You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.
How long will this project take? How sensitive is the network schedule? Calculate the free slack and total slack for all noncritical activities.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?
Prepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities).
Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to
complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project
(Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a
house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your
time estimates and the correctness of your analysis.
UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.
A group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.
Chapter 6 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 6 - How does the WBS differ from the project network?Ch. 6 - How are WBS and project networks linked?Ch. 6 - Why bother creating a WBS? Why not go straight to...Ch. 6 - Why is slack important to the project manager?Ch. 6 - What is the difference between free slack and...Ch. 6 - Why are lags used in developing project networks?Ch. 6 - What is a hammock activity, and when is it used?Ch. 6 - Here is a partial work breakdown structure for a...Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...
Ch. 6 - Draw a project network from the following...Ch. 6 - Draw a project network from the following...Ch. 6 - From the following information, develop an AON...Ch. 6 - The project information for the custom order...Ch. 6 - You have signed a contract to build a garage for...Ch. 6 - You are creating a customer database for the...Ch. 6 - K. Nelson, project manager of Print Software....Ch. 6 - A large Southeast city is requesting federal...Ch. 6 - You are creating a customer database for the...Ch. 6 - You are completing a group term paper. Given the...Ch. 6 - You are managing a product upgrade project for...Ch. 6 - You are creating a database for the Oklahoma City...Ch. 6 - The planning department of an electronics firm has...Ch. 6 - Using Microsoft Project, set up the network and...Ch. 6 - The optical disk project team has started...Ch. 6 - From the following information, compute the early,...Ch. 6 - Given the following information, compute the...Ch. 6 - Given the information in the following lag...Ch. 6 - Given the network below, compute the early, late,...Ch. 6 - The CyClon project team has started gathering...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - Advantage Energy Technology Data Center...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The GE Company is preparing a bid to build the new...Ch. 6 - The G&E Company is preparing a bid to build the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- A project has the following activities, precedence relationships, and activity duration. Draw the AOA project network. How long would it take to complete this project? What is the length of the critical path?arrow_forwardI'm having trouble creating a project network diagram. I don't understand calculating the time and total slack for each activity using forward pass and backward pass. Please explain how to draw and calculate a project network diagram.arrow_forwardConstruct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.arrow_forward
- You may need to use the appropriate technology to answer this question. Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1. Start Activity A B C D E F G A H The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity. Variance 1.0 0.4 1.3 0.9 0.2 0.7 0.5 B 0.9 E 1 D C 4 F G 3 H 7 Finish 4 (a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.) The expected project completion is weeks from May 1 with a critical path of (b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.) weeks from May 1.arrow_forwardFrom the following information, develop an AON project network. Complete theforward and backward pass, compute activity slack, and identify the critical path.How many days will the project take?arrow_forwardDevelop the network activity (AON) chart and identify the critical path for a project based on the table below. Draw the activity network as a Gantt chart using MS Project. What is the expected duration of the project? Please use MS Project and submit the answer .arrow_forward
- A group of developers is building a new shopping center.A consultant for the developers has constructed theCPM/PERT network below and assigned activity times inweeks. Determine the earliest start and finish times, lateststart and finish times, activity slack, critical path, and duration for the project.arrow_forwardA project's activities must be completed in the sequence indicated below. Activity Immediately Preceding Activity Duration in Weeks A - 3 B - 20 C - 15 D - 10 E - 5 F A 4 G D 3 H D, E 10 I F 3 J B 10 K G, H 7 L B, I 5 The project ends with the intersection of activities: C, J, K and L 1- Use CPM to construct (Draw) the project Network and find the critical path. 2- How long is the project expected to takearrow_forwardA project consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 4 C A, B 7 D A, B 3 E C, D 5 F C, D 6 G E, F 4 Draw the project network diagram. Calculate each activity's ES, EF, LS, LF, and Slack using the project activity nodes on the project network diagram. What is the project completion time? Identify the critical patharrow_forward
- Given the following network, What is the critical path? How long will it take to complete this project? The duration, in days, follows the letter of each activity. Can activity B be delayed without delaying the completion of the project? If so, how many days?arrow_forwardA project schedule has the following characteristics: explain all the step to construct the network and find critical patharrow_forwardGiven the following network, compute the early, late, and slack time for each activity. Clearly identify the critical path.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY