Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 4E
Firewall Project XT. Using the ‘complexity weighting” scheme shown in Table 5.3 and the function point complexity weight table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project.
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Hi, I need help answering the last question.
Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity
Normal Time (weeks)
Crashed Time (weeks)
Normal Cost
Crashed Cost
Predecessor(s)
A
5
3
$800
$1,200
-
B
6
5
$300
$450
-
C
6
5
$550
$775
-
D
3
2
$750
$950
A
E
6
3
$1,350
$2,250
C
F
5
3
$675
$875
B
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)
Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table attached as an image.
Determine the minimum cost-schedule for this project to be completed in 18 weeks.
Assume a linear relationship between crash cost and crash time. For example, crash cost per week for activity A can be calculated as: ($650 - $200)/(4-2) = $225.
2. What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum cost-schedule you found in part 1?
9.
A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals.
Activity
Precedent
Duration
Crash cost/day
A
-
3
$350
B
A
3.8
$250
C
A
6
$400
D
B
6
$150
E
B
4.1
$200
F
C
4
$275
G
D
6.2
$500
H
E
8
$300
Answer:
Chapter 5 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 5.1A - How many labor hours should the eighth satellite...Ch. 5.1A - How many labor hours for the whole project of...Ch. 5.1A - What price would you ask for the project? Why?Ch. 5.1A - Midway through the project your design and...Ch. 5.1A - Near the end of the project, Deutsch Telefon AG...Ch. 5 - Why are accurate estimates critical to effective...Ch. 5 - Prob. 2RQCh. 5 - Prob. 3RQCh. 5 - What are the major types of costs? Which costs are...Ch. 5 - Why is it difficult to estimate mega project...
Ch. 5 - Define what a white elephant is in project...Ch. 5 - Calculate the direct cost of labor tor a project...Ch. 5 - Mrs. Tolstoy and her husband, Serge, are planning...Ch. 5 - Exercise Figure 5.1 is a project WBS with cost...Ch. 5 - Firewall Project XT. Using the complexity...Ch. 5 - At this point, what would you do if you were the...Ch. 5 - Prob. 5.1.2CCh. 5 - What estimating techniques should be used for a...Ch. 5 - Assume you are either Mike or Josh; how would you...Ch. 5 - Prob. 5.2.2CCh. 5 - After cost, what other factors should be...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 5arrow_forwardWidgetco is making a prototype of a new product. The productconsists of two subassemblies. Before building either subassembly, the firm must purchaseraw materials and train workers. Before the subassemblies can be combined, subassembly2 must be inspected. The following table describes the project:Activity Description Requires Duration (Days)A Train workers 6B Purchase materials 9C Make subassembly 1 A,B 8D Make subassembly 2 A,B 7E Inspect subassembly 2 D 10F Combine subassemblies C, E 12G Subassembly 2 safety report E 6How quickly can Widgetco complete this project?(a) Define decision variables.(b) Write a suitable LP problem formulation.arrow_forwardCritically assess and comment on the success of the project from the followingviewpoints aline with a project To enhance Sports development by providing assistance to sports clubs and teams in St. Catherine North Central by providing them with the necessary gears and equipment for whichever Sporting disciple that they may part-take in. a. Level or degree of alignment of end results and outcomes to the organization’sstrategic goals.b. Level of success in the management of the triple constraints of time, cost, andscope.arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G Harrow_forwardProject lifecycle 1. With the use of a diagram, show (illustrate) the typical levels of project staffingrelated to each phase and throughout a project. 2. For each project phase identified in 1(a) above, identify and describe at least one (1)major deliverable (output) of the phase.arrow_forwardWe are the project manager for an IT project in our company. We identified the following top-level project tasks and estimated durations to standup a small test lab for the project: Identify test lab building/space requirements and possible locations(8days) Select best location for lab (1day) Once the best location is selected, immediately start the next two tasks: Prepare lab space with power and cabling (3days) Identify/procure required specialized test lab hardware/software(5) Once the lab space is prepared, install/check out available infrastructure hardware/software(1day). Once the specialized software/hardware is received and the infrastructure hardware/software is installed/checked out, install/checkout specialized software/hardware (2days) Once all tasks are completed, conduct the final inspection (1 day). Let's create a PERT/CPM chart for this project and identify the overall project duration and critical path.arrow_forward
- Problem 2: Chicago Project You are asked to manage an upcoming project for a client based in Chicago. Your supervisor, Susan, asked you to determine if the project will be completed in 2 months (60 days). Susan sent you the estimated time durations (in days) for the project. The information is given below: 4. Your supervisor was told that the client would like to complete the project in 56 days. Which path in the project network has the greatest risk of running over this new deadline of 56 days? 5. Prepare a report for Susan regarding your findings. Include your recommended strategy to finish the project in the least possible time.arrow_forwardDevelopment of Version 2.0 of a particular accountingsoftware product is being considered by Jose Noguera'stechnology firm in Baton Rouge. The activities necessary for thecompletion of this project are listed in the following table: a) What is the project completion date?b) What is the total cost required for completing this project on normal time? c) If you wish to reduce the time required to complete this projectby I week, which activity should be crashed, and how much will this increase the total cost?d) What is the maximum time that can be crashed? How much would costs increase?arrow_forwardJabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the projectand identify the activities that neeD to be prioritised by the project manager. (Nodiagram is required) TABLE- PROJECT INSTALLATION Activity Predecessor optimistic Most Likely Pessismistic Estimated time A - 4 7 10 7 B - 2 9 10 8 C A,B 2 5 8 5 D C 16 19 28 20 E C 6 9 24 11 F E 1 7 13 7 G C 4 10 28 12 H D,F 2 5 14 6 I G 5 8 17 9 J H,I 2 5 8 5arrow_forward
- answer only question 3 and 4 1) List and explain the phases that mark the life of a project 2) For each project phase identified in 1(a) above, describe at least four (4) project activities/processes performed in the phase. 3) With the use of a diagram, show (illustrate) the typical levels of uncertainty or project risks associated with each phase and throughout a project. 4) With the use of a diagram, show (illustrate) the typical levels of project staffing related to each phase and throughout a project. 5) For each project phase identified in 1(a) above, identify and describe at least one (1) major deliverable (output) of the phase.arrow_forwardProject Typhoon has a net present value of $10,000 and a profitability index of 1.01. Project Cyclone has a net present value of $10,000 and a profitability index of 1.10. Project SurfsUp has a net present value of $10,000 and a profitability index of 1.05. If only one project could be undertaken, what should the oraganiztion select?arrow_forwardDave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY