EBK CONTEMPORARY ENGINEERING ECONOMICS
6th Edition
ISBN: 8220101336736
Author: Park
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 5, Problem 4P
Refer to Problem 5.2, and answer the following questions:
- (a) How long does it take to recover the investment?
- (b) If the firm’s interest rate is 15% after taxes, what would be the discounted payback period for this project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Determine the payback period for a proposed investment as follows
The government is considering undertaking one of the four projects A1, A2, A3, and A4. These projects are mutually exclusive, and the estimated present values of their costs and of their benefits are shown in millions of dollars as follows:
All of the projects have the same duration. Assuming that there is no donothing alternative, which alternative would you select? Justify your choice by using a benefit-cost ratio on incremental investment (BC(i)).
Consider the following cash flow data for two competing investment projects:
(a) At i = 12%, which of the two projects would be a better choice?{b)At i = 22%, which project is chosen by the NPW rule?
Chapter 5 Solutions
EBK CONTEMPORARY ENGINEERING ECONOMICS
Ch. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - If a project costs 100,000 and is expected to...Ch. 5 - Refer to Problem 5.2, and answer the following...Ch. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Consider the cash flows from an investment...Ch. 5 - Prob. 10P
Ch. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Consider the project balances in Table P5.19 for a...Ch. 5 - Your RD group has developed and tested a computer...Ch. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Geo-Star Manufacturing Company is considering a...Ch. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Two methods of carrying away surface runoff water...Ch. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 1STCh. 5 - Prob. 2ST
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Similar questions
- Consider the following two mutually exclusive investment projects that have unequal service lives: (a) What assumption(s) do you need in order to compare a set of mutually exclusive investments with unequal service lives?(b) With the assumption(s) defined in (a) and using i = 10%, determine which project should be selected.(c) If your analysis period (study period) is just three years, what should bethe salvage value of Project B at the end of year 3 in order to make the twoalternatives economically indifferent?arrow_forwardA rural community/company is considering an investment in a cottage industry for which the net cash flows have been estimated as follows: i) What is the NPV if the discount rate is 10%? ii) Using discount rates of 10% and 14% calculate the IRR? iii) Is this project acceptable?arrow_forwardYou have been asked to evaluate the profitability of building a new distribution center under the following conditions:I. The proposal is for a distribution center costing $1,500,000. The facility has an expected useful life of 35 years and a net salvage value (net proceeds from its sale after tax adjustments) of $225,000.II. Annual savings (due to a better strategic location) of $227,000 are expected, annual maintenance and administrative costs will be $114,000, and annual income taxes are $43,000. Suppose that the firm's MARR is 12%. Determine the net present worth of the investment.arrow_forward
- You are considering developing an 18-hole championship golf course that requires an investment of $18,000,000. This investment cost includes the course development, club house, and golf carts. Once constructed, you expect the maintenance cost for the golf course to be $640,000 in the first year, $695,000 in the second year and continue to increase by $55,000 in subsequent years. The net revenue generated from selling food and beverage will be about 17% of greens fees paid by the players. The cart fee per player is $20, and 40,000 rounds of golf are expected per year. You will own and operate the course complex for 9 years and expect to sell it for $24,000,000. What is the greens fee per round that will provide a return on investment of 17%? Assume that the greens fee will be increased at an annual rate of 6%. The greens fee that will provide a return on investment of 17% is _____ per round. (Round to the nearest cent.)arrow_forwardIf a project costs $90,000 and is expected to return $24,500 annually, how long does it take to recover the initial investment? What would be the discounted payback period at i=14%? Assume that the cash flows occur continuously throughout the year. The payback period is___________years. (Round to one decimal place.)arrow_forwardConsider the following two mutually exclusive service projects with projectlives of three years and two years, respectively. (The mutually exclusive service projects will have identical revenues for each year of service.) The interest rate is known to be 12%. Net Cash Flow End of Year Project A Project B 0 -$1,000 -$800 1 -400 -200 2 -400 -200+0 3 -400+200 If the required service period is six years and both projects can be repeated with the given costs and better service projects are unavailable in the future, which project is better and why? Choose from the following options:(a) Select Project B because it will save you $344 in present worth over the required service period.(b) Select Project A because it will cost $1,818…arrow_forward
- A UK manufacturer of particle board furniture is considering investing in a new stamping machine. The machine is expected to have a useful life of five years, after which the machine can be sold as scrap for an estimated £5000. The firm plans to issue bonds to pay for the machine and intends to treat the interest rate on the bonds as the relevant discount rate for evaluating the project. The machine will cost the firm £175,000, all of which must be paid at the beginning of the project. The new stamping machine will reduce costs £50,000 per year, for each year of the machineʹs life. The firm treats all the cost savings as if they occur at year end. Should the firm plan to undertake the investment project, bonds will be issued in approximately three months. The firm has estimated the supply and demand for loanable funds given by these equations:LD = 25,000,000 - 125,000,000r LS = 2,500,000 + 62,500,000r(1) Given the information above, should the firm undertake the investment in the…arrow_forwardConsider the investment project with the net cash flows as shown in the following table. What would be the value of X if the project's IRR is 23%? (a) $4,500(b)$4,750(c) $6,890(d)$6,500arrow_forwardPayback Period and Net Present Value If a project with conventional cash flows has a payback period less than the project’s life, can you definitively state the algebraic sign of the NPV? Why or why not? If you know that the discounted payback period is less than the project’s life, what can you say about the NPV? Explain. Qarrow_forward
- Consider the following two mutually exclusive projects: (a) At an interest rate of 25%, which project would you recommend choosing?(b) Compute the area of negative project balance, discounted payback period, and area of positive project balance for each project. Which project isexposed to a higher risk of loss if either project terminates at the end ofyear 2?arrow_forwardConsider the following two mutually exclusive investment projects: Salvage values represent the net proceeds (after tax) from the disposal of assets if they are sold at the end of the year listed. Both projects will be available (and can be repeated) with the same costs and salvage values for an indefinite period.(a) With an infinite planning horizon, which project is a better choice atMARR= 12%?(b) With a 10-year planning horizon, which project is a better choice atMARR= 12%?arrow_forwardCT Corp. is considering two mutually exclusive projects. Both require an initial investment of P120,000 at t = 0. Project X has an expected life of 2 years with after-tax cash inflows of P67,000 and P75,000 at the end of Years 1 and 2, respectively. In addition, Project X can be repeated at the end of Year 2 with no changes in its cash flows. Project Y has an expected life of 4 years with after-tax cash inflows of P38,500 at the end of each of the next 4 years. Each project has a WACC of 8%. Listed below are the requirements for this data set: Using the replacement chain approach, how much is the NPV of Project X? (Round the final answer to the nearest peso. Use the "NPV formula" in excel for exact computation. Otherwise, answer based on rounded pv factors will also be accepted.) Which of the two projects will be more profitable considering the replacement chain approach on the NPV of Project X? Using the equivalent annuity approach, what is the equivalent annuity of Project Y?…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education
Break Even Analysis (BEP); Author: Tutorials Point (India) Ltd.;https://www.youtube.com/watch?v=wOEkc3O_Q_Y;License: Standard YouTube License, CC-BY
Cost Volume Profit Analysis (CVP): calculating the Break Even Point; Author: Edspira;https://www.youtube.com/watch?v=Nw2IioaF6Lc;License: Standard Youtube License