A production line has three machines A, B, and C, with reliabilities of .99, .96, and .93, respectively. The machine are arrange to that if one breaks down, the other: must shut down. Engineers are weighing two alternative designs for the line’s reliability. Plan 1 involve adding an identical backup line, and plan 2 involves providing a backup for each machine. In either case, three machines (A, B, and C) would be used with reliabilities equal to the original three.
a. Which plan will provide the higher reliability?
b. Explain why the two reliabilities are not the same.
c. What other factors might enter into the decision of which plan to adopt?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A production line has three machines A, B, and C, with reliabilities of .99, .96, and .93, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineersare weighing two alternative designs for increasing the line’s reliability. Plan 1 involves addingan identical backup line, and plan 2 involves providing a backup for each machine. In either case,three machines (A, B, and C) would be used with reliabilities equal to the original three.a. Which plan will provide the higher reliability?
A typical retail transaction consists of several smaller steps, which can be considered components subject to failure. A list of such components might include: Let the eight probabilities of success be .92, .94, .99, .99, .98, .97,.95, and .96. What is the reliability of the system; that is, the probabilitythat there will be a satisfied customer? If you were the storemanager, what do you think should be an acceptable value forthis probability? Which components would be good candidatesfor backup, which for redesign?
A typical retail transaction consists of severalsmaller steps, which can be considered components subject tofailure. A list of such components might include:
Let the eight probabilities of success be .92, .94, .99, .99, .98,.97, .95, and .96. What is the reliability of the system; thatis, the probability that there will be a satisfied customer? Ifyou were the store manager, what do you think should bean acceptable value for this probability? Which componentswould be good candidates for backup, which for redesign?
Chapter 4 Solutions
Operations Management
Ch. 4.4 - Prob. 1.1RQCh. 4.4 - Prob. 1.2RQCh. 4.8 - LEGO A/S IN THE PINK Lego A/S overcame the recent...Ch. 4.8 - Prob. 2.1RQCh. 4.8 - Prob. 2.2RQCh. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.S - Prob. 1DRQCh. 4.S - Prob. 2DRQCh. 4.S - Prob. 3DRQ
Ch. 4.S - Consider the following system: Determine the...Ch. 4.S - A product is composed of four parts. In order for...Ch. 4.S - A system consists of three identical components....Ch. 4.S - A product engineer has developed the following...Ch. 4.S - The guidance system of a ship is controlled by a...Ch. 4.S - One of the industrial robots designed by a leading...Ch. 4.S - A production line has three machines A, B, and C,...Ch. 4.S - Prob. 8PCh. 4.S - A Web server has five major components that must...Ch. 4.S - Repeat Problem 9 under the condition that one of...Ch. 4.S - Hoping to increase the chances of reaching a...Ch. 4.S - An electronic chess game has a useful life that is...Ch. 4.S - A manufacturer of programmable calculators is...Ch. 4.S - Lucky Lumen light bulbs have an expected life that...Ch. 4.S - Prob. 15PCh. 4.S - Prob. 16PCh. 4.S - A major television manufacturer has determined...Ch. 4.S - Prob. 18PCh. 4.S - Determine the availability for each of these...Ch. 4.S - Prob. 20PCh. 4.S - A manager must decide between two machines. The...Ch. 4.S - Prob. 22PCh. 4.S - Auto batteries have an average life of 2.7 years....Ch. 4 - Prob. 1DRQCh. 4 - Prob. 2DRQCh. 4 - Prob. 3DRQCh. 4 - Prob. 4DRQCh. 4 - Prob. 5DRQCh. 4 - Prob. 6DRQCh. 4 - Prob. 7DRQCh. 4 - Prob. 8DRQCh. 4 - a. What is meant by the term life cycle? b. Why...Ch. 4 - Prob. 10DRQCh. 4 - Prob. 11DRQCh. 4 - Prob. 12DRQCh. 4 - Prob. 13DRQCh. 4 - Explain what quality function development is and...Ch. 4 - Prob. 15DRQCh. 4 - Prob. 16DRQCh. 4 - Prob. 17DRQCh. 4 - Prob. 18DRQCh. 4 - Prob. 19DRQCh. 4 - Describe some of the trade-off that are...Ch. 4 - Prob. 2TSCh. 4 - Prob. 3TSCh. 4 - Prob. 1CTECh. 4 - Prob. 2CTECh. 4 - Prob. 3CTECh. 4 - Prob. 4CTECh. 4 - Prob. 5CTECh. 4 - Give two examples of unethical conduct involving...Ch. 4 - Prob. 1PCh. 4 - Prob. 2PCh. 4 - Prepare a service blueprint for each of these...Ch. 4 - Prepare a service blueprint for each of these post...Ch. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prepare a table similar to that shown in Problem...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The guidance system of a ship is controlled by a computer that has three major modules. In order for the computer to function properly, all three modules must function. The modules have reliabilities of 97%, 95%, and 99%. What is the reliability of the computer? A backup computer identical to the one being used will be installed to improve overall reliability. Assuming the new computer automatically functions if the main one fails, determine the resulting reliability. If the backup computer must be activated by a switch in the event that the first computer fails, and the switch has a reliability of 98%, what is the overall reliability of the system? Both the switch and the backup computer must function in order for the backup to take over.arrow_forwardOne of the industrial robots designed by a leading producer of servomechanisms has four major components. Components’ reliabilities are .98, .95, .94, and .90. All of the components must function in order for the robot to operate effectively.a. Compute the reliability of the robot.b. Designers want to improve the reliability by adding a backup component. Due to space limitations, only one backup can be added. The backup for any component will have the same reliability as the unit for which it is the backup. Which component should get the backup in orderto achieve the highest reliability?c. If one backup with a reliability of .92 can be added to any one of the main components, which component should get it to obtain the highest overall reliability?arrow_forwardThe ABC Bank processes loan applications through 3 clerks set up in series, with reliabilities of 0.90, 0.80, and 0.99. a. The bank manager decided to provide redundancy to the two least reliable clerks. Reliability measures of the redundants are equal to the corresponding primary clerk. What is the new system reliability? Show illustration and complete solution. b. What will be the system reliability if the bank replaces the clerk with reliability measure of 0.80 and his redundant, with a 90% reliable clerk? Show illustration and complete solution.arrow_forward
- An engine system consists of 2 main components in a series, all having the same reliability. Determine the level of reliability required for each of the components if the engine is to have a reliability of 0.989. round answer to 4 decimal places.arrow_forwardA university Web server has fi ve main components, each withthe same reliability. All fi ve components must work for the serverto function as intended. If the university wants to have a 95 percentreliability, what must be the reliability of each of the components?arrow_forwardA University Web server has 5 main components, each with the same reliability. All 5 components must work for the server to function as intended. If the University wants to have a 81 percent reliability, what must be the reliability of each of the components?arrow_forward
- Consider Solved Problem 17.2 given in the textbook. If the reliability of each and every component shown in R1, R2, R3, R4 and R5 are reduced by 15% (for example, R2 becomes 0.8), calculate the total reliability of the system. As done in the solved example, be sure to show all steps. NOTE: You should not redraw the diagram. Solved 17.2 A recent engineering change at Sullivan Wrist Calculator places a backup component in each of the two least reliable transistor circuits. The new circuits will look like the following: What is the reliability of the new system? Solution attachedarrow_forwardAssume that a computer has two 1TB disks, D0 and D1. The Mean Time to Failure (MTTF) ofeach disk is 1M hours.a. If the disk system is configured to have 2TB total storage capacity, when any of the two disksfails, the disk system fails. What is the MTTF of the disk system?b. Mirroring (RAID-1) is a technique can improve the reliability of disk systems by usingredundancy. Each data block will have two identical copies stored in both D0 and D1. Under thisconfiguration, the disk system has only 1TB total storage capacity; but it only fails when bothdisks fail (e.g. when the failed disk is being repaired, the second disk also fails). If the MTTR of afailed disk is 20 hours, what is the MTTF of the disk system now?arrow_forwardA jet engine has 10 components in series. Th e average reliabilityof each component is 0.998. What is the reliability of the engine?arrow_forward
- The semiconductor used in the Sullivan Wrist Calculatorhas five circuits, each of which has its own reliability rate. Component 1 has a reliability of .90; component 2, .95; com-ponent 3, .98; component 4, .90; and component 5, .99. What is the reliability of one semiconductor?arrow_forwardAn office security system at PAC Ltd has two component parts, both of which must work for the system to function. Part 1 has a reliability of 80 percent, and part 2 has a reliability of 98 percent. Compute the reliability of the system.arrow_forwardThe president of AS Electronics, Inc., has two design options for his new line of cathode ray tubes (CRTs). The forecast for the CRTs is 100,000 units annually. The company will make 100,000 units using one of the two designs at a cost of $75 each. Good CRTs can be sold, but bad CRTs are destroyed and have no salvage value. (Ignore any disposal cost issues for the moment.) The company can sell good CRTs for $150. Design option A has a .90 probability of yielding 59 good CRTs per 100 and a .10 probability of yielding 64 good CRTs per 100. The design will cost $1,000,000. Design option B has a .80 probability of yielding 64 good CRTs per 100 and a .20 probability of yielding 59 good CRTs per 100. The design will cost $1,350,000. Draw and label the decision tree (for two design options with two possible yields each). Calculate the first-year payoff for each option. [Payoff = Annual Revenues – annual manufacturing costs – design costs] Calculate the expected payoff for each of the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY