Before installing a gauge on the high-pressure side of a system, you should do which of the following?
A. Turn on the system.
B. Turn off the system.
C. Adjust the system to a neutral position.
D. Have a cylinder approved by the DOT nearby.
The work should be done before installing a gauge on the high-pressure side of a system.
Answer to Problem 1RQ
The work should be done before installing a gauge on the high-pressure side of a system is turn off the system.
Explanation of Solution
The pressure gauge is an instrument used to measure the gauge pressure of the flow of fluid. It displays high and low pressure side of the system when it is put in operation. This used to convert the pressure of the system different refrigerant requirements.
The technician should be skilled to attach the manifold gauge. Attaching the gauge to the manifold should be done very carefully. Wearing goggles and gloves are necessary while attaching the gauge otherwise the high-pressurised refrigerant can injure to eyes and skin of technician.
This type of dangerous condition can be prevented by letting the pressure of high-pressure side refrigerant down to lower pressure. To reduce the pressure to lower pressure, the system should be turned off.
Conclusion:
Hence, the work should be done before installing a gauge on the high-pressure side of a system is turn off the system.
Want to see more full solutions like this?
Chapter 41 Solutions
REFRIGERATION+AIR COND.TECH.-W/2 ACCESS
- Which of the following statements about oil gauge circuits is not true? A switch can be used A thermistor can be used. A piezoresistive sensor can be used d An oil pressure gauge may not show actual oil pressure.arrow_forwardFor a hydraulic power unit, this part reads the oil pressure at the pump outlet a. filler/breather b. suction strainer c. liquid level gauge d. pressure gaugearrow_forwardWhat is thermocouple gauge used for detection of leaks in vacuum systems.arrow_forward
- The pressure measured with the help of a pressure gauge is called absolute pressure. Select one: True Falsearrow_forwardConsider the following: 1. Safety valve 2 Fusible plug 3 Feed water pump 4 Pressure gauge The essential boiler mountings would include.arrow_forwardAn expansion valve in an improperly operating refrigerator system is shownbelow. The system is misoperating such that there is gas on both sides of theexpansion valve, not liquid as would be found on a properly operating system.What would a pressure gauge read on the low pressure side of the expansionvalve?arrow_forward
- For a hydraulic power unit, this part protects the pump from taking in any harmful particles that may be in the reservoir a. liquid level gauge b. filler/breather c. pressure gauge d. suction strainerarrow_forwardDraw the system of Boiler, put a label.arrow_forwardA one-pipe system may be used when the oil tank is higher or lower than the oil pump. True or false.arrow_forward
- Refrigeration and Air Conditioning Technology (Mi...Mechanical EngineeringISBN:9781305578296Author:John Tomczyk, Eugene Silberstein, Bill Whitman, Bill JohnsonPublisher:Cengage LearningWelding: Principles and Applications (MindTap Cou...Mechanical EngineeringISBN:9781305494695Author:Larry JeffusPublisher:Cengage LearningAutomotive Technology: A Systems Approach (MindTa...Mechanical EngineeringISBN:9781133612315Author:Jack Erjavec, Rob ThompsonPublisher:Cengage Learning