Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9780078024108
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

Question
Book Icon
Chapter 5.S, Problem 9P

a)

Summary Introduction

To draw: A decision tree for the given problem.

Introduction:

Decision tree is one of the methods used in decision-making process. It would graphically represent the available alternatives and states of nature. It would also mention the payoffs and probabilities of the alternatives. It helps to choose the best alternative that would give the best result among the alternatives.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Three decision alternatives:

  • 1st construct small stamping plant
  • 2nd construct medium stamping plant
  • 3rd construct stamping plant

Each decision has demand:

  • Low demand which have 20% probability
  • Low demand which have 80% probability
  • If firm build small facility and demand turn out to be low than NPV is $42,000,000
  • If firm build small facility and demand turn out to be high than either subcontract or expand greatly, if sub contract than NPV is $42,000,000 and if expand greatly than $48,000,000.
  • If firm build medium facility and demand turn out to be low than NPV is $22,000,000.
  • If firm build medium facility and demand turn out to be high than either it do nothing or expand, if sub contract than NPV is $46,000,000 and if expand greatly than $50,000,000.
  • If firm build large facility and demand turn out to be low than NPV is -$20,000,000.
  • If firm build large facility and demand turn out to be high than NPV is $72,000,000.

As per given information, construct the decision tree:

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 5.S, Problem 9P , additional homework tip  1

Now, calculate the value of payoff and monetary value in decision tree:

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 5.S, Problem 9P , additional homework tip  2

Analysis the decision from right to left:

  • In the decision tree, there are two decisions making; first decision is between small, medium and large and second decision is between high demand of small and medium build facilities.
  • If small facilities build with high demand then select expand greatly because the payoff of expand greatly is higher than subcontract. The payoff of expand greatly is $48,000,000 and place double slash (reject) on subcontract.
  • If large facility build with high demand then select expand, because the payoff of expand greatly is higher than do nothing. The payoff of expand is $50,000,000 place double slash (reject) on do nothing.

Calculate the product of the chance probabilities and their respective payoffs for the remaining branches:

  • If small facility build:

Lowdemand=(Probability×NPVsmall,low)=(20%×$42,000,000)=$8,400,000

Highdemand=(Probability×NPVsmall,high)=(80%×$48,000,000)=$38,400,000

  • If medium facility IS build:

Lowdemand=(Probability×NPVmedium,low)=(20%×$22,000,000)=$4,400,000

Highdemand=(Probability×NPVmedium,high)=(80%×$50,000,000)=$40,000,000

  • If large facility is build:

Lowdemand=(Probability×NPVlarge,low)=(20%×$20,000,000)=$4,000,000

Highdemand=(Probability×NPVmedium,high)=(80%×$72,000,000)=$57,600,000

Calculation of the expected value in each alternative:

  • If small facility build

Expectedvalue=(Lowdemandpayoff+highdemandpayoff)=($8,400,000+$38,400,000)=$46,800,000

  • If medium facility build

Expectedvalue=(Lowdemandpayoff+highdemandpayoff)=($4,400,000+$40,400,000)=$44,400,000

  • If large facility build

Expectedvalue=(Lowdemandpayoff+highdemandpayoff)=($4,00,000+$57,600,000)=$53,600,000

Here, it is obtained that large facility build have higher expected value, hence it should be selected. And small and medium facilities have to be rejected.

b)

Summary Introduction

To determine: Maximin alternatives

Introduction:

Maximin is the decision making method which is used to make decision under uncertainty. This method will find an alternative that maximizes the minimum outcome of every alternative or we can say that calculating the minimum outcome within the each alternative.

b)

Expert Solution
Check Mark

Answer to Problem 9P

To suitable option is to build a small facility.

Explanation of Solution

Determine the worst possible alternatives from the given demand:

As definition stated above, Maximim is the selection from the best of the worst possible payoff for each alternatives.

AlternativeNext Year’s DemandWorst PayoffDecision
Low High
Small $42,000,000.00 $48,000,000.00 $42,000,000.00 Best of the Worst
Medium $22,000,000.00 $50,000,000.00 $22,000,000.00
Large -$20,000,000.00 $72,000,000.00 -$20,000,000.00

Hence, the best decision according to Maximin decision is to select a small medium facility.

c)

Summary Introduction

To determine: Expected value of perfect information (EVPI) and interpret it.

Expected value of perfect information: It is the rate that a person is willing to pay to gain access to perfect information. A common area which uses expected value of perfect information is the healthcare economy. This value tries to evaluate the expected cost of the uncertainty, which can be interpreted as the expected value of perfect information

The expected value of perfect information can be calculated by using below given formula:

EVPI=ExpectedvaluewithperfectinformationMaximum EMV

c)

Expert Solution
Check Mark

Answer to Problem 9P

Theexpected value of perfect information is $12,400,000.

Explanation of Solution

Calculate the expected value with perfection information or Expected payoff under certainty:

EVwPI=Max(Alternativepayoff)×Probabilitystate of nature =(42,000,000×20%)+($72,000,000×80%)=$66,000,000

Calculate the expected value with perfect information:

EVPI=ExpectedvaluewithperfectinformationMaximum EMV=$66,000,000$53,600,000=$12,400,000

Therefore, EVPI is $12,400,000.

d)

Summary Introduction

To determine: The sensitive analysis on P (high).

Introduction

Decision table is formats or visual representations were data is expressed arranged, determined and calculated to make a effective decision making. A decision table is a tabular representation that is used to analyze decision alternatives and states of nature.

d)

Expert Solution
Check Mark

Explanation of Solution

Explanation

Here we draw each alternative to P (high), low demand should be on the left hand side and high demand value on the right hand side:

Next Year’s Demand
Alternative Low High
Small $42,000,000.00 $48,000,000.00
Medium $22,000,000.00 $50,000,000.00
Large -$20,000,000.00 $72,000,000.00

Graph plot:

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 5.S, Problem 9P , additional homework tip  3

From the above graph, we can determine the value of P (high) where each alternative are optimal.

From the graph, we can obtain that small build facility is best option, because of higher expected value. For low value of P(high) while for higher and intermediate value of P(high) large is the best option.

Calculate the range needed to determine upper part of line intersects:

For each line, b is the slope of the line and x = P(High). The slope of each line Right hand valueLefthand value .

Determination of equation:

Small build facility = 42+6P (because high demand $48 million which is subtracted with low demand value $42 million)

Large build facility =-20+92P (because high demand $72million which is subtracted with low demand value -$20million)

Determination of intersection between small and large

42 + 6P=20 + 92P6P – 92P = 20 – 4286P = 62= 6286=0.7209

Hence, the intersection between small and large is 0.7209.

Therefore, optimal range can be derived as:

Small:  P (High) = 0 to < .7209

Large: P (High) > .7209 to 1.00

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A firm must decide whether to construct a small, medium, or large stamping plant. A consultant’sreport indicates a .20 probability that demand will be low and an .80 probability that demand willbe high.If the firm builds a small facility and demand turns out to be low, the net present value will be$42 million. If demand turns out to be high, the firm can either subcontract and realize the net present value of $42 million or expand greatly for a net present value of $48 million.The firm could build a medium-size facility as a hedge: If demand turns out to be low, its netpresent value is estimated at $22 million; if demand turns out to be high, the firm could do nothingand realize a net present value of $46 million, or it could expand and realize a net present value of$50 million.If the firm builds a large facility and demand is low, the net present value will be – $20 million,whereas high demand will result in a net present value of $72 million.a. Analyze this problem using a decision…
A firm must decide whether to construct a small, medium or large stamping plant. A consultant’s report indicates a 0.20 probability that demand will be low and 0.80 that demand will be high. If the firm builds a small facility and demand turns out to be low, the Net Present Value (NPV) willbe $42M. If demand turns out to be high, the firm can either subcontract and realize the NPV of $42M orexpand greatly for a Net Present Value of $48M. The firm could build a medium size facility as a hedge: if demand turns out to be low, its NPV is estimated at $22M; if demand turns out to be high, the firm could do nothing and realize a NPV of $46M, or could expand and realize a NPV of $50M. If the firm builds a large facility and demand is low, the NPV will be ($20M), whereas high demand will result in a NPV of $72M.  Compute the EVPI  *
A manager is trying to decide whether to build a small,medium, or large facility. Demand can be low, average,or high, with the estimated probabilities being 0.25, 0.40,and 0.35, respectively.A small facility is expected to earn an after-tax net pres-ent value of just $18,000 if demand is low. If demand isaverage, the small facility is expected to earn $75,000; it canbe increased to medium size to earn a net present value of$60,000. If demand is high, the small facility is expected to earn $75,000 and can be expanded to medium size to earn$60,000 or to large size to earn $125,000.A medium-sized facility is expected to lose an estimated$25,000 if demand is low and earn $140,000 if demand isaverage. If demand is high, the medium-sized facility isexpected to earn a net present value of $150,000; it can beexpanded to a large size for a net payoff of $145,000.If a large facility is built and demand is high, earningsare expected to be $220,000. If demand is average for thelarge facility, the…

Chapter 5 Solutions

Operations Management (McGraw-Hill Series in Operations and Decision Sciences)

Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning