start Duration Early Finish Activity Float Late Start Late Finisharrow_forwardCan you please assist with answers from question 6 to 10, Now that you have selected a project (a case), develop an analytical report of the project with specific focus on the components and questions/statements listed below: (1) State the name of the project and give a brief description of the project. (2) Outline the problem(s) that the project was initiated to solve or the opportunity it exploited. (3) Describe the technique or method used to select the project. (4) Identify and describe at least five (5) characteristics that make this endeavour a project. (5) Identify the project developmental approach used for the project. Give reasons or justification for your conclusion(s). Hint: (Agile, Waterfall/Traditional, or Hybrid approach?) (6) Using your knowledge of the project life cycle and information gathered from the examination of the project documents, describe the phases of the project and the key activities/tasks associated with each phase of the project. (7) List and…arrow_forwardDuring the course of a project, it is common for a requirements document to undergo many revisions. Mention two (2) reasons why the requirements may be susceptible to change and provide a short explanation for each of them.arrow_forward
- Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided." Project 1arrow_forwardDesign a Gantt Chart schedule that includes, work break-down structure (WBS), start and end date of each task, responsible person to perform the task and proceedingtask/s. It is important to mention thatWBS is required for all the stages (i.e., Integration and Request, Project Planning, Project Execution, and Implementation and Support) mentioned in the case scenario.Moreover, you mustinclude the relevant sub-stages necessary to complete the project.It is compulsory that students use Microsoft Project to complete WBS, allocate time and resources.arrow_forwarduse case diagram given blow, draw deployment diagram accordinglyarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning