Textbook Question
Chapter 6, Problem 2P
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of
a. In order of most following tasks Tiebreaker: greatest positional weight.
b. In order of greatest positional weight Tiebreaker: most following tasks.
c. What is the efficiency?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An electricity power plant was redesigned so that the old system consisting of a
single large display screen which could be seen by all of a team of three operators
was replaced by individual workstation screens for operators. This worked well
until there was a problem which resulted in dangerous gases being released. The
team of operators had great difficulty in finding the source of the problem and
deciding what to do.
Because they no longer have access to all the information, they have to spend
time explicitly co-ordinating their understanding of the situation by talking to
each other. Under the old system, the knowledge would be shared – one operator
would know what was happening with another’s area of the plant without explicit
communication. Although the team’s individual responsibilities would still have
been clearly divided, the knowledge of the system would be shared.
How could the new system of individual workstations be modified to make better use of
distributed cognition?
3-
An organization plans to have a manufacturing unit after eight years and two new offices after nine years. They plan accordingly so that there can be sufficient funds for achieving this plan. Which type of plan is being discussed?
a.
Intermediate
b.
Long-term
c.
Short-term
d.
Single use
The XYZ company produces all type of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long office hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks;
Task
Time (min)
Immediate predecessor
A
4
-
B
7
-
C
6
A, B
D
5
C
E
6
D
F
7
E
G
8
E
I
6
F, G
a) Draw a precedence diagram of this operation
b) What is the cycle time for this operation?
c) What is the theoretical minimum number of workstations?
d) Assign tasks to the workstations
e) What is the idle time per cycle?
f) What is the efficiency of the assembly line?
Chapter 6 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQ
Ch. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manager must decide which type of machine to buy, A, B, or C. Machines costs are as follows: Machine Cost A $40,000 B $30,000 C $80,000 Product forecast, processing times on the machines, and setup times are as follows: Processing Time Per Unit (minutes) Product Annual Demand A B C Setup Times (minutes) Production Lots (units) 1 16,000 3 4 2 20 200 2 12,000 4 5 3 35 100 3 6,000 5 6 3 60 50 4 30,000 2 4 1 15 500 Machines operate 10 hours a day, 250 days a year. The manager wants to have a capacity cushion of 10%. a. Assume that only purchasing costs are being considered. Which machines would have the lowest total cost, and how many of that machines would be needed? b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $11 each, B machines have an hourly operating cost of $10 each, and C machines have an hourly operating cost of $12 each. Which alternative would…arrow_forwardIn a job shop, effective capacity is only 88 percent of design capacity, and actual output is 69 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs =( ) (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs =( ) (round to whole number)arrow_forward2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correctarrow_forward
- A Manager’s Woes Kyle Peschken has been a manager for the discount store Zelmart for the past two years. It’s time for his annual performance review, and Kyle would like to make a big impression on the corporate staff. Walking through the store, he makes a mental note of which departments need to be straightened, which ones need to be reorganized, and which employees he’d like to schedule during the week of his review. And then he sees it—blocking the aisles, creating commotion, and looking very unprofessional—the long line in the electronics department. It’s time to confront Chris, the sales clerk. “Chris, what’s the holdup here?” “I’mwaiting for a manager to approve this $120 check. And then I have to show this lady a digital camera from the display cabinet. She’s been waiting half an hour, and then . . . .” “Alright Chris . . . I can help out for a while . . .Two hours later, Kyle exited the electronics department disheartened. That’s no way for a store manager to spend his…arrow_forwardA linear programming computer package is needed. EZ-Windows, Inc., manufactures replacement windows for the home remodeling business. In January, the company produced 15,000 windows and ended the month with 9,000 windows in inventory. EZ-Windows' management team would like to develop a production schedule for the next three months. A smooth production schedule is obviously desirable because it maintains the current workforce and provides a similar month-to-month operation. However, given the sales forecasts, the production capacities, and the storage capabilities as shown, the management team does not think a smooth production schedule with the same production quantity each month possible. February March April Sales forecast 15,000 16,500 20,000 Production capacity 14,000 14,000 18,000 Storage capacity 6,000 6,000 6,000 The company's cost accounting department estimates that increasing production by one window from one month to the next will increase total costs by $1.00…arrow_forwardA linear programming computer package is needed. EZ-Windows, Inc., manufactures replacement windows for the home remodeling business. In January, the company produced 15,000 windows and ended the month with 9,000 windows in inventory. EZ-Windows' management team would like to develop a production schedule for the next three months. A smooth production schedule is obviously desirable because it maintains the current workforce and provides a similar month-to-month operation. However, given the sales forecasts, the production capacities, and the storage capabilities as shown, the management team does not think a smooth production schedule with the same production quantity each month possible. February March April Sales forecast 15,000 16,500 20,000 Production capacity 14,000 14,000 18,000 Storage capacity 6,000 6,000 6,000 The company's cost accounting department estimates that increasing production by one window from one month to the next will increase total costs by $1.00…arrow_forward
- A linear programming computer package is needed. EZ-Windows, Inc., manufactures replacement windows for the home remodeling business. In January, the company produced 15,000 windows and ended the month with 9,000 windows in inventory. EZ-Windows' management team would like to develop a production schedule for the next three months. A smooth production schedule is obviously desirable because it maintains the current workforce and provides a similar month-to-month operation. However, given the sales forecasts, the production capacities, and the storage capabilities as shown, the management team does not think a smooth production schedule with the same production quantity each month possible. February March April Sales forecast 15,000 16,500 20,000 Production capacity 14,000 14,000 18,000 Storage capacity 6,000 6,000 6,000 The company's cost accounting department estimates that increasing production by one window from one month to the next will increase total costs by $1.00…arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A $ 60,000 B $ 50,000 C $ 60,000 Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Product AnnualDemand A B C 1 16,000 3 4 4 2 10,000 6 5 1 3 15,000 1 3 6 4 17,000 5 3 4 Click here for the Excel Data File a. Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type. The machines will operate 10 hours a day, 240 days a year. (Enter total processing times as whole numbers. Round up machine quantities to the next higher whole number. Compute total purchasing costs using these rounded machine quantities. Enter the resulting total purchasing cost as a whole…arrow_forwardUse excel to show formulas 1. A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?arrow_forward
- A TV factory plans to add production lines for its new product and plans to produce as many as 200 units per hour. The production process, production time, and the production process to continue the next production process are described in the table below: (1 day = 8 working hours) Production Process Production Time (s) The production process that follows the next production according to the list below A 12 - B 15 A C 8 A D 5 B,C E 20 D Based on the data above. a. What is the cycle time for the production of the new product? (note: in seconds)b. What is the minimum number of workstations?arrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A $ 60,000 B $ 50,000 C $ 60,000 Product forecasts and processing times on the machines are as follows: PROCCESSING TIME PER UNIT (minutes) Product AnnualDemand A B C 1 16,000 3 4 4 2 10,000 6 5 1 3 15,000 1 3 6 4 17,000 5 3 4 a. Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type. The machines will operate 10 hours a day, 240 days a year. (Enter total processing times as whole numbers. Round up machine quantities to the next higher whole number. Compute total purchasing costs using these rounded machine quantities. Enter the resulting total purchasing cost as a whole number. Omit the "$" sign.) Total…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY