Here is a partial work breakdown structure for a wedding. Use the method described in the Snapshot from Practice 6.i: The Yellow Sticky Approach to create a network for this project.

Note: Do not include summary tasks in the network (i.e., 1.3, Ceremony, is a summary task; 1.2, Marriage license, is not a summary task). Do not consider who would be doing the task in building the network. For example, do not arrange “hiring a band” to occur after “florist” because the same person is responsible for doing both tasks. Focus only on technical dependencies between tasks.

Hint: Start with the last activity (wedding reception), and work your way back to the start of the project. Build the logical sequence of tasks by asking the following question: In order to have or do this, what must be accomplished immediately before this? Once completed, check forward in time by asking this question: Is this task(s) the only thing that is needed immediately before the start of the next task?

Work Breakdown Structure

Wedding project

1.1 Decide on date

1.2 Marriage license

1.3 Ceremony

1.3.1 Rent church

1.3.2 Florist

1.3.3 Create/print programs

1.3.4 Hire photographer

1.3.5 Wedding ceremony

1.4 Guests

1.4.1 Develop guest list

1.4.2 Order invitations

1.4.3 Address and mail invitations

1.4.4 Track RSVPs

1.5 Reception

1.5.1 Reserve reception hail

1.5.2 Food and beverage

1.5.2.1 Choose caterer

1.5.2.2 Decide on menu

1.5.2.3 Make final order

1.5.3 Hire DJ

1.5.4 Decorate reception hail

1.5.5 Wedding reception

Blurred answer
Students have asked these similar questions
The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?
Topic: Project  management   Please after reading activity use this work breakdown struction below to input in gantt chart, minimum 10 task  WORK BREAKDOWN STRUCTURE Main objective : training for aquaponicsIdentify 30 entrepreneurs and 10 teachers5 day work shop, practical and theoretical  1st Phase: Identification of entrepreneurs, teachers and experts  -    Social Media and Radio Announcements -    Registration -    Locate interested experts to lecture  2nd Phase: Preparation of Training Area -    Identify proper training area -    Set up facility for training -    Contact caterers for subsequent training.-    Formulate 5 day Curriculum -    3rd Phase: Training -    Lectures -    Practical Lessons -    Testing at end of training days.4th Closure: -    Award Ceremony for high performance particpants-    Gifting of Certificates -    Ending Ceremony. 5.    Create a partial project schedule using a Gantt Chart (with a minimum of 10 tasks).
To Finnd  A) Draw Project Network - Activity On Arrow (AOA) B) CPM Calculations: – Forward Pass        C) CPM Calculations: – Backward Pass    D)CPM Calculations: – Float Calculations E) Trace Critical Activities and Critical Path.N Note:Each Part Should Be Solved Solved on separate sheet and Diagram.See Attached Picture For Details

Chapter 6 Solutions

PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS

Knowledge Booster
Background pattern image
Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Text book image
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Text book image
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Text book image
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Text book image
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Text book image
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY