Textbook Question
Chapter 6, Problem 8P
A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:
a. Construct the precedence diagram.
b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.
c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.
d. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.
A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:a. Construct the precedence diagram.b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.d. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?
TaskImmediatePredecessorTaskTimea — 0.5b a 1.4c a 1.2d a 0.7e b, c 0.5f d 1.0g e 0.4h g 0.3i f 0.5j e, i 0.8k h, j 0.9m k 0.3
The Action Toy Company has decided to manufacture a new train set, the
production of which is broken into six steps. The demand for the train is
4,600 units per 40-hour workweek:
Task
A
BCDEF
C
Performance Time
(seconds)
22
30
12
15
12
27
Predecessors
A
A
A
B, C
D, E
This exercise only contains part a.
a) The correct precedence diagram for the assembly line is presented in
C
Fig. 1
Fig. 2
Fig. 3
B
E
Chapter 6 Solutions
OPERATIONS MANAGEMENT (LL) W/CONNECT
Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - Prob. 2.1RQCh. 6.3 - Prob. 2.2RQ
Ch. 6.3 - Prob. 3.1RQCh. 6.3 - Prob. 3.2RQCh. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Task A BCDEF Performance Time (seconds) 20 30 14 14 10 30 Predecessors A A A B, C D, E This exercise only contains part a. a) The correct precedence diagram for the assembly line is presented in CBD Fig. 1 A Fig. 2 Fig. 3 B B E B N o 勺 Narrow_forwardFrancis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in th following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME (MINUTES) IMMEDIATE PREDECESSOR rint TASK A 2.0 B 2.0 3.0 1.0 А, В, с 3.0 2.0 G 3.0 b. What is the workstation cycle time required to produce 15 units per hour? (Round your answer to 1 decimal place.) Workstation cycle time minutes d. Balance the line to use the fewest possible workstations to meet the cycle time found in part b. Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part b? (Round your answer to 1 decimal place.)arrow_forwardA shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following: a- What is the cycle time and what s the minimum number of workstations required b- Construct the precedence diagram. c- Assign tasks according to the most following tasks rule.. d- what is the efficiency of such line Immediate Task Task Predecessor Time a 0.5 a 1.4 a 1.2 a 0.7 0.5 f 1.0 0.4 03 05 e i 0.8 h j 0.9 k 0.3arrow_forward
- A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following: b.) Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule. c.) Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule. d.) Compute the efficiency level for each rule. Which one yields the better set of assignments in this instance?arrow_forwardA dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table. (a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.arrow_forwardFrancis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forward
- An assembly line must be designed to produce 40 containers per hour. The following data give the necessary information Table 1 TASK IMMEDIATE PREDECESSOR TASK TIME (sec) A None 60 B A 12 C B 35 D A 55 E D 10 F E 50 G F, C 5 Draw the precedence diagram. Compute the cycle time (in seconds) to achieve the desired output rate. What is the theoretical minimum number of stations? Assign the tasks to the workstation? What is the efficiency of the line? Calculate the idle timearrow_forwardA production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).a) Which operation is the bottleneck?b) What is the bottleneck time?c) What is the throughput time of the overall system?d) If the firm operates 8 hours per day, 20 days per month, whatis the monthly capacity of the manufacturing process?arrow_forwardAssembly Line Problem A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the following table. Task Immediate Predecessor Task(s) Task Time (minutes) a --- 0.5 b a 1.4 c a 1.2 d a 0.7 e b,c 0.5 f d g e 0.4 h g 0.3 i F 0.5 j e, I 0.8 k h, j 0.9 l k 0.3 d)Compute the efficiency of the assembly linearrow_forward
- As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. b. Draw the precedence diagram for the problem that you set up in part “a” above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forward3. SCM301 Warehouse takes orders from 7 a.m. to 7 p.m. The manager wants to analyze the process and has provided the following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The order-taking step works at a maximum rate of 100 customer orders per hour. Order picking works at a maximum of 80 per hour, and packing works at 60 per hour. Customers, Take Orders 100 Customers/ hour Customer Orders, Pick Orders 80 Customers/ hour Picked Orders Pack Orders 60 Customers/ hour Wait for Shipper SCM301 Warehouse wants to figure out the following: A. What is the current maximum output of the process assuming that no one works overtime? (For your answers to these questions, assume that everyone can start working at 7 a.m.) B. How long will the picking and packing operations have to work if we have a…arrow_forwardA production schedule requires six work stations. However, there are nine work tasks to be performed to produce a unit of output. The warchouse is operated for seven days a week and three 8-hour shifts per day. The desired output per week is 1.728 units. The tasks, precedence relationships and the approximate amount of time required to carry out cach task is presented below. Use this information to answer questions 62 - 69 Task 1. Duration (min) 5.0 Immediate Preceding Task 3 4 4.5 2.0 3.0 3.5 2,3 4,5 1.5 2.5 7. 4.8 2.5 62. What is the available time for production in minutes? (a) 1260 (b) 1440 (c) 3,360 (d) 10080 63. The required cycle time for this operation is: (а) 2.58 (b) 5.83 (c) 7.25 (d) 9.42 64. Which activity or set of activities should be assigned to station 2? (a) 2 only (b) I and 2 (c) 3 only (d) 3 and 4 65. Which activity or set of activities should be assigned to station 4? (a) 3 only (b) 3 and 4 (c) 5 and 6 (d) 7 only 66. Which activity or set of activities should be…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY