ENGINEERING ECO ANALYSIS W/STUDY GUIDE
ENGINEERING ECO ANALYSIS W/STUDY GUIDE
13th Edition
ISBN: 9780190693053
Author: NEWNAN
Publisher: Oxford University Press
bartleby

Concept explainers

Question
Book Icon
Chapter 5, Problem 33P
To determine

Which of the two alternatives should be selected.

Expert Solution & Answer
Check Mark

Answer to Problem 33P

The Option to be implemented is Cantilever bridge, since it results in a lower cash outflow for a period of 50 years.

Explanation of Solution

Given information: (all costs in $Million)

Installation Cost:

Suspension Bridge $585

Cantilever Bridge $470

Land acquisition Cost:

Suspension Bridge $120

Cantilever Bridge $95

Annual Operation and Maintenance costs:

Suspension Bridge $2

Cantilever Bridge $3

Annual Increase in Operation and Maintenance costs:

Suspension Bridge 4%

Cantilever Bridge 3%

Salvage Value in year 50:

Suspension Bridge $30

Cantilever Bridge $27

Rate of Interest for calculation: 8%.

Based on the above information, the following tables outlines the net present value calculation of the two options.

Suspension Bridge:

Year Particulars (Figures in Million) Cash flow Present value Factor @8% Present value
0 Installation Cost $585.00 1.0000 $585.00
0 Land Cost $120.00 1.0000 $120.00
1 Operating Costs $2.00 0.9259 $1.85
2 Operating Costs $2.08 0.8573 $1.78
3 Operating Costs $2.16 0.7938 $1.71
4 Operating Costs $2.25 0.7350 $1.65
5 Operating Costs $2.34 0.6806 $1.59
6 Operating Costs $2.43 0.6302 $1.53
7 Operating Costs $2.53 0.5835 $1.48
8 Operating Costs $2.63 0.5403 $1.42
9 Operating Costs $2.74 0.5002 $1.37
10 Operating Costs $2.85 0.4632 $1.32
11 Operating Costs $2.96 0.4289 $1.27
12 Operating Costs $3.08 0.3971 $1.22
13 Operating Costs $3.20 0.3677 $1.18
14 Operating Costs $3.33 0.3405 $1.13
15 Operating Costs $3.46 0.3152 $1.09
16 Operating Costs $3.60 0.2919 $1.05
17 Operating Costs $3.75 0.2703 $1.01
18 Operating Costs $3.90 0.2502 $0.98
19 Operating Costs $4.05 0.2317 $0.94
20 Operating Costs $4.21 0.2145 $0.90
21 Operating Costs $4.38 0.1987 $0.87
22 Operating Costs $4.56 0.1839 $0.84
23 Operating Costs $4.74 0.1703 $0.81
24 Operating Costs $4.93 0.1577 $0.78
25 Operating Costs $5.13 0.1460 $0.75
25 Maintenance Cost $185.00 0.1460 $27.01
26 Operating costs $5.33 0.1352 $0.72
27 Operating costs $5.54 0.1252 $0.69
28 Operating costs $5.77 0.1159 $0.67
29 Operating costs $6.00 0.1073 $0.64
30 Operating costs $6.24 0.0994 $0.62
31 Operating costs $6.49 0.0920 $0.60
32 Operating costs $6.75 0.0852 $0.58
33 Operating costs $7.02 0.0789 $0.55
34 Operating costs $7.30 0.0730 $0.53
35 Operating costs $7.59 0.0676 $0.51
36 Operating costs $7.89 0.0626 $0.49
37 Operating costs $8.21 0.0580 $0.48
38 Operating costs $8.54 0.0537 $0.46
39 Operating costs $8.88 0.0497 $0.44
40 Operating costs $9.23 0.0460 $0.42
41 Operating costs $9.60 0.0426 $0.41
42 Operating costs $9.99 0.0395 $0.39
43 Operating costs $10.39 0.0365 $0.38
44 Operating costs $10.80 0.0338 $0.37
45 Operating costs $11.23 0.0313 $0.35
46 Operating costs $11.68 0.0290 $0.34
47 Operating costs $12.15 0.0269 $0.33
48 Operating costs $12.64 0.0249 $0.31
49 Operating costs $13.14 0.0230 $0.30
50 Operating costs $13.67 0.0213 $0.29
50 Salvage Value ($30.00) 0.0213 ($0.64)
Net cash outflow $773.80

Cantilever Bridge:

Year Particulars (Figures in Million) Cash flow Present value Factor @8% Present value
0 Installation Cost $470.00 1.0000 $470.00
0 Land Cost $95.00 1.0000 $95.00
1 Operating Costs $3.00 0.9259 $2.78
2 Operating Costs $3.09 0.8573 $2.65
3 Operating Costs $3.18 0.7938 $2.52
4 Operating Costs $3.28 0.7350 $2.41
5 Operating Costs $3.38 0.6806 $2.30
6 Operating Costs $3.48 0.6302 $2.19
7 Operating Costs $3.58 0.5835 $2.09
8 Operating Costs $3.69 0.5403 $1.99
9 Operating Costs $3.80 0.5002 $1.90
10 Operating Costs $3.91 0.4632 $1.81
11 Operating Costs $4.03 0.4289 $1.73
12 Operating Costs $4.15 0.3971 $1.65
13 Operating Costs $4.28 0.3677 $1.57
14 Operating Costs $4.41 0.3405 $1.50
15 Operating Costs $4.54 0.3152 $1.43
16 Operating Costs $4.67 0.2919 $1.36
17 Operating Costs $4.81 0.2703 $1.30
18 Operating Costs $4.96 0.2502 $1.24
19 Operating Costs $5.11 0.2317 $1.18
20 Operating Costs $5.26 0.2145 $1.13
21 Operating Costs $5.42 0.1987 $1.08
22 Operating Costs $5.58 0.1839 $1.03
23 Operating Costs $5.75 0.1703 $0.98
24 Operating Costs $5.92 0.1577 $0.93
25 Operating Costs $6.10 0.1460 $0.89
25 Maintenance Cost $210.00 0.1460 $30.66
26 Operating costs $6.28 0.1352 $0.85
27 Operating costs $6.47 0.1252 $0.81
28 Operating costs $6.66 0.1159 $0.77
29 Operating costs $6.86 0.1073 $0.74
30 Operating costs $7.07 0.0994 $0.70
31 Operating costs $7.28 0.0920 $0.67
32 Operating costs $7.50 0.0852 $0.64
33 Operating costs $7.73 0.0789 $0.61
34 Operating costs $7.96 0.0730 $0.58
35 Operating costs $8.20 0.0676 $0.55
36 Operating costs $8.44 0.0626 $0.53
37 Operating costs $8.69 0.0580 $0.50
38 Operating costs $8.96 0.0537 $0.48
39 Operating costs $9.22 0.0497 $0.46
40 Operating costs $9.50 0.0460 $0.44
41 Operating costs $9.79 0.0426 $0.42
42 Operating costs $10.08 0.0395 $0.40
43 Operating costs $10.38 0.0365 $0.38
44 Operating costs $10.69 0.0338 $0.36
45 Operating costs $11.01 0.0313 $0.34
46 Operating costs $11.34 0.0290 $0.33
47 Operating costs $11.69 0.0269 $0.31
48 Operating costs $12.04 0.0249 $0.30
49 Operating costs $12.40 0.0230 $0.29
50 Operating costs $12.77 0.0213 $0.27
50 Salvage Value ($27.00) 0.0213 ($0.58)
Net cash outflow $649.48

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash inflows in the form of salvage value and cash outflows such as installation cost and operating cost.

In case of the suspension bridge, Installation Cost is $575 Million, Land Cost is $120 Million and Annual Operating costs are $2 Million with an increase of 4% each year. There is a maintenance cost of $180 Million in Year 25.Salvage value in year 50 is $30 Million.

In case of the cantilever bridge, Installation Cost is $470 Million, Land Cost is $95 Million and Annual Operating costs are $3 Million with an increase of 3% each year. There is a maintenance cost of $210 Million in Year 25. Salvage value in year 50 is $27 Million.

Present value factor is calculated as 1/1.08 ^ N where N is the year of operation of the bridge.

Conclusion:

Hence the bridge to be constructed is the Cantilever bridge, since it results in lower overall cash outflow over the period of 50 years.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 5 Solutions

ENGINEERING ECO ANALYSIS W/STUDY GUIDE

Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 60PCh. 5 - Prob. 61PCh. 5 - Prob. 62PCh. 5 - Prob. 63PCh. 5 - Prob. 64PCh. 5 - Prob. 65PCh. 5 - Prob. 66PCh. 5 - Prob. 67PCh. 5 - Prob. 68PCh. 5 - Prob. 69PCh. 5 - Prob. 70PCh. 5 - Prob. 71PCh. 5 - Prob. 72PCh. 5 - Prob. 73PCh. 5 - Prob. 74PCh. 5 - Prob. 75PCh. 5 - Prob. 76PCh. 5 - Prob. 77PCh. 5 - Prob. 78PCh. 5 - Prob. 79PCh. 5 - Prob. 80PCh. 5 - Prob. 81PCh. 5 - Prob. 82PCh. 5 - Prob. 83PCh. 5 - Prob. 84PCh. 5 - Prob. 85PCh. 5 - Prob. 86PCh. 5 - Prob. 87PCh. 5 - Prob. 88PCh. 5 - Prob. 89PCh. 5 - Prob. 90PCh. 5 - Prob. 91PCh. 5 - Prob. 92PCh. 5 - Prob. 93PCh. 5 - Prob. 94PCh. 5 - Prob. 95PCh. 5 - Prob. 96PCh. 5 - Prob. 97PCh. 5 - Prob. 98PCh. 5 - Prob. 99PCh. 5 - Prob. 100PCh. 5 - Prob. 101P
Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education