Question
Book Icon
Chapter 6, Problem 14P

a.

Summary Introduction

Interpretation: The current inventory level of the cell is to be computed.

Concept Introduction: Value Stream Mapping is one of the lean management techniques used to analyze, design the process, and control the flow of information and materials in the facility to make sure that the end product has been delivered to the customer.

b.

Summary Introduction

Interpretation: The takt time required in the manufacturing cell is to be computed.

Concept Introduction: Kanban system is a concept implemented under the Lean concepts and Just in time management system. It is useful in achieving the manufacturing efficiency of any organization.

c.

Summary Introduction

Interpretation: The production lead time required at each process in the cell of manufacturing is to be calculated.

Concept Introduction: Production lead time is the duration of process which begins at the time the customer places the order and ends with the time the customer order fulfills and is completed.

d.

Summary Introduction

Interpretation: The total processing time is to be calculated by summing up all the processing steps involved in this manufacturing cell.

Concept Introduction: Production lead time is the duration of process which begins at the time the customer places the order and ends with the time the customer order fulfills and is completed.

e.

Summary Introduction

Interpretation: The total holding capacity of the manufacturing cell is to be calculated.

Concept Introduction: Production lead time is the duration of process which begins at the time the customer places the order and ends with the time the customer order fulfills and is completed.

Blurred answer
Students have asked these similar questions
What is used to indicate suggested changes in a process that may lead to improvements in a value stream?
Meritor is so pleased with the outcome from previous suggestions that the consultants are invited back for more work. The consultants now suggest a more complete robotic automation of the making of muffler assemblies and also a reduction in container size to eight per container. Meritor implements these suggestions and the result is that the muffler assembly fabrication cell now averages approximately 32 assemblies per hour, and the catalytic converter assembly cell can now respond to an order for a batch of catalytic converters in one hour. The safety stock remains at 12.5 percent. How many kanban cards are needed? (Answer in Appendix D)
What are the first two areas that should be identified in value stream mapping?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.