Chapter 6, Problem 4DQ
Explanation of Solution
Difference between estimating activity durations and estimating the effort required to perform an activity:
- Duration is the time taken to complete an activity or task in a project. Activity duration is affected by the individual resources involved in it.
- The duration and effort are different to each other.
- Effort is the resource estimate and the hard work required to complete an activity. Estimated activity duration relates to time estimate...
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Project Management Tech Solutions is a company which develops software solutions for clients. Each project is associated with only one client. A minimum of two staff members must be allocated to each project. A staff member can work on many projects at the same time.
Contract staff can be hired for certain projects illustrate with a diagram how this can be implemented with generalisation
How many different types of metrics are used in software upkeep?
How accurate is a certain method when it comes to calculating how much an
engineering project will cost?
Chapter 6 Solutions
Mindtap For Schwalbe's Information Technology Project Management, 1 Term Printed Access Card
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Task Effort (person-days) Duration(days) Dependencies T1 5 5 Â T2 12 24 T1 T3 5 10 Â T4 15 5 T2 T5 10 10 T3 What is the total effort ?What will be the shortest duration of the project, if you can have multiple people working on it ?arrow_forwardDraw a Gantt chart for the tasks shown inProblem and Exercise 3-26.arrow_forwardIdentify significant constraints on testing, such as test-item availability, testing-resource availability, and deadlines.arrow_forward
- Computer science: A work breakdown structure is what? What resources and equipment are utilised to create one?arrow_forwardProfessional and Scientific Staff Management (PSSM) is a unique type of temporary staffing agency. Many organizations today hire highly skilled technical employees on a short-term, temporary basis to assist with special projects or to provide a needed technical skill. PSSM negotiates contracts with its client companies in which it agrees to provide temporary staff in specific job categories for a specified cost. For example, PSSM has a contract with an oil and gas exploration company in which it agrees to supply geologists with at least a master’s degree for $5,000 per week. PSSM has contracts with a wide range of companies and can place almost any type of professional or scientific staff members, from computer programmers to geologists to astrophysicists. When a PSSM client company determines that it will need a temporary professional or scientific employee, it issues a staffing request against the contract it had previously negotiated with PSSM. When PSSM’s contract manager receives…arrow_forwardProfessional and Scientific Staff Management (PSSM) is a unique type of temporary staffing agency. Many organizations today hire highly skilled technical employees on a short-term, temporary basis to assist with special projects or to provide a needed technical skill. PSSM negotiates contracts with its client companies in which it agrees to provide temporary staff in specific job categories for a specified cost. For example, PSSM has a contract with an oil and gas exploration company in which it agrees to supply geologists with at least a master’s degree for $5,000 per week. PSSM has contracts with a wide range of companies and can place almost any type of professional or scientific staff members, from computer programmers to geologists to astrophysicists. When a PSSM client company determines that it will need a temporary professional or scientific employee, it issues a staffing request against the contract it had previously negotiated with PSSM. When PSSM’s contract manager receives…arrow_forward
- Task Effort (person-days) Duration(days) Dependencies T1 5 5  T2 11 24 T1 T3 5 10  T4 15 5 T2 T5 10 10 T3 What is the total effort ?What will be the shortest duration of the project, if you can have multiple people working on it ?  a. Effort: 44, Duration: 34 b. Effort: 34, Duration: 34 c. Effort:46, Duration: 46 d. Effort: 46, Duration: 34 e. Effort: 45, Duration: 34arrow_forwardDonation is an act of compassion, where an individual who has financially more than enough of what he or she needs contributes a part of his or her surplus income for the fulfilment of the needs of those who are less capable. The majority of NGOs has experienced difficulties in getting funds or other required things. Getting donor is a very hard task, and sometime dealing with some donor’s conditions can be a big challenge for NGOs to fulfil it. This donation management system will help NGOs to find donors easily. This system has three modules namely, Administration, NGO and Donor. Admin can login using credentials and manage the request raised by NGO by approving or rejecting it. Approval will be done after verifying the NGO documents uploaded by NGO. Admin will get the report of NGOs who get donations. NGOs can register and raise request by uploading NGO documents. Once admin gets the approval, they can login using credentials. NGO can raise request in need to the various registered…arrow_forwardSystem development involves multiple processes. Explain phase goals.arrow_forward
- In software upkeep, what kind of metrics are often employed?arrow_forwardExplain the concept of task deadline planning and describe the information required for this kind of planning.arrow_forwardThe method of managing projects involving software development is slightly distinct from the process of managing other sorts of projects.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningEnhanced Discovering Computers 2017 (Shelly Cashm...Computer ScienceISBN:9781305657458Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. CampbellPublisher:Cengage Learning
- Principles of Information Security (MindTap Cours...Computer ScienceISBN:9781337102063Author:Michael E. Whitman, Herbert J. MattordPublisher:Cengage LearningOperations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Enhanced Discovering Computers 2017 (Shelly Cashm...
Computer Science
ISBN:9781305657458
Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:Cengage Learning
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole